Planning decisions in Orkney
How long Orkney takes to decide a planning application and how many it approves, from the 131 decisions it made in the twelve months to August 2026. Days run from validation to decision, the clock the council reports against; the wait from receipt is shown beside it. How the figures are made.
66 daysmedian from validation to decision (UK 52); 97 from receipt
29%decided within eight weeks (UK 73%), 77% within thirteen
97%approved (UK 89%): 98 approved, 3 refused, 8 withdrawn
314 of 322UK rank for speed, up 16 places on last year; 35 of 322 for approvals
By kind of application
| Kind | Median days | Within 8 weeks | Approved | Decisions | UK rank |
|---|---|---|---|---|---|
| Full applications | 77 | 18% | 96% | 49 | 284 of 298 |
| Householder applications * | 70 | 23% | 100% | 24 | 155 of 158 |
| Listed building consent * | 63 | 18% | 100% | 11 | 163 of 200 |
Delegated or committee
| Route | Share | Median days | Approved | Decisions |
|---|---|---|---|---|
| Delegated to officers | 95% | 65 | 98% | 124 |
| Planning committee | 5% | 66 | 83% | 6 |
Where the register states how the decision was made. 1 decisions did not say.
By year
| Year decided | Median days | Within 8 weeks | Approved | Decisions |
|---|---|---|---|---|
| 2016 * | 58 | 46% | 100% | 40 |
| 2017 * | 50 | 63% | 100% | 56 |
| 2018 * | 63 | 37% | 96% | 300 |
| 2019 * | 48 | 56% | 94% | 59 |
| 2020 * | 36 | 62% | 92% | 55 |
| 2021 * | 68 | 31% | 98% | 43 |
| 2022 * | 72 | 26% | 96% | 28 |
| 2023 * | 95 | 12% | 96% | 205 |
| 2024 * | 85 | 15% | 97% | 178 |
| 2025 * | 71 | 40% | 90% | 53 |
| 2026 so far | 97 | 13% | 97% | 130 |
* Years from our archive, which carries no validation date: timed from receipt, so a few days longer than the live years above them.
Decided in the last three weeks
- 32 Summerdale Drive (Land Near), 16 Craigie Crescent (Land Near), 17 Craigie Crescent (Land Near), Kirkwall OrkneyInstall 3 x 9m wooden polesApproved7 Sept 2026
- 3 Robertson Loan, Kirkwall, Orkney KW15 1GQExtend a houseApproved7 Sept 2026
- Sule Skerry Lighthouse, OrkneyInternal strip out (including watchroom immediately beneath the lantern), structural repairs to cracks, roof and drainage repairs, re-waterpApproved2 Sept 2026
- Nationwide Building Society, 24 Bridge Street, Kirkwall Orkney KW15 1HRInstall a defibrillator unit and bleed kit unitApproved1 Sept 2026
- Upper Flat, Old Manse, The Palace, Birsay, Orkney KW17 2LXReplace roof covering with composite slatesApproved1 Sept 2026
- Ben-elgar, Harray, Orkney KW17 2JUErect a house with an integral garage (retrospective)Approved28 Aug 2026
- Braeside, Orphir Orkney KW17 2RBChange of use of land from agriculture to domestic, extend a house, and erect an agricultural building (part retrospective)Approved28 Aug 2026
- Westermill, 24 Willowburn Road, Kirkwall, Orkney KW15 1NGProposed alteration and extension including dormer windowApproved27 Aug 2026
Built nightly from Orkney's planning register. Ranks are among the 322 published councils. See planning applications in Orkney, or get alerts for Orkney.
About these figures
How are decision times measured?
Days from the date the council validated the application to the date it decided it, for applications approved or refused in the window. That is the clock councils report against and the official statistics use. Each council’s page also shows the count from receipt, which is what the applicant actually waited. Withdrawn and undecided applications are not timed.
Why do these figures differ from the council’s own?
Councils count an agreed extension of time as decided on time; we treat the calendar as the calendar. Our figures are also live and rolling, where official statistics are quarterly and annual. So a council’s own within-eight-weeks figure will usually sit a little above ours.
What counts as approved?
Approval rate is approvals divided by approvals plus refusals. Withdrawals, and decisions whose outcome the register does not state, are counted in the totals but not in the rate.
Why is a council missing?
A council is published when it has at least 25 timed decisions in the window and its register’s decision data passes our consistency checks. Councils that fail are listed with the reason rather than shown with a number that would mislead.
How often is this updated?
Nightly, from the decisions we collect from every council register we monitor. The window is the twelve months to the last complete month.