Pickfords Wharf Clink Street London Southwark SE1 9DG Data via plota.co.uk

Proposal

Refurbishment of the existing building to include a single storey roof extension, an adjacent rooftop terrace and roof level plant; alterations to the existing facade, inclusive of replacement windows and additional window openings at fifth floor level; creation of a new cafe/ retail unit at ground floor (Class E); improvements to cycle access, end of journey facilities and waste storage facilities; internal improvements inclusive of a new fire-fighting core. Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
28 Apr 2026
✓
Validated
29 Apr 2026
✓
Approved
8 Oct 2026

Approved on 8 Oct 2026 · Committee - Small Sites · Last checked 8 Oct 2026

Planning committee

Decided by Southwark Planning Committee (Smaller Applications) on 7 Oct 2026.

Approved

As officers recommended.

  • Officers advised approval because the revised scheme would preserve heritage assets and manage amenity, transport and servicing impacts through conditions.
  • Residents objected mainly to noise, transport, heritage, daylight, privacy and the effects of the rooftop development.
  • The committee voted to grant permission, subject to the report and addendum conditions.
Read how the committee decided The proposal, site, officer assessment, consultation responses, committee discussion, vote and decision.

Source: Plota analysis of Southwark's committee minutes of 7 Oct 2026.

Documents 101

Statements & assessments 31

PDF PLANNING STATEMENT Planning statement · 10 Aug 2026 View ↗ PDF HERITAGE REBUTTAL REPORT Comment - Consultee · 28 Jul 2026 View ↗
PDF Commenter’s name hidden Show Comment - Contributor · 27 Jul 2026 View ↗
PDF FLOOD RISK ASSESSMENT Flood risk assessment · 28 Apr 2026 View ↗ PDF NOISE IMPACT ASSESSMENT Noise impact assessment · 28 Apr 2026 View ↗ PDF TRANSPORT ASSESSMENT Transport assessment · 28 Apr 2026 View ↗ PDF 1 ARCHAEOLOGICAL ASSESSMENT Other · 28 Apr 2026 View ↗ PDF 2 ARCHAEOLOGICAL ASSESSMENT Other · 28 Apr 2026 View ↗ PDF 3 ARCHAEOLOGICAL ASSESSMENT Other · 28 Apr 2026 View ↗ PDF HERITAGE STATEMENT Heritage statement · 28 Apr 2026 View ↗ PDF 1 DESIGN AND ACCESS STATEMENT Design and Access statement · 28 Apr 2026 View ↗ PDF 2 DESIGN AND ACCESS STATEMENT Design and Access statement · 28 Apr 2026 View ↗ PDF 3 DESIGN AND ACCESS STATEMENT Design and Access statement · 28 Apr 2026 View ↗ PDF 4 DESIGN AND ACCESS STATEMENT Design and Access statement · 28 Apr 2026 View ↗ PDF 5 DESIGN AND ACCESS STATEMENT Design and Access statement · 28 Apr 2026 View ↗ PDF 6 DESIGN AND ACCESS STATEMENT Design and Access statement · 28 Apr 2026 View ↗ PDF 7 DESIGN AND ACCESS STATEMENT Design and Access statement · 28 Apr 2026 View ↗ PDF 8 DESIGN AND ACCESS STATEMENT Design and Access statement · 28 Apr 2026 View ↗ PDF 9 DESIGN AND ACCESS STATEMENT Design and Access statement · 28 Apr 2026 View ↗ PDF 10 DESIGN AND ACCESS STATEMENT Design and Access statement · 28 Apr 2026 View ↗ PDF 11 DESIGN AND ACCESS STATEMENT Design and Access statement · 28 Apr 2026 View ↗ PDF 12 DESIGN AND ACCESS STATEMENT Design and Access statement · 28 Apr 2026 View ↗ PDF 13 DESIGN AND ACCESS STATEMENT Design and Access statement · 28 Apr 2026 View ↗ PDF 14 DESIGN AND ACCESS STATEMENT Design and Access statement · 28 Apr 2026 View ↗ PDF 15 DESIGN AND ACCESS STATEMENT Design and Access statement · 28 Apr 2026 View ↗ PDF 16 DESIGN AND ACCESS STATEMENT Design and Access statement · 28 Apr 2026 View ↗ PDF 17 DESIGN AND ACCESS STATEMENT Design and Access statement · 28 Apr 2026 View ↗ PDF 18 DESIGN AND ACCESS STATEMENT Design and Access statement · 28 Apr 2026 View ↗ PDF 19 DESIGN AND ACCESS STATEMENT Design and Access statement · 28 Apr 2026 View ↗ PDF FIRE STATEMENT Fire Statement · 28 Apr 2026 View ↗ PDF PLANNING STATEMENT Planning statement · 28 Apr 2026 View ↗

Consultation & comments 41

PDF TIME EXTENSION AGREEMENT Time Extension - Response · 23 Sept 2026 View ↗ PDF OBJECTION Comment - Contributor · 28 Jul 2026 View ↗ PDF DAYLIGHT AND SUNLIGHT REPORT REBUTTAL Comment - Consultee · 28 Jul 2026 View ↗
PDF Objector’s name hidden Show Comment - Consultee · 28 Jul 2026 View ↗
PDF OBJECTION EMAIL Comment - Contributor · 28 Jul 2026 View ↗ PDF OBJECTION LETTER DATED 24TH JULY 2026 Comment - Contributor · 24 Jul 2026 View ↗ PDF OBJECTION EMAIL Comment - Contributor · 24 Jul 2026 View ↗ PDF OBJECTION LETTER 20 JULY 2026 Comment - Contributor · 23 Jul 2026 View ↗ PDF OBJECTION EMAIL 20 JULY 2026 Comment - Contributor · 23 Jul 2026 View ↗ PDF OBJECTION LETTER 20 JULY 2026 Comment - Contributor · 23 Jul 2026 View ↗ PDF OBJECTION Comment - Contributor · 21 Jul 2026 View ↗ PDF OBJECTION Comment - Contributor · 20 Jul 2026 View ↗ PDF OBJECTION Comment - Contributor · 17 Jul 2026 View ↗ PDF OBJECTION Comment - Contributor · 16 Jul 2026 View ↗ PDF OBJECTION Comment - Contributor · 16 Jul 2026 View ↗ PDF OBJECTION Comment - Contributor · 14 Jul 2026 View ↗ PDF OBJECTION Comment - Contributor · 14 Jul 2026 View ↗ PDF FILE COPY - NEIGHBOUR NOTIFICATION+LIST Neighbour Notification List · 7 Jul 2026 View ↗
PDF Commenter’s name hidden Show Comment - Contributor · 19 Jun 2026 View ↗
PDF TIME EXTENSION RESPONSE Time Extension - Response · 19 Jun 2026 View ↗ PDF RESIDENTS REQUESTED CONDITIONS Comment - Consultee · 18 Jun 2026 View ↗ PDF OBJECTION Comment - Contributor · 21 May 2026 View ↗ PDF OBJECTION Comment - Contributor · 20 May 2026 View ↗ PDF OBJECTION Comment - Contributor · 20 May 2026 View ↗ PDF OBJECTION Comment - Contributor · 20 May 2026 View ↗ PDF OBJECTION Comment - Contributor · 20 May 2026 View ↗ PDF OBJECTION Comment - Contributor · 19 May 2026 View ↗ PDF OBJECTION Comment - Contributor · 19 May 2026 View ↗ PDF OBJECTION Comment - Contributor · 19 May 2026 View ↗ PDF OBJECTION Comment - Contributor · 19 May 2026 View ↗ PDF OBJECTION Comment - Contributor · 19 May 2026 View ↗ PDF OBJECTION Comment - Contributor · 19 May 2026 View ↗ PDF OBJECTION Comment - Contributor · 18 May 2026 View ↗ PDF OBJECTION Comment - Contributor · 17 May 2026 View ↗ PDF OBJECTION Comment - Contributor · 17 May 2026 View ↗ PDF OBJECTION Comment - Contributor · 16 May 2026 View ↗ PDF HISTORIC ENGLAND Comment - Consultee · 13 May 2026 View ↗ PDF OBJECTION Comment - Contributor · 13 May 2026 View ↗ PDF OBJECTION Comment - Contributor · 13 May 2026 View ↗ PDF OBJECTION LETTER DATED 11.05.2026 Comment - Contributor · 12 May 2026 View ↗ PDF FILE COPY - NEIGHBOUR NOTIFICATION+LIST Neighbour Notification List · 29 Apr 2026 View ↗

All documents on the council site ↗

Site constraints 18

Scheduled monument: Remains of Winchester Palace, Clink Street and waterfront
Scheduled monument consent is needed for any work to it, separate from planning permission.
Nationally important archaeology protected by the Secretary of State. Work that affects the monument or its setting is rarely permitted.
Historic England ↗
11 listed buildings within 150 m
Nearest: Remains of Winchester Palace, 22 m away · 1 Grade I, 1 Grade II*, 7 Grade II
The site itself is not listed. Listed building consent is needed for work that affects the special interest of a listed building, inside or out, on top of planning permission. Setting can be a consideration for buildings nearby; there is no fixed radius.
Show all 11 with distances
Flood zone 3, rivers and sea
High chance: a 1 in 100 or greater annual chance from rivers, or 1 in 200 from the sea. Any development here needs a flood risk assessment. Defences are not counted.
The Environment Agency flood map for planning. Homes in zone 3 must also pass the sequential test. Surface water flooding is a separate map.
Flood map ↗
Borough High Street conservation area
Demolition needs planning permission and permitted development is restricted.
The council must give weight to preserving or enhancing the area's character and appearance. Not every council has published its boundaries as open data.
Council document ↗
3 Article 4 directions
Bankside and Borough District Town Centre · Old Thameside Inn · Central Activities Zone. Named permitted development rights are withdrawn here.
An Article 4 direction withdraws particular permitted development rights, so work that would normally need no application needs one here. Not every council has published its directions.
National infrastructure project: Thames Tideway Tunnel
The site is inside the project boundary. Waste water treatment, decided. The project page says whether consent was granted. Also within 2 km: London Strategic Heat Main Project (at pre-application, 89 m).
Nationally significant infrastructure projects (power stations, electricity lines, pipelines, major roads and railways, harbours, airports and reservoirs) are consented by a Secretary of State under the Planning Act 2008, after an examination by the Planning Inspectorate, rather than by the council. The boundary is the one the Inspectorate consults on and can change as the scheme does. Projects are shown within 2 km of the site.
Planning Inspectorate project page ↗
Archaeological priority area
An assessment or field evaluation may be asked for before ground works.
The council or Historic England considers archaeology likely here. A desk-based assessment, and sometimes trial trenching, can be asked for with the application.
Air quality management area: Southwark AQMA
The council has declared the area as failing an air quality objective.
Schemes that add traffic, parking or combustion plant are assessed against the area's action plan and may need an air quality assessment.
Council record ↗
Thames Path 13 m away
Matters where it crosses or adjoins the site; the route and its margin are protected.
Town centre: Bankside and The Borough
A designated centre in the London Plan.
Shops, services and active frontages are protected in centres, and main town centre uses are steered here first.
Central activities zone
The core of central London in the London Plan.
Offices, culture and the other strategic functions of the centre take priority over new housing here.
Opportunity area
Where the London Plan expects significant growth.
Boundaries are indicative and the borough holds the detailed plan.
Also on the record
Wider setting of protected view 2A.1 Parliament Hill summit to St Paul's Cathedral; 3A.1 Kenwood viewing gazebo to St Paul's Cathedral; Flood defence 15 m away (wall, designed for a 1 in 1000 year flood); Inside the Southwark built-up area; Public transport access: PTAL 0 (very poor), TfL 2023, for the 100 m square; Priority habitat 15 m away: Mudflats; Designated open space 15 m away.
Not affected
Not green belt

Checked on 3 November 2026. Historic England, the Environment Agency, Natural England, the Planning Inspectorate, Transport for London (public transport access levels, Powered by TfL Open Data, OGL v3.0, contains OS data © Crown copyright and database right 2025) and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Building

Floor area90 m² (969 sq ft)
Energy ratingD (57 out of 100)
PropertySemi-detached flat, 2 habitable rooms
Built2003 to 2006
HeatingBoiler and radiators, electric
WallsSolid brick, as built, insulated (assumed)

From the energy performance certificate lodged in June 2009, the latest held for this property. The building may have changed since. View the certificate

Work with planning data?

Every application in Southwark - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Council
Southwark
Application type
Minor application
Postcode
SE1 9DG
Received
28 Apr 2026
Validated
29 Apr 2026
Ward
Borough & Bankside
Parish
Borough, Bankside And Walworth
Case officer
Show
Target decision
12 Oct 2026
Decision
Minor - GRANTED
Decision date
8 Oct 2026
Decision level
Committee - Small Sites
Applicant
Show
Agent
Rolfe Judd Planning
Freehold owner
Show

How this decision compares

Decided in 162 days from validation, 107 days slower than Southwark's median of 55 for changes of use. Approved, as 78% of changes of use here are.

56%decided within 8 weeks
78%approved
89decided in the last year

Plota live figures for changes of use decided by Southwark in the last twelve months, from validation. Southwark decision record →

Public comments

32comments received
30 objecting1 neutral1 supporting

94% object · above the UK average of 74%

110 neighbours consulted · Last counted 8 Oct 2026

Read the comments on the council site ↗

Consultation & key dates

Committee
7 Oct 2026
Statutory expiry
23 Jun 2026
Env. assessment
No
Southwark
Planning Authority Score
7/10
Good
#64 of 296 councils
Relevant to this application:
Householder decisions

Southwark is faster than most councils at deciding householder applications, ranking #54 out of 296. Householder applications are slightly more likely to be approved here (95%) than the national average (90%).

Faster than most councils
for householder decisions
These figures are council-wide context, not a prediction for this application. View full council performance
Southwark decision statistics
Based on MHCLG data, the year to March 2026
92%
Overall approval rate
Above avg (87%) #93 of 296
95%
Householder approved
Above avg (90%) #92 of 296
78%
Decided in 8 weeks
Above avg (63%) #54 of 296
37%
Extended time limit
Below avg (41%) #122 of 296
92%
Minor dwellings approved
259 decided (1-9 homes)
86%
Major dwellings approved
14 decided (10+ homes)
82%
Change of use approved
38 decided
1,622
Total decisions
132 refused in the year to March 2026

Freehold boundary: © Crown copyright and database rights 2026, HM Land Registry. Polygons © Crown copyright and database rights 2026 Ordnance Survey 100026316. Conditions of use

Energy performance: Energy performance certificates from the Energy Performance of Buildings Register, Ministry of Housing, Communities and Local Government. Contains public sector information licensed under the Open Government Licence v3.0. © Crown copyright 2026.

Freehold owner and leaseholders: Information produced by HM Land Registry. © Crown copyright 2026. Source: HM Land Registry, UK and overseas companies that own property in England and Wales, September 2026 release.