Mercure London Kensington, 1A Lexham Gardens, London, W8 6JJ Data via plota.co.uk

CON/25/05792 - Discharge of Conditions Approved

Proposal

Details required by condition 13 (revised fire strategy prior to occupation) of planning permission Ref. (Change of use from hotel accommodation (Use Class C1) to health care facility (Use Class E(e)) together with associated alterations including replacement glazed entrance doors, removal and replacement of shutters with glazing and replacement cladding, and erection of projecting entrance canopy at ground floor level; replacement roofing and glazing across all levels and installation of entrance and way finding signage (Major). Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
23 Sept 2025
✓
Approved
27 Apr 2026

Approved on 27 Apr 2026 · Last checked 23 Oct 2026

Associated applications 7

Site constraints 7

Article 4 direction
Article 4 - No 100. Named permitted development rights are withdrawn here.
An Article 4 direction withdraws particular permitted development rights, so work that would normally need no application needs one here. Not every council has published its directions.
Air quality management area: Kensington and Chelsea AQMA
The council has declared the area as failing an air quality objective.
Schemes that add traffic, parking or combustion plant are assessed against the area's action plan and may need an air quality assessment.
Council record ↗
Conservation area about 16 m away: Lexham
The edge of the area; work outside it can still affect its setting.
The council must give weight to preserving or enhancing the area's character and appearance. Not every council has published its boundaries as open data.
Council document ↗
Also on the record
National infrastructure project about 1.5 km away: Thames Tideway Tunnel; Tree preservation order about 16 m away; Inside the Kensington and Chelsea built-up area; Public transport access: PTAL 6a (excellent), TfL 2023, for the 100 m square.
Not affected
Outside flood zones 2 and 3 · Not green belt · No scheduled monument at the site

Checked on 2 November 2026. The pin for this application is the centre of its postcode rather than the building, so distances to nearby designations are measured from the postcode and can be out by the width of the postcode area. Historic England, the Environment Agency, Natural England, the Planning Inspectorate, Transport for London (public transport access levels, Powered by TfL Open Data, OGL v3.0, contains OS data © Crown copyright and database right 2025) and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Work with planning data?

Every application in Kensington and Chelsea - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Application type
Discharge of Conditions
Postcode
W8 6JJ
Received
23 Sept 2025
Validated
23 Sept 2025
Ward
Abingdon
Case officer
Show
Target decision
18 Nov 2025
Decision
Granted
Decision date
27 Apr 2026

How this decision compares

Decided in 216 days from validation, 137 days slower than Kensington and Chelsea's median of 79 for commercial premises. Approved, as 93% of commercial premises here are.

37%decided within 8 weeks
93%approved
419decided in the last year

Plota live figures for commercial premises decided by Kensington and Chelsea in the last twelve months, from validation. Kensington and Chelsea decision record →

Consultation & key dates

Comments by
31 Oct 2025
Kensington and Chelsea
Planning Authority Score
5.1/10
Average
#144 of 296 overall
Relevant to this application:
Change of use

Kensington and Chelsea is #174 of 296 councils on householder decision speed. Householder applications are slightly more likely to be approved here (94%) than the national average (90%).

These figures are council-wide context, not a prediction for this application. View full council performance
Kensington and Chelsea decision statistics
Based on MHCLG data, the nine months to December 2025
93%
Overall approval rate
Above avg (87%) #58 of 296
94%
Householder approved
Above avg (90%) #110 of 296
61%
Decided in 8 weeks
Below avg (63%) #174 of 296
40%
Extended time limit
Below avg (41%) #152 of 296
94%
Minor dwellings approved
455 decided (1-9 homes)
87%
Change of use approved
53 decided
1,839
Total decisions
135 refused in the nine months to December 2025