1 Rodney Road London Southwark SE17 1BA Data via plota.co.uk

25/AP/3252 - Major application Awaiting decision

Proposal

Erection of seven-storey building, plus basement to provide eleven dwellings with commercial and community floorspace on the ground floor, including associated landscaping, parking and refuse storage. Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
7 Nov 2025
✓
Validated
13 Nov 2025
Decision
Target date was 2 Oct 2026

Under consideration

No decision has been issued yet. Plota predicted a decision around 6 Nov 2026; it is now day 358.

Documents 71

Statements & assessments 25

PDF DESIGN AND ACCESS STATEMENT Design and Access statement · 9 Sept 2026 View ↗ PDF TT_VL_P24-3209_03TN FLOOD RISK ASSESSMENT TECHNICAL NOTE Flood risk assessment · 20 Aug 2026 View ↗ PDF TT/VL/P24-3209/02TN TECHNICAL NOTE TO LLFA COMMENTS Flood risk assessment · 19 Jun 2026 View ↗ PDF BNG METRIC Biodiversity BNG Metrics · 19 Jun 2026 View ↗ PDF SUPERSEDED DESIGN AND ACCESS STATEMENT Design and Access statement · 19 Jun 2026 View ↗ PDF VERSION 3.0 PEA AND PRA REPORT Biodiversity survey / ecology assessment · 19 Jun 2026 View ↗ PDF VERSION 2.0 ECOLOGICAL WALKOVER SURVEY Biodiversity survey / ecology assessment · 19 Jun 2026 View ↗ PDF BNG ASSESSMENT Biodiversity BNG Metrics · 19 Jun 2026 View ↗ PDF 1115_DN01.1 GATEWAY ONE RESPONSE Fire Statement · 19 Jun 2026 View ↗ PDF FIRE STATEMENT Fire Statement · 7 Nov 2025 View ↗ PDF DAYLIGHT OR SUNLIGHT ASSESSMENT Daylight/Sunlight assessment · 7 Nov 2025 View ↗ PDF HERITAGE STATEMENT Heritage statement · 7 Nov 2025 View ↗ PDF ENERGY STATEMENT Energy statement · 7 Nov 2025 View ↗ PDF PRELIMINARY ECOLOGICAL APPRAISAL AND PRELIMINARY ROOST ASSESSMENT Document - Superseded · 7 Nov 2025 View ↗ PDF TRANSPORT ASSESSMENT Transport assessment · 7 Nov 2025 View ↗ PDF PLANNING STATEMENT Planning statement · 7 Nov 2025 View ↗ PDF SUPERSEDED DESIGN AND ACCESS STATEMENT Document - Superseded · 7 Nov 2025 View ↗ PDF REVISION A BASEMENT SCREENING QUESTIONS, FLOOD RISK AND SURFACE WATER DRAINAGE ASSESSMENT Flood risk assessment · 7 Nov 2025 View ↗ PDF SUPERSEDED BIODIVERSITY NET GAIN ASSESSMENT Document - Superseded · 7 Nov 2025 View ↗ PDF BIODIVERSITY SURVEY AND REPORT Document - Superseded · 7 Nov 2025 View ↗ PDF SUPERSEDED BIODIVERSITY METRIC CALCULATION TOOL Document - Superseded · 7 Nov 2025 View ↗ PDF ARBTECH AIA 01 REV C Tree survey or Arboricultural implications · 7 Nov 2025 View ↗ PDF ARBORICULTURAL METHOD STATEMENT Tree survey or Arboricultural implications · 7 Nov 2025 View ↗ PDF ROD-P-100-P05 TREE PROTECTION SURVEY Tree survey or Arboricultural implications · 7 Nov 2025 View ↗ PDF 1 FINANCIAL VIABILITY ASSESSMENT (APPLICANT) Viability report · 7 Nov 2025 View ↗

Plans & drawings 25

PDF ROD_P_120 REV P10 PROPOSED SECOND FLOOR PLAN Plan - Amended · 9 Sept 2026 View ↗ PDF ROD_P_100 REV P08 PROPOSED GROUND FLOOR Plan - Amended · 19 Jun 2026 View ↗ PDF ROD_P_110 REV P10 PROPOSED FIRST FLOOR Plan - Amended · 19 Jun 2026 View ↗ PDF ROD_P_120 REV P09 PROPOSED SECOND FLOOR Plan - Superseded · 19 Jun 2026 View ↗ PDF ROD_P_130 REV P10 PROPOSED THIRD FLOOR Plan - Amended · 19 Jun 2026 View ↗ PDF ROD_P_140 REV P10 PROPOSED FOURTH FLOOR Plan - Amended · 19 Jun 2026 View ↗ PDF ROD_P_150 REV P10 PROPOSED FIFTH FLOOR Plan - Amended · 19 Jun 2026 View ↗ PDF ROD_P_160 REV P08 PROPOSED SIXTH FLOOR Plan - Amended · 19 Jun 2026 View ↗ PDF ROD_P_170 REV P06 PROPOSED ROOF PLAN Plan - Amended · 19 Jun 2026 View ↗ PDF ROD_P_210 REV P05 PROPOSED ELEVATIONS AND SECTIONS 02 Plan - Amended · 19 Jun 2026 View ↗ PDF ROD_P_220 REV P05 PROPOSED ELEVATIONS AND SECTIONS 03 Plan - Amended · 19 Jun 2026 View ↗ PDF ROD_P_310 REV P06 PROPOSED ELEVATIONS Plan - Amended · 19 Jun 2026 View ↗ PDF ROD- P-085 REV P03 PROPOSED ROOF PLAN Plan - Superseded · 7 Nov 2025 View ↗ PDF ROD-P- 090 REV P05 PROPOSED BASEMENT PLANS Plan - Proposed · 7 Nov 2025 View ↗ PDF ROD-P- 106 REV P06 PROPOSED GROUND FLOOR PLAN Plan - Superseded · 7 Nov 2025 View ↗ PDF ROD-P-110 REV P07 PROPOSED FIRST FLOOR PLAN Plan - Superseded · 7 Nov 2025 View ↗ PDF ROD-P-120- REV P06 PROPOSED SECOND FLOOR PLAN Plan - Superseded · 7 Nov 2025 View ↗ PDF ROD-P-130 REV P07 PROPOSED THIRD FLOOR PLAN Plan - Superseded · 7 Nov 2025 View ↗ PDF ROD-P--140- REV 107 PROPOSED FOURTH FLOOR PLAN Plan - Superseded · 7 Nov 2025 View ↗ PDF ROD-P-150 REV 107 PROPOSED FIFTH FLOOR PLAN Plan - Superseded · 7 Nov 2025 View ↗ PDF ROD-P-160 REV 105 PROPOSED SIXTH FLOOR PLAN Plan - Superseded · 7 Nov 2025 View ↗ PDF ROD-P- 170 REV P03 PROPOSED ROOF PLAN Plan - Superseded · 7 Nov 2025 View ↗ PDF ROD-P-210- REV P03 PROPOSED ELEVATION AND SECTION 02 PLANS Plan - Superseded · 7 Nov 2025 View ↗ PDF ROD -P-220 REV P03 PROPOSED ELEVATION AND SECTION 03 Plan - Superseded · 7 Nov 2025 View ↗ PDF ROD-P-310 REV P04 PROPOSED ELEVATION PLAN Plan - Superseded · 7 Nov 2025 View ↗

All documents on the council site ↗

Site constraints 15

Flood zone 3, rivers and sea
High chance: a 1 in 100 or greater annual chance from rivers, or 1 in 200 from the sea. Any development here needs a flood risk assessment. Defences are not counted.
The Environment Agency flood map for planning. Homes in zone 3 must also pass the sequential test. Surface water flooding is a separate map.
Flood map ↗
2 Article 4 directions
Central Activities Zone · Elephant and Castle Major Town Centre. Named permitted development rights are withdrawn here.
An Article 4 direction withdraws particular permitted development rights, so work that would normally need no application needs one here. Not every council has published its directions.
Tree preservation order: Trafalgar Place land bounded by Victory Place, Balfour St and Rodney Road SE17 1AS
Consent is needed before work on protected trees.
Not every council has published its orders as open data, so no order shown is not proof there is none.
Air quality management area: Southwark AQMA
The council has declared the area as failing an air quality objective.
Schemes that add traffic, parking or combustion plant are assessed against the area's action plan and may need an air quality assessment.
Council record ↗
Town centre: Elephant and Castle/ Walworth Road
A designated centre in the London Plan.
Shops, services and active frontages are protected in centres, and main town centre uses are steered here first.
Habitat network: Network Enhancement Zone 2
Where habitat is joined up enough to work as a network. Context, not a constraint on its own.
Central activities zone
The core of central London in the London Plan.
Offices, culture and the other strategic functions of the centre take priority over new housing here.
2 listed buildings within 150 m of the postcode pin
Nearest: Lady Margaret Church, Grade II, about 42 m from the postcode pin · 2 Grade II
The site itself is not listed. Listed building consent is needed for work that affects the special interest of a listed building, inside or out, on top of planning permission. Setting can be a consideration for buildings nearby; there is no fixed radius.
Show all 2 with distances
Historic England ↗
National infrastructure project about 952 m away: Thames Tideway Tunnel
The site is about 952 m from the project boundary. Waste water treatment, decided. The project page says whether consent was granted. Also within 2 km: London Strategic Heat Main Project (at pre-application, about 398 m).
Nationally significant infrastructure projects (power stations, electricity lines, pipelines, major roads and railways, harbours, airports and reservoirs) are consented by a Secretary of State under the Planning Act 2008, after an examination by the Planning Inspectorate, rather than by the council. The boundary is the one the Inspectorate consults on and can change as the scheme does. Projects are shown within 2 km of the site.
Planning Inspectorate project page ↗
Opportunity area
Where the London Plan expects significant growth.
Boundaries are indicative and the borough holds the detailed plan.
Conservation area about 22 m away: Yates Estate and Victory
The edge of the area; work outside it can still affect its setting.
The council must give weight to preserving or enhancing the area's character and appearance. Not every council has published its boundaries as open data.
Council document ↗
Also on the record
Wider setting of protected view 1A.2 Alexandra Palace viewing terrace to St Paul's Cathedral; 23A.1 Centre of Bridge over the Serpentine to the Palace of Westminster; Radon affected area, class 2; Inside the Southwark built-up area; Public transport access: PTAL 6b (excellent), TfL 2023, for the 100 m square.
Not affected
Not green belt · No scheduled monument at the site

Checked on 2 November 2026. The pin for this application is the centre of its postcode rather than the building, so distances to nearby designations are measured from the postcode and can be out by the width of the postcode area. Historic England, the Environment Agency, Natural England, the Planning Inspectorate, the British Geological Survey and UK Health Security Agency (radon, contains BGS materials © UKRI), Transport for London (public transport access levels, Powered by TfL Open Data, OGL v3.0, contains OS data © Crown copyright and database right 2025) and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Work with planning data?

Every application in Southwark - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Council
Southwark
Application type
Major application
Postcode
SE17 1BA
Received
7 Nov 2025
Validated
13 Nov 2025
Ward
North Walworth
Parish
Borough, Bankside And Walworth
Case officer
Show
Target decision
2 Oct 2026
Applicant
Show
Agent
Planning Potential

Decision outlook

Day 358, past the statutory target. 76% of full applications in Southwark are decided within thirteen weeks; extensions of time are common, and the council need not decide on the day. Last seen undecided on 4 Nov 2026.

Day 358267 days past the 91-day target
55%decided within 8 weeks
87%approved
540decided in the last year

Plota live figures for full applications decided by Southwark in the last twelve months, from validation. Southwark decision record →

Public comments

3comments received
3 supporting

100% support · above the UK average of 16%

647 neighbours consulted · Last counted 4 Nov 2026

Read the comments on the council site ↗

Consultation & key dates

Statutory expiry
12 Feb 2026
Env. assessment
No
Southwark
Planning Authority Score
7/10
Good
#64 of 296 councils
Relevant to this application:
Major dwellings

Southwark is faster than most councils at deciding householder applications, ranking #54 out of 296. Householder applications are slightly more likely to be approved here (95%) than the national average (90%).

Faster than most councils
for householder decisions
These figures are council-wide context, not a prediction for this application. View full council performance
Southwark decision statistics
Based on MHCLG data, the year to March 2026
92%
Overall approval rate
Above avg (87%) #93 of 296
95%
Householder approved
Above avg (90%) #92 of 296
78%
Decided in 8 weeks
Above avg (63%) #54 of 296
37%
Extended time limit
Below avg (41%) #122 of 296
92%
Minor dwellings approved
259 decided (1-9 homes)
86%
Major dwellings approved
14 decided (10+ homes)
82%
Change of use approved
38 decided
1,622
Total decisions
132 refused in the year to March 2026