Pegasus House 37 - 43 Sackville Street London W1S 3EH Data via plota.co.uk

25/07407/ADFULL - Approval of Details (Full PP) Approved

Proposal

Detailed drawings (scales 1:20, 1:5 and 1:1) of various roof level elements for the 4th floor terrace, 6th floor terrace, 7th floor roofs, mansard roofs, zinc cladding, plant screen and chimneys pursuant to partial discharge of condition 7 of planning permission dated 22nd September 2021 (RN: ) Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
14 Oct 2025
✓
Validated
11 Nov 2025
✓
Approved
12 Jan 2026

Approved on 12 Jan 2026 · Delegated Decision · Last checked 9 Oct 2026

Documents 126

Plans & drawings 77

PDF WEST ELEVATION 2 Drawing · 11 Nov 2025 View ↗ PDF WEST ELEVATION Drawing · 11 Nov 2025 View ↗ PDF SOUTH ELEVATION Drawing · 11 Nov 2025 View ↗ PDF EAST ELEVATION Drawing · 11 Nov 2025 View ↗ PDF NORTH ELEVATION Drawing · 11 Nov 2025 View ↗ PDF TYPICAL ZINC WALL SYSTEM BUILD-UP DETAIL (RT10) Drawing · 11 Nov 2025 View ↗ PDF TYPICAL SLATE MANSARD ROOF SYSTEM BUILD-UP DETAIL (RT08) Drawing · 11 Nov 2025 View ↗ PDF TYPICAL CLAY PITCHED ROOF SYSTEM BUILD-UP DETAIL (RT09) Drawing · 11 Nov 2025 View ↗ PDF TYPICAL GREEN ROOF SYSTEM BUILD-UP DETAIL (RT02) Drawing · 11 Nov 2025 View ↗ PDF BUR ROOF FALL ARREST SYSTEM SECTION DETAIL Drawing · 11 Nov 2025 View ↗ PDF INVERTED BLUE ROOF SECTION DETAIL Drawing · 11 Nov 2025 View ↗ PDF INVERTED ROOF HOT PIPE PENETRATION SECTION DETAIL Drawing · 11 Nov 2025 View ↗ PDF INVERTED ROOF VERTICAL RAINWATER OUTLET SECTION DETAIL Drawing · 11 Nov 2025 View ↗ PDF INVERTED ROOF HORIZONTAL SURFACE SECTION DETAIL Drawing · 11 Nov 2025 View ↗ PDF NINTH FLOOR GENERAL ARRANGEMENT Drawing · 11 Nov 2025 View ↗ PDF LEVEL 09 RIDGE DETAIL Drawing · 11 Nov 2025 View ↗ PDF LEVEL 09 AOV DETAIL Drawing · 11 Nov 2025 View ↗ PDF LEVEL 09 ZINC CLADDING AND GUTTER DETAILS Drawing · 11 Nov 2025 View ↗ PDF LEVEL 08 FLAT 5 TERRACE WATERPROOFING DETAIL 2 Drawing · 11 Nov 2025 View ↗ PDF LEVEL 08 ZINC CLADDING DETAILS Drawing · 11 Nov 2025 View ↗ PDF LEVEL 08 PICCADILLY SLATED MANSARD WATERPROOFING DETAIL - GRID B/2 (COURTYARD FA Drawing · 11 Nov 2025 View ↗ PDF LEVEL 08 PICCADILLY SLATED MANSARD & FLAT ROOF WATERPROOFING DETAIL Drawing · 11 Nov 2025 View ↗ PDF LEVEL 08 PICCADILLY SLATED MANSARD Drawing · 11 Nov 2025 View ↗ PDF LEVEL 08 FLAT 5 TERRACE WATERPROOFING DETAIL Drawing · 11 Nov 2025 View ↗ PDF LEVEL 07 WINDOW PROFILE PLAN DETAIL Drawing · 11 Nov 2025 View ↗ PDF LEVEL 07 MANSARD ROOF BETWEEN GL G-H Drawing · 11 Nov 2025 View ↗ PDF LEVEL 07 ZINC CLADDING DETAILS Drawing · 11 Nov 2025 View ↗ PDF LEVEL 07 SACKVILLE ST DORMER TYPE 4 Drawing · 11 Nov 2025 View ↗ PDF LEVEL 07 STAIR (B) PITCHED ROOF DETAIL Drawing · 11 Nov 2025 View ↗ PDF LEVEL 07 STAIR (A) ROOF WATERPROOFING DETAIL Drawing · 11 Nov 2025 View ↗ PDF LEVEL 07 FLAT 4 TERRACE WATERPROOFING DETAIL Drawing · 11 Nov 2025 View ↗ PDF LEVEL 07 FLAT 1 TERRACE WATERPROOFING DETAIL Drawing · 11 Nov 2025 View ↗ PDF LEVEL 07 LIFT OVERRUN DETAIL Drawing · 11 Nov 2025 View ↗ PDF LEVEL 07 PLANT ROOF WATERPROOFING DETAIL Drawing · 11 Nov 2025 View ↗ PDF SIXTH FLOOR GENERAL ARRANGEMENT Drawing · 11 Nov 2025 View ↗ PDF LEVEL 06 OFFICE TERRACE ABUTMENT WATERPROOFING DETAILS Drawing · 11 Nov 2025 View ↗ PDF LEVEL 06 OFFICE TERRACE ABUTMENT WATERPROOFING DETAILS Drawing · 11 Nov 2025 View ↗ PDF LEVEL 06 SACKVILLE ST INSET DORMER TYPE 1 Drawing · 11 Nov 2025 View ↗ PDF LEVEL 06 SACKVILLE ST DORMER TYPE 3 Drawing · 11 Nov 2025 View ↗ PDF LEVEL 06 OFFICE TERRACE WATERPROOFING DETAILS Drawing · 11 Nov 2025 View ↗ PDF FIFTH FLOOR GENERAL ARRANGEMENT Drawing · 11 Nov 2025 View ↗ PDF LEVEL 05 SACKVILLE ST GUTTER WATERPROOFING DETAIL WITH BRACKET Drawing · 11 Nov 2025 View ↗ PDF FOURTH FLOOR GENERAL ARRANGEMENT Drawing · 11 Nov 2025 View ↗ PDF LEVEL 04 OFFICE TERRACE WALL WATERPROOFING DETAIL Drawing · 11 Nov 2025 View ↗ PDF LEVEL 04 OFFICE TERRACE WATERPROOFING DETAIL Drawing · 11 Nov 2025 View ↗ PDF SECOND FLOOR GENERAL ARRANGEMENT Drawing · 11 Nov 2025 View ↗ PDF LEVEL 02 SACKVILLE ST TERRACE DETAIL Drawing · 11 Nov 2025 View ↗ PDF ROOF PIPEWORK HOUSING Drawing · 11 Nov 2025 View ↗ PDF MANSARD ROOF VENT Drawing · 11 Nov 2025 View ↗ PDF STAIRWELL SUPPLY FANS ARRANGEMENT Drawing · 11 Nov 2025 View ↗ PDF CHIMNEY CAP (STYLE 02) Drawing · 14 Oct 2025 View ↗ PDF LOUVRE SCREEN PLAN AND ELEVATIONS Drawing · 14 Oct 2025 View ↗ PDF STEEL POST AND SECTION DETAIL (TYPICAL STRAIGHT RUN) Drawing · 14 Oct 2025 View ↗ PDF EAST ELEVATION Superseded document · 14 Oct 2025 View ↗ PDF SOUTH ELEVATION FIRE STRATEGY ELEVATION Superseded document · 14 Oct 2025 View ↗ PDF WEST ELEVATION Superseded document · 14 Oct 2025 View ↗ PDF WEST ELEVATION 2 Superseded document · 14 Oct 2025 View ↗ PDF NORTH ELEVATION Superseded document · 14 Oct 2025 View ↗ PDF LEVEL 07 WINDOW PROFILE PLAN DETAIL Superseded document · 14 Oct 2025 View ↗ PDF INVERTED ROOF VERTICAL RAINWATER OUTLET SECTION DETAIL Superseded document · 14 Oct 2025 View ↗ PDF INVERTED ROOF HOT PIPE PENETRATION SECTION DETAIL Superseded document · 14 Oct 2025 View ↗ PDF INVERTED BLUE ROOF SECTION DETAIL Superseded document · 14 Oct 2025 View ↗ PDF BUR ROOF FALL ARREST SYSTEM SECTION DETAIL Superseded document · 14 Oct 2025 View ↗ PDF INVERTED ROOF HORIZONTAL SURFACE SECTION DETAIL Superseded document · 14 Oct 2025 View ↗ PDF COMPONENT DETAIL Drawing · 14 Oct 2025 View ↗ PDF EIGHT FLOOR-MOV Drawing · 14 Oct 2025 View ↗ PDF SACKVILLE STREET PRESENTATION ELEVATION Drawing · 14 Oct 2025 View ↗ PDF NINTH FLOOR COMBINED SERVICES LAYOUT AND SECTIONS Drawing · 14 Oct 2025 View ↗ PDF LIGHTNING PROTECTION TYPICAL DETAILS Drawing · 14 Oct 2025 View ↗ PDF SECTION THROUGH DOOR AND LEAN BACK SECTION DETAIL Drawing · 14 Oct 2025 View ↗ PDF LOUVRE SCREEN ELEVATION AND ACCESS DOOR DETAILS Drawing · 14 Oct 2025 View ↗ PDF LEAN BACK DOOR DETAIL AND ELEVATION Drawing · 14 Oct 2025 View ↗ PDF SEVENTH FLOOR LIGHTNING PROTECTION LAYOUT Drawing · 14 Oct 2025 View ↗ PDF NINTH FLOOR LIGHTNING PROTECTION LAYOUT Drawing · 14 Oct 2025 View ↗ PDF CHIMNEY DETAIL 01 Drawing · 14 Oct 2025 View ↗ PDF CHIMNEY DETAIL 02 Drawing · 14 Oct 2025 View ↗ PDF CHIMNEY CAP (STYLE 01) Drawing · 14 Oct 2025 View ↗

Other documents 41

PDF 1ST INVALID LETTER Background Papers · 20 Oct 2025 View ↗ PDF RECEIPT OF APPLICATION Background Papers · 16 Oct 2025 View ↗ PDF COVER LETTER Background Papers · 14 Oct 2025 View ↗ PDF FOURTH FLOOR GENERAL ARRANGEMENT Superseded document · 14 Oct 2025 View ↗ PDF TYPICAL SLATE MANSARD ROOF SYSTEM BUILD-UP DETAIL (RT08) Superseded document · 14 Oct 2025 View ↗ PDF TYPICAL SLATE MANSARD ROOF SYSTEM BUILD-UP DETAIL (RT08) Superseded document · 14 Oct 2025 View ↗ PDF TYPICAL ZINC WALL SYSTEM BUILD-UP DETAIL (RT10) Superseded document · 14 Oct 2025 View ↗ PDF TYPICAL GREEN ROOF SYSTEM BUILD-UP DETAIL (RT02) Superseded document · 14 Oct 2025 View ↗ PDF TYPICAL CLAY PITCHED ROOF SYSTEM BUILD-UP DETAIL (RT09) Superseded document · 14 Oct 2025 View ↗ PDF TYPICAL CLAY PITCHED ROOF SYSTEM BUILD-UP DETAIL (RT09) Superseded document · 14 Oct 2025 View ↗ PDF LEVEL 08 FLAT 5 TERRACE WATERPROOFING DETAIL 2 Superseded document · 14 Oct 2025 View ↗ PDF LEVEL 09 ZINC CLADDING AND GUTTER DETAILS Superseded document · 14 Oct 2025 View ↗ PDF LEVEL 09 AOV DETAIL Superseded document · 14 Oct 2025 View ↗ PDF LEVEL 09 RIDGE DETAIL Superseded document · 14 Oct 2025 View ↗ PDF NINTH FLOOR GENERAL ARRANGEMENT-AMR-XX-09-DR-X-101900_VER2 Superseded document · 14 Oct 2025 View ↗ PDF LEVEL 07 SACKVILLE ST DORMER TYPE 4 Superseded document · 14 Oct 2025 View ↗ PDF LEVEL 07 ZINC CLADDING DETAILS Superseded document · 14 Oct 2025 View ↗ PDF LEVEL 07 MANSARD ROOF BETWEEN GL G-H Superseded document · 14 Oct 2025 View ↗ PDF LEVEL 08 FLAT 5 TERRACE WATERPROOFING DETAIL Superseded document · 14 Oct 2025 View ↗ PDF LEVEL 08 PICCADILLY SLATED MANSARD Superseded document · 14 Oct 2025 View ↗ PDF LEVEL 08 PICCADILLY SLATED MANSARD & FLAT ROOF WATERPROOFING DETAILL Superseded document · 14 Oct 2025 View ↗ PDF LEVEL 08 ZINC CLADDING DETAILS Superseded document · 14 Oct 2025 View ↗ PDF LEVEL 07 PLANT ROOF WATERPROOFING DETAIL Superseded document · 14 Oct 2025 View ↗ PDF LEVEL 07 LIFT OVERRUN DETAIL Superseded document · 14 Oct 2025 View ↗ PDF LEVEL 07 FLAT 1 TERRACE WATERPROOFING DETAIL Superseded document · 14 Oct 2025 View ↗ PDF LEVEL 07 FLAT 4 TERRACE WATERPROOFING DETAIL Superseded document · 14 Oct 2025 View ↗ PDF LEVEL 07 STAIR (A) ROOF WATERPROOFING DETAIL Superseded document · 14 Oct 2025 View ↗ PDF LEVEL 07 STAIR (B) PITCHED ROOF DETAILL Superseded document · 14 Oct 2025 View ↗ PDF LEVEL 02 SACKVILLE ST TERRACE AND JULIET BALCONY WATERPROOFING DETAIL Superseded document · 14 Oct 2025 View ↗ PDF STAIRWELL SUPPLY FANS ARRANGEMENT Superseded document · 14 Oct 2025 View ↗ PDF LEVEL 06 SACKVILLE ST INSET DORMER TYPE 1 Superseded document · 14 Oct 2025 View ↗ PDF LEVEL 06 OFFICE TERRACE ABUTMENT WATERPROOFING DETAILS Superseded document · 14 Oct 2025 View ↗ PDF LEVEL 06 OFFICE TERRACE ABUTMENT WATERPROOFING DETAILS Superseded document · 14 Oct 2025 View ↗ PDF SIXTH FLOOR GENERAL ARRANGEMENT Superseded document · 14 Oct 2025 View ↗ PDF SECOND FLOOR GENERAL ARRANGEMENT Superseded document · 14 Oct 2025 View ↗ PDF LEVEL 04 OFFICE TERRACE WATERPROOFING DETAIL Superseded document · 14 Oct 2025 View ↗ PDF LEVEL 04 OFFICE TERRACE WALL WATERPROOFING DETAIL Superseded document · 14 Oct 2025 View ↗ PDF LEVEL 05 SACKVILLE ST GUTTER WATERPROOFING DETAIL WITH BRACKET Superseded document · 14 Oct 2025 View ↗ PDF FIFTH FLOOR GENERAL ARRANGEMENT Superseded document · 14 Oct 2025 View ↗ PDF LEVEL 06 OFFICE TERRACE WATERPROOFING DETAILS Superseded document · 14 Oct 2025 View ↗ PDF LEVEL 06 SACKVILLE ST DORMER TYPE 3 Superseded document · 14 Oct 2025 View ↗

All documents on the council site ↗

Associated applications 15

Site constraints 11

Mayfair conservation area
Demolition needs planning permission and permitted development is restricted.
The council must give weight to preserving or enhancing the area's character and appearance. Not every council has published its boundaries as open data.
Council document ↗
2 Article 4 directions
Article 4 Basement Development Permitted Rights Removed · Article 4 Direction Class E To C3 In Central Activities Zone. Named permitted development rights are withdrawn here.
An Article 4 direction withdraws particular permitted development rights, so work that would normally need no application needs one here. Not every council has published its directions.
Archaeological priority area: City of Westminster APA 2.5
An assessment or field evaluation may be asked for before ground works.
The council or Historic England considers archaeology likely here. A desk-based assessment, and sometimes trial trenching, can be asked for with the application.
Air quality management area: Westminster AQMA
The council has declared the area as failing an air quality objective.
Schemes that add traffic, parking or combustion plant are assessed against the area's action plan and may need an air quality assessment.
Council record ↗
Town centre: West End
A designated centre in the London Plan.
Shops, services and active frontages are protected in centres, and main town centre uses are steered here first.
42 listed buildings within 150 m
Nearest: 36, Sackville Street W1, Grade II*, 10 m away · 4 Grade I, 10 Grade II*, 28 Grade II
The site itself is not listed. Listed building consent is needed for work that affects the special interest of a listed building, inside or out, on top of planning permission. Setting can be a consideration for buildings nearby; there is no fixed radius.
Show all 42 with distances
Historic England ↗
National infrastructure project 633 m away: Thames Tideway Tunnel
The site is 633 m from the project boundary. Waste water treatment, decided. The project page says whether consent was granted. Also within 2 km: London Strategic Heat Main Project (at pre-application, 378 m).
Nationally significant infrastructure projects (power stations, electricity lines, pipelines, major roads and railways, harbours, airports and reservoirs) are consented by a Secretary of State under the Planning Act 2008, after an examination by the Planning Inspectorate, rather than by the council. The boundary is the one the Inspectorate consults on and can change as the scheme does. Projects are shown within 2 km of the site.
Planning Inspectorate project page ↗
Central activities zone
The core of central London in the London Plan.
Offices, culture and the other strategic functions of the centre take priority over new housing here.
Also on the record
Registered park or garden 249 m away: St James's Square; Inside the City of Westminster built-up area; Public transport access: PTAL 6b (excellent), TfL 2023, for the 100 m square.
Not affected
Outside flood zones 2 and 3 · Not green belt · No scheduled monument at the site

Checked on 2 November 2026. Historic England, the Environment Agency, Natural England, the Planning Inspectorate, Transport for London (public transport access levels, Powered by TfL Open Data, OGL v3.0, contains OS data © Crown copyright and database right 2025) and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Building

Floor area83 m² (893 sq ft)
Energy ratingF (28 out of 100), could reach C
PropertyDetached flat, 2 habitable rooms
BuiltBefore 1900
HeatingRoom heaters, electric
WallsSolid brick, as built, no insulation (assumed)

From the energy performance certificate lodged in April 2015, the latest held for this property. The building may have changed since. View the certificate

Work with planning data?

Every application in Westminster - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Application type
Approval of Details (Full PP)
Postcode
W1S 3EH
Received
14 Oct 2025
Validated
11 Nov 2025
Ward
West End
Case officer
Show
Target decision
6 Jan 2026
Decision
Application Permitted
Decision date
12 Jan 2026
Decision level
Delegated Decision
Applicant
Show
Agent
Gerald Eve

How this decision compares

Decided in 62 days from validation, 25 days slower than Westminster's median of 37 for discharge of conditions. Approved, as 91% of discharge of conditions here are.

68%decided within 8 weeks
91%approved
1,908decided in the last year

Plota live figures for discharge of conditions decided by Westminster in the last twelve months, from validation. Westminster decision record →

Public comments

No public comments yet.

Last counted 9 Oct 2026

Read the comments on the council site ↗

Consultation & key dates

Alt. reference
PP-14367885
Planning Portal ref
PP-14367885
Env. assessment
No
Westminster
Planning Authority Score
3.5/10
Below average
#221 of 296 councils
Relevant to this application:
Householder decisions

Westminster is slower than most councils at deciding householder applications, ranking #258 out of 296. Only 28% of applications have the time limit extended, well below the 41% national average - the council usually decides on time. Westminster is also one of the strictest councils - it refuses more householder applications than almost any other, with only 81% approved vs 90% nationally.

One of the strictest councils
only 81% approved vs 90% nationally
These figures are council-wide context, not a prediction for this application. View full council performance
Westminster decision statistics
Based on MHCLG data, the year to March 2026
86%
Overall approval rate
Below avg (87%) #201 of 296
81%
Householder approved
Below avg (90%) #277 of 296
44%
Decided in 8 weeks
Below avg (63%) #258 of 296
28%
Extended time limit
Below avg (41%) #46 of 296
83%
Minor dwellings approved
12 decided (1-9 homes)
67%
Major dwellings approved
3 decided (10+ homes)
81%
Change of use approved
133 decided
4,602
Total decisions
648 refused in the year to March 2026

Energy performance: Energy performance certificates from the Energy Performance of Buildings Register, Ministry of Housing, Communities and Local Government. Contains public sector information licensed under the Open Government Licence v3.0. © Crown copyright 2026.