Anchor 1 Bankside London Southwark SE1 9DN Data via plota.co.uk

26/AP/3231 - Listed Building Consent Under consideration/assessment

Proposal

Listed building consent: Utilise redundant catering kitchen and glass wash area and form new bar servery and staff wc and change area Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
2 Nov 2026
✓
Validated
3 Nov 2026
Decision
Expected by 28 Dec 2026

Under consideration

No decision has been issued yet. Plota predicts a decision between 26 Dec 2026 and 15 Jan 2027, from Southwark's recent changes of use.

Site constraints 18

Grade II listed: Anchor Public House
List entry 1376546 · The pin is inside its outline · 8 more listed buildings within 150 m (1 Grade II*, 5 Grade II)
Listed building consent is needed for work that affects the special interest of a listed building, inside or out, on top of planning permission. Setting can be a consideration for buildings nearby; there is no fixed radius.
Show the other 8 with distances
Historic England ↗
Flood zone 3, rivers and sea
High chance: a 1 in 100 or greater annual chance from rivers, or 1 in 200 from the sea. Any development here needs a flood risk assessment. Defences are not counted.
The Environment Agency flood map for planning. Homes in zone 3 must also pass the sequential test. Surface water flooding is a separate map.
Flood map ↗
3 Article 4 directions
Bankside and Borough District Town Centre · The Anchor Bankside · Central Activities Zone. Named permitted development rights are withdrawn here.
An Article 4 direction withdraws particular permitted development rights, so work that would normally need no application needs one here. Not every council has published its directions.
National infrastructure project: Thames Tideway Tunnel
The site is inside the project boundary. Waste water treatment, decided. The project page says whether consent was granted. Also within 2 km: London Strategic Heat Main Project (at pre-application, 2 m).
Nationally significant infrastructure projects (power stations, electricity lines, pipelines, major roads and railways, harbours, airports and reservoirs) are consented by a Secretary of State under the Planning Act 2008, after an examination by the Planning Inspectorate, rather than by the council. The boundary is the one the Inspectorate consults on and can change as the scheme does. Projects are shown within 2 km of the site.
Planning Inspectorate project page ↗
Thames Path 8 m away
Matters where it crosses or adjoins the site; the route and its margin are protected.
Archaeological priority area
An assessment or field evaluation may be asked for before ground works.
The council or Historic England considers archaeology likely here. A desk-based assessment, and sometimes trial trenching, can be asked for with the application.
Air quality management area: Southwark AQMA
The council has declared the area as failing an air quality objective.
Schemes that add traffic, parking or combustion plant are assessed against the area's action plan and may need an air quality assessment.
Council record ↗
Town centre: Bankside and The Borough
A designated centre in the London Plan.
Shops, services and active frontages are protected in centres, and main town centre uses are steered here first.
Scheduled monument 86 m away: Remains of Winchester Palace, Clink Street and waterfront
Its setting is a consideration for work nearby.
Nationally important archaeology protected by the Secretary of State. Work that affects the monument or its setting is rarely permitted.
Historic England ↗
Central activities zone
The core of central London in the London Plan.
Offices, culture and the other strategic functions of the centre take priority over new housing here.
Opportunity area
Where the London Plan expects significant growth.
Boundaries are indicative and the borough holds the detailed plan.
Also on the record
Wider setting of protected view 3A.1 Kenwood viewing gazebo to St Paul's Cathedral; Conservation area 55 m away: Borough High Street; Flood defence 33 m away (wall, designed for a 1 in 1000 year flood); Inside the Southwark built-up area; Public transport access: PTAL 6b (excellent), TfL 2023, for the 100 m square; Priority habitat 33 m away: Mudflats; Designated open space 33 m away.
Not affected
Not green belt

Checked on 6 November 2026. Historic England, the Environment Agency, Natural England, the Planning Inspectorate, Transport for London (public transport access levels, Powered by TfL Open Data, OGL v3.0, contains OS data © Crown copyright and database right 2025) and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Work with planning data?

Every application in Southwark - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Council
Southwark
Application type
Listed Building Consent
Postcode
SE1 9DN
Received
2 Nov 2026
Validated
3 Nov 2026
Ward
Borough & Bankside
Parish
Borough, Bankside And Walworth
Case officer
Show
Target decision
28 Dec 2026
Applicant
Show
Agent
Concept IDL Ltd

Decision outlook

Day 6 of the 56-day target. Southwark usually decides changes of use by day 55.

Day 650 days to the 56-day target
56%decided within 8 weeks
78%approved
89decided in the last year

Plota live figures for changes of use decided by Southwark in the last twelve months, from validation. Southwark decision record →

Public comments

No public comments yet.

Last counted 6 Nov 2026

Read the comments on the council site ↗

Consultation & key dates

Statutory expiry
28 Dec 2026
Env. assessment
No
Southwark
Planning Authority Score
7/10
Good
#64 of 296 councils
Relevant to this application:
Other decisions

Southwark is faster than most councils at deciding householder applications, ranking #54 out of 296. Householder applications are slightly more likely to be approved here (95%) than the national average (90%).

Faster than most councils
for householder decisions
These figures are council-wide context, not a prediction for this application. View full council performance
Southwark decision statistics
Based on MHCLG data, the year to March 2026
92%
Overall approval rate
Above avg (87%) #93 of 296
95%
Householder approved
Above avg (90%) #92 of 296
78%
Decided in 8 weeks
Above avg (63%) #54 of 296
37%
Extended time limit
Below avg (41%) #122 of 296
92%
Minor dwellings approved
259 decided (1-9 homes)
86%
Major dwellings approved
14 decided (10+ homes)
82%
Change of use approved
38 decided
1,622
Total decisions
132 refused in the year to March 2026