Part Parcel 0038 Tewkesbury Road Longford Gloucester Gloucestershire Data via plota.co.uk

26/00002/S37EA - S73 of the Electricity Act Awaiting decision

Proposal

A connection offer was accepted by Wessex Solar Power Limited for a 16MW PV generation connection scheme (planning ref: ). The connection will be provided by constructing new H-poles between 33kV Poles 78ZC3C28 and 78XC3C29 from where a short length of cable will be installed down to the bottom of the wood-poles to 2 x 33kV straight joints to serve as the point of connection for the connection. Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
1 Apr 2026
✓
Validated
10 Sept 2026
✓
Consultation
15 Sept 2026
Decision
Expected by 5 Nov 2026

Under consideration

No decision has been issued yet. Plota predicts a decision between 12 Oct 2026 and 1 Nov 2026, from Tewkesbury's recent amendments.

The consultation period closed on 4 Oct 2026.

Site constraints 4

Flood zone 3, rivers and sea
High chance: a 1 in 100 or greater annual chance from rivers, or 1 in 200 from the sea. Any development here needs a flood risk assessment. Defences are not counted.
The Environment Agency flood map for planning. Homes in zone 3 must also pass the sequential test. Surface water flooding is a separate map.
Flood map ↗
Priority habitat: Coastal and floodplain grazing marsh
A habitat of principal importance. It shapes the ecology work and the biodiversity net gain a scheme has to show.
Agricultural land, grade 3a
Best and most versatile land (grades 1, 2 and 3a). Source: the Predictive Agricultural Land Classification Map (Defra and Natural England, 2025; the Welsh Government's Predictive ALC Map 2 in Wales), a model rather than a site survey. Natural England's Provisional ALC map (1:250,000, 1970s), which most planning maps still show, had this area as grade 4. The predicted grade is Defra's current estimate; only a site survey settles it.
Where development of farmland is needed, policy prefers poorer land over the best and most versatile (grades 1, 2 and 3a). Three sources: Natural England's post-1988 field surveys, which are definitive where they exist; the Defra predictive map for England (2025) and the Welsh Government predictive map, modelled from the soil map with 3a and 3b split; and the 1970s provisional map, which planners and other services still show, coarser and with grade 3 undivided. Where the provisional and predicted grades disagree, treat the predicted grade as the current estimate and expect an application to carry its own survey.
Habitat network: Other Priority Habitats - NEZ
Where habitat is joined up enough to work as a network. Context, not a constraint on its own.
Not affected
Not green belt · No listed building at the site · No scheduled monument at the site

Checked on 6 October 2026. Historic England, the Environment Agency, Natural England and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Work with planning data?

Every application in Tewkesbury - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Council
Tewkesbury
Application type
S73 of the Electricity Act
Received
1 Apr 2026
Validated
10 Sept 2026
Ward
Innsworth
Parish
Longford
Case officer
Show
Target decision
5 Nov 2026

Decision outlook

Day 29 of the 56-day target. Tewkesbury usually decides amendments by day 37.

Day 2927 days to the 56-day target
70%decided within 8 weeks
81%approved
72decided in the last year

Plota live figures for amendments decided by Tewkesbury in the last twelve months, from validation. Tewkesbury decision record →

Public comments

No public comments yet.

9 neighbours consulted · Last counted 5 Oct 2026

Read the comments on the council site ↗

Consultation & key dates

Neighbours
11 Sept 2026
Consultation
15 Sept 2026
Comments by
4 Oct 2026
Statutory expiry
5 Nov 2026
Env. assessment
No
Tewkesbury
Planning Authority Score
3.7/10
Below average
#212 of 296 councils
Relevant to this application:
Householder decisions

Tewkesbury ranks #197 out of 296 councils for householder decision speed. 50% of applications have the time limit extended, above the 41% national average. Householder applications are slightly more likely to be approved here (93%) than the national average (90%).

These figures are council-wide context, not a prediction for this application. View full council performance
Tewkesbury decision statistics
Based on MHCLG data, the year to March 2026
89%
Overall approval rate
Above avg (87%) #144 of 296
93%
Householder approved
Above avg (90%) #139 of 296
57%
Decided in 8 weeks
Below avg (63%) #197 of 296
50%
Extended time limit
Above avg (41%) #228 of 296
69%
Minor dwellings approved
89 decided (1-9 homes)
100%
Major dwellings approved
12 decided (10+ homes)
86%
Change of use approved
37 decided
689
Total decisions
74 refused in the year to March 2026