Hotel extension and reconfiguration at Delta Marriott Hotel, Cheshunt
Summary of planning committee decision
Decided by Broxbourne Planning and Regulatory Committee on 29 Jul 2026.
What is proposed
The application would reconfigure and extend the vacant hotel, adding a courtyard extension, ancillary facilities, cycle parking, landscaping and 142 guestrooms.
“DESCRIPTION OF PROPOSAL 3.1 The proposed development involves reconfiguration and extension of the vacant hotel building to include the construction a two-storey courtyard infill with a flat roof. This element will largely consume the existing courtyard space apart from a section of terrace and planting, and would contain a gym, changing rooms, sauna, steam room and spa at ground level.”
Officer report
The site
The hotel is beside Halfhide Lane, near the A10, Turnford Place business centre, allotments and other commercial development.
“SUMMARY 1.1 This application proposes the reconfiguration and extension of the Delta Marriot Hotel, which is currently vacant as of June 2026, but was formerly used to accommodate asylum seekers from December 2022. The proposed development would provide a two-storey courtyard infill extension with ancillary restaurant, cafe, gym and spa facilities. Access would be from Halfhide Lane as per the current situation.”
“To the south on the opposite side of Halfhide Lane is the recently built business and household storage facility and discount supermarket granted permission October 2023. Access to the hotel is via Halfhide Lane / A1170 roundabout junction. To the frontage is a parking forecourt with landscaping. The front of the hotel building features a covered driveway at the main entrance.”
Officer report
Consultation responses
Neighbouring occupiers raised no objections, while most consultees had no objection subject to conditions; the highway authority objected.
“CONSULTATIONS AND REPRESENTATIONS 5.1 Detailed below is a summary of the consultation responses received. The full version of each consultation response can be viewed on the Council’s website via public access at the following link: https://www.broxbourne.gov.uk/planning/planning- register/1 using the planning reference: 07/26/0319/F. Publicity Notification of this planning application was sent to 97 neighbouring properties.”
“BBC Waste Management – no objection. The applicant will need to follow the detailed Borough-Wide Waste Supplementary Planning Guidance. HCC Ecology – no objection, subject to the General Biodiversity Gain condition, including Landscape and Ecological Management Plan (LEMP) 5.8 HCC Highway Authority – Object to the proposed development due to increase in vehicle trips and no mitigation or improvement measures shown on the public highway.”
Officer report
Committee discussion
The committee noted that the Growth and Infrastructure Board had objected because it considered the mitigation insufficient, while officers considered mitigation unnecessary.
“It was noted that the Hertfordshire County Council Growth and Infrastructure Board had now objected to the application on the grounds that there were insufficient mitigations given the potential impact of the development. The officers indicated that as the application related to improvements and expansion to that currently existing at the site mitigations were unnecessary.”
Minutes
The decision
Planning permission was granted subject to the conditions set out in the original report.
“RESOLVED that planning permission be granted subject to the conditions set out at the end of the original report.”
Minutes
Conditions attached
The conditions covered approved plans, lighting, landscaping, trees, materials, travel, contamination, construction, drainage, biodiversity and ecological management.
“RECOMMENDATION 9.1 That planning permission be granted subject to the conditions set out below; Conditions 1. Standard time limit. Development in accordance with the numbered plans. In accordance with External Lighting Strategy. In accordance with landscaping scheme. Tree protection and landscaping retention. Submission / approval of external materials. Submission/approval of a site/use specific travel plan - prior to occupation. 8.”
“Detailed construction drawings of the surface water drainage scheme and construction method statement - prior to commencement. Scheme to dispose of foul drainage – prior to commencement. Details and a method statement for interim and temporary drainage measures during the demolition and construction phases - prior to commencement. Details of the maintenance and management of the sustainable drainage scheme – prior to occupation. 16.”
Officer report
Sources
- Broxbourne Planning and Regulatory Committee minutes, 29 July 2026
- Agenda and papers (council website)
Source: Plota analysis of Broxbourne's committee minutes and officer report. Quotations are the council's own words; headings and summaries are Plota's.
Committee decisions and nationwide planning applications, in one API
The Plota API returns planning applications from every council we cover, each with its decision, whether a committee or officers decided it, and the committee date. Build it into your own tools.
See the API →At the meeting
- Council
- Broxbourne
- Date
- Wednesday 29 July 2026
- Recommendation
- Officers recommended approval
- Committee decided
- Approved
- Minutes
- The council's minutes
- Meeting
- Agenda and papers (council website)
- Application
- View application →
- All decisions
- Broxbourne committee decisions →
This committee's year
15 decisions in the 12 months to this meeting, 3 against officer advice.
Source: Plota analysis of the committee's minutes.