Field to West of National Grid Converter Substation, Church Lane, Aldington, Kent, TN25 6AF Data via plota.co.uk

PA/2026/0214 - Removal/variation of conditions Approved

Proposal

Variation of conditions 2 (Approved Plans), 4 (CEMP), 5 (Tree Protection), 7 (Noise Impact Assessment), 10 (Surface Water Drainage), 12 (Fire Pollutants Control), 13 (Soft Landscaping), 15 (LEMP), 16 (EMMP), 18 (External Lighting) and removal of Condition 6(i) (Highway condition Survey) in its entirety for Planning Permission PA/2022/2544 "The laying out of a battery storage facility, intermediate substation, water storage tank, cabling, fencing, access tracks and associated drainage infrastructure on field to west of National Grid Sellindge Converter Substation"; to allow for changes to layout and alternative technology to be installed. Data via plota.co.uk

View original council record ↗

Application progress

Validated
4 Feb 2026
Received
7 Feb 2026
Approved

Approved on · Delegated Decision · Last checked 15 Jul 2026

Documents 75

Statements & assessments 20

PDF KCC Bio-diversity/Ecology - Consultation Response Consultee · 8 Jun 2026 View ↗ PDF Updated Landscape and Ecological Management Plan (LEMP) (Rev: 05, dated 20 May 2026) Supporting Documents · 1 Jun 2026 View ↗ PDF KCC: Ecological Advice Service Consultee · 14 May 2026 View ↗ PDF KCC: Highways & Transportation Consultee · 5 May 2026 View ↗ PDF Ecological Mitigation and Management Plan (EMMP) (Rev: V3.0, dated 30 April 2026) Supporting Documents · 1 May 2026 View ↗ PDF KCC Bio-diversity/Ecology - Consultation Response Consultee · 17 Apr 2026 View ↗ PDF KCC: Highways & Transportation Consultee · 9 Apr 2026 View ↗ PDF KCC Drainage - Consultation Response Consultee · 3 Mar 2026 View ↗ PDF Biodiversity Net Gain (BNG) Covering Letter Supporting Documents · 4 Feb 2026 View ↗ PDF Landscape and Ecological Management Plan (LEMP) Supporting Documents · 4 Feb 2026 View ↗ PDF Flood Risk Assessment and Drainage Strategy (Rev: P01, dated 23 January 2026) Supporting Documents · 4 Feb 2026 View ↗ PDF Ecological Mitigation and Management Plan (EMMP) Supporting Documents · 4 Feb 2026 View ↗ PDF Updated Ecological Information (UEI) Report Supporting Documents · 4 Feb 2026 View ↗ PDF Historic Environment Desk-Based Assessment Supporting Documents · 4 Feb 2026 View ↗ PDF Great Crested Newt (GCN) Survey Report Supporting Documents · 4 Feb 2026 View ↗ PDF Arboricultural Report and Method Statement Supporting Documents · 4 Feb 2026 View ↗ PDF Biodiversity Metric Supporting Documents · 4 Feb 2026 View ↗ PDF Proposed Drainage Strategy - 065008-SLR-XXX-XXX-DR-CH-0500-Rev P01, dated January 2026 Plan · 4 Feb 2026 View ↗ PDF Water Vole and Otter Survey Report Supporting Documents · 4 Feb 2026 View ↗ PDF Noise Impact Assessment (Version No: 1, dated December 2025) Supporting Documents · 4 Feb 2026 View ↗

Plans & drawings 32

PDF 402.065008.00003-PD03 - Swept Path Analysis - 16.5m Articulated HGV Plan · 28 May 2026 View ↗ PDF SEL-EDF-BESS-CIV-PLN-200C - Construction Compound plan Plan · 28 May 2026 View ↗ PDF Indicative Construction Compound Plan Plan · 1 May 2026 View ↗ PDF Construction Environment Management Plan (CEMP) (Rev: 03 dated 23 January 2026) Supporting Documents · 8 Apr 2026 View ↗ PDF Construction Traffic Management Plan (CTMP) (Rev: 03 dated 22 January 2026) Supporting Documents · 8 Apr 2026 View ↗ PDF Landscape & Visual Appraisal - Designations Plan - SB-LA/001 Plan · 4 Feb 2026 View ↗ PDF Spares Container Arrangement - SEL-EDFR-BESS-ARC-DRG-362 Plan · 4 Feb 2026 View ↗ PDF Reactive Power Unit Arrangement - SEL-EDFR-BESS-ARC-DRG-371 Plan · 4 Feb 2026 View ↗ PDF EV Charger Arrangement - SEL-EDFR-BESS-ARC-DRG-372 Plan · 4 Feb 2026 View ↗ PDF 132kV Transformer Arrangement - SEL-EDFR-BESS-ARC-DRG-373 Plan · 4 Feb 2026 View ↗ PDF Site Plan - Figure 1 Plan · 4 Feb 2026 View ↗ PDF Site Elevations - SEL-EDFR-BESS-ARC-DRG-350 Plan · 4 Feb 2026 View ↗ PDF Construction Traffic Management Plan (CTMP) Supporting Documents · 4 Feb 2026 View ↗ PDF Landscape & Visual Appraisal - Viewpoint Location Plan - SB-LA/003 Plan · 4 Feb 2026 View ↗ PDF MV Skid Arrangement - SEL-EDFR-BESS-ARC-DRG-360 Plan · 4 Feb 2026 View ↗ PDF Water Tank Arrangement - SEL-EDFR-BESS-ARC-DRG-369 Plan · 4 Feb 2026 View ↗ PDF Landscape Proposals plan (SB LA / 005 Rev: 04, dated Jan 2026) Plan · 4 Feb 2026 View ↗ PDF Location Plan - Figure 1 Plan · 4 Feb 2026 View ↗ PDF CCTV & Fence Arrangement - SEL-EDFR-BESS-ARC-DRG-364 Plan · 4 Feb 2026 View ↗ PDF DNO Substation Arrangement - SEL-EDFR-BESS-ARC-DRG-363 Plan · 4 Feb 2026 View ↗ PDF BESS Container Arrangement - SEL-EDFR-BESS-ARC-DRG-361 Plan · 4 Feb 2026 View ↗ PDF Proposed Site Levels - 065008-SLR-XX-XX-D-C-000001 P03 Plan · 4 Feb 2026 View ↗ PDF Construction Environmental Management Plan (CEMP) Supporting Documents · 4 Feb 2026 View ↗ PDF Harmonic Filter Arrangement - SEL-EDFR-BESS-ARC-DRG-370 Plan · 4 Feb 2026 View ↗ PDF Control Room/Welfare Unit - SEL-EDFR-BESS-ARC-DRG-368 Plan · 4 Feb 2026 View ↗ PDF Landscape & Visual Appraisal - Character Plan - SB-LA/002 Plan · 4 Feb 2026 View ↗ PDF Proposed Site elevations - 065008-SLR-XX-XX-D-C-000003 Rev P02 Plan · 4 Feb 2026 View ↗ PDF Proposed Site Sections - 065008-SLR-XX-XX-D-C-000002 Rev P02 Plan · 4 Feb 2026 View ↗ PDF Earthing & Aux Transformer Arrangement - SEL-EDFR-BESS-ARC-DRG-366 Plan · 4 Feb 2026 View ↗ PDF Site Layout Plan - SEL-EDFR-BESS-CIV-PLN-200 Plan · 4 Feb 2026 View ↗ PDF LV Switchroom Arrangement - SEL-EDFR-BESS-ARC-DRG-367 Plan · 4 Feb 2026 View ↗ PDF BESS Switchgear Arrangement - SEL-EDFR-BESS-ARC-DRG -65 Plan · 4 Feb 2026 View ↗

All documents on the council site ↗

Important details

Council
Ashford
Application type
Removal/variation of conditions
Postcode
TN25 6AF
Received
7 Feb 2026
Validated
4 Feb 2026
Ward
Bircholt
Parish
Smeeth
Case officer
Show
Target decision
12 Jun 2026
Decision
Approve with Conditions
Decision level
Delegated Decision
Applicant
Show
Ashford
Planning Authority Score
5.9/10
Average
#105 of 296 councils
Relevant to this application:
Householder decisions

Ashford is faster than most councils at deciding householder applications, ranking #75 out of 296. Householder applications are slightly more likely to be approved here (92%) than the national average (90%).

Faster than most councils
for householder decisions
These figures are council-wide context, not a prediction for this application. View full council performance
Ashford decision performance
Based on MHCLG data, the year to March 2026
88%
Overall approval rate
Above avg (87%) #147 of 296
92%
Householder approved
Above avg (90%) #146 of 296
75%
Decided in 8 weeks
Above avg (63%) #75 of 296
40%
Extended time limit
Below avg (41%) #146 of 296
71%
Minor dwellings approved
106 decided (1-9 homes)
89%
Major dwellings approved
18 decided (10+ homes)
90%
Change of use approved
40 decided
991
Total decisions
123 refused in the year to March 2026