Peninsular House 30 - 36 Monument Street London EC3R 8LJ Data via plota.co.uk

26/00952/FULMAJ - Full Major Application Under Consideration

Proposal

Refurbishment and extension of the existing building at the front, tenth and eleventh floors, alteration to City Walkway and all enabling works associated with the development and a change of use from Office (Class E(g)) to deliver a new Hotel (Class C1). Data via plota.co.uk

View original council record ↗

Application progress

Received
3 Jul 2026
Validated
17 Jul 2026
Consultation
22 Jul 2026
Decision
Awaiting decision

This application is under consideration - no decision has been issued yet. The consultation period closed on 21 Aug 2026.

Documents 121

Statements & assessments 43

PDF CLIMATE CHANGE RESLIENCE SUSTAINABILITY STATEMENT Accompanying report · 6 Jul 2026 View ↗ PDF CIRCULAR ECONOMY STATEMENT REPORT Accompanying report · 6 Jul 2026 View ↗ PDF CIRCULAR ECONOMY STATEMENT TEMPLATE Other · 6 Jul 2026 View ↗ PDF SUSTAINABILITY STATEMENT Accompanying report · 6 Jul 2026 View ↗ PDF WHOLE LIFECYCLE CARBON ASSESSMENT (WLCA) REPORT Accompanying report · 6 Jul 2026 View ↗ PDF WHOLE LIFECYCLE CARBON ASSESSMENT (WLCA) TEMPLATE Accompanying report · 6 Jul 2026 View ↗ PDF NOISE ASSESSMENT Report - Acoustic/Noise Report · 3 Jul 2026 View ↗ PDF AIR QUALITY ASSESSMENT Accompanying report · 3 Jul 2026 View ↗ PDF ARCHAEOLOGICAL DESK-BASED ASSESSMENT Report - Archaeological Report · 3 Jul 2026 View ↗ PDF DAS 01 INTRODUCTION Report - Design & Access Statement/Report · 3 Jul 2026 View ↗ PDF DAS 03 CONSULTATION Report - Design & Access Statement/Report · 3 Jul 2026 View ↗ PDF DAS 04 DESIGN EVALUATION AND PROPOSAL 3 OF 3 Report - Design & Access Statement/Report · 3 Jul 2026 View ↗ PDF DAS 05 PROPOSAL IN CONTEXT 1 OF 3 Report - Design & Access Statement/Report · 3 Jul 2026 View ↗ PDF DAS 05 PROPOSAL IN CONTEXT 2 OF 3 Report - Design & Access Statement/Report · 3 Jul 2026 View ↗ PDF DAS 05 PROPOSAL IN CONTEXT 3 OF 3 Report - Design & Access Statement/Report · 3 Jul 2026 View ↗ PDF DAS 07 ACCESSIBILITY Report - Design & Access Statement/Report · 3 Jul 2026 View ↗ PDF DAS 08 TRANSPORT AND SERVICING Report - Design & Access Statement/Report · 3 Jul 2026 View ↗ PDF DAS 09 LIGHTING STRATEGY Report - Design & Access Statement/Report · 3 Jul 2026 View ↗ PDF DAS 10 FIRE STRATEGY Report - Design & Access Statement/Report · 3 Jul 2026 View ↗ PDF DAS 11 SUICIDE PREVENTION STRATEGY Report - Design & Access Statement/Report · 3 Jul 2026 View ↗ PDF DAS 04 DESIGN EVALUATION AND PROPOSAL 1 OF 3_COMPRESSED Report - Design & Access Statement/Report · 3 Jul 2026 View ↗ PDF DAS 04 DESIGN EVALUATION AND PROPOSAL 2 OF 3_COMPRESSED Report - Design & Access Statement/Report · 3 Jul 2026 View ↗ PDF DAS 06 SUSTAINABILITY APPROACH_COMPRESSED Report - Design & Access Statement/Report · 3 Jul 2026 View ↗ PDF FIRE STATEMENT Accompanying report · 3 Jul 2026 View ↗ PDF SUSTAINABLE DRAINAGE STRATEGY Accompanying report · 3 Jul 2026 View ↗ PDF FINANCIAL VIABILITY ASSESSMENT & MARKETING REPORT Accompanying report · 3 Jul 2026 View ↗ PDF ACCESS STATEMENT Report - Access Statement · 3 Jul 2026 View ↗ PDF LANDSCAPE STATEMENT-PART1 Accompanying report · 3 Jul 2026 View ↗ PDF SOCIO-ECONOMIC STATEMENT Accompanying report · 3 Jul 2026 View ↗ PDF TRANSPORT STATEMENT Report - Transport Statement/Report · 3 Jul 2026 View ↗ PDF HERITAGE, TOWNSCAPE AND VISUAL IMPACT ASSESSMENT_PART2 Accompanying report · 3 Jul 2026 View ↗ PDF HERITAGE, TOWNSCAPE AND VISUAL IMPACT ASSESSMENT_PART3 Accompanying report · 3 Jul 2026 View ↗ PDF PENINSULAR HOUSE PLANNING STATEMENT (FINAL) Report - Planning Statement/Report · 3 Jul 2026 View ↗ PDF LANDSCAPE STATEMENT-PART3 Accompanying report · 3 Jul 2026 View ↗ PDF LANDSCAPE STATEMENT-PART4 Accompanying report · 3 Jul 2026 View ↗ PDF LANDSCAPE STATEMENT-PART2 Accompanying report · 3 Jul 2026 View ↗ PDF ENERGY AND SUSTAINABILITY ASSESSMENT Accompanying report · 3 Jul 2026 View ↗ PDF HERITAGE, TOWNSCAPE AND VISUAL IMPACT ASSESSMENT_PART1 Accompanying report · 3 Jul 2026 View ↗ PDF PRELIMINARY ECOLOGICAL ASSESSMENT Accompanying report · 3 Jul 2026 View ↗ PDF FLOOD RISK ASSESSMENT Accompanying report · 3 Jul 2026 View ↗ PDF STATEMENT OF COMMUNITY INVOLVEMENT Accompanying report · 3 Jul 2026 View ↗ PDF RAPID HEALTH IMPACT ASSESSMENT Accompanying report · 3 Jul 2026 View ↗ PDF HERITAGE, TOWNSCAPE AND VISUAL IMPACT ASSESSMENT_PART4 Accompanying report · 3 Jul 2026 View ↗

Plans & drawings 70

PDF PROPOSED SEVENTH FLOOR DEMOLITION PLAN Drawing · 17 Jul 2026 View ↗ PDF EXISTING SITE PLAN Site Plan · 3 Jul 2026 View ↗ PDF EXISTING BASEMENT -2 FLOOR PLAN P0 Drawing · 3 Jul 2026 View ↗ PDF EXISTING BASEMENT -1 FLOOR PLAN P0 Drawing · 3 Jul 2026 View ↗ PDF EXISTING GROUND FLOOR PLAN P0 Drawing · 3 Jul 2026 View ↗ PDF EXISTING FIRST FLOOR PLAN P0-A Drawing · 3 Jul 2026 View ↗ PDF EXISTING SECOND FLOOR PLAN P0 Drawing · 3 Jul 2026 View ↗ PDF EXISTING THIRD FLOOR PLAN P0 Drawing · 3 Jul 2026 View ↗ PDF EXISTING FOURTH FLOOR PLAN P0 Drawing · 3 Jul 2026 View ↗ PDF EXISTING FIFTH FLOOR PLAN P0 Drawing · 3 Jul 2026 View ↗ PDF EXISTING SIXTH FLOOR PLAN P0 Drawing · 3 Jul 2026 View ↗ PDF EXISTING SEVENTH FLOOR PLAN P0 Drawing · 3 Jul 2026 View ↗ PDF EXISTING EIGHTH FLOOR PLAN P0 Drawing · 3 Jul 2026 View ↗ PDF EXISTING NINTH FLOOR PLAN P0 Drawing · 3 Jul 2026 View ↗ PDF EXISTING ROOF PLAN P0 Drawing · 3 Jul 2026 View ↗ PDF EXISTING NORTH ELEVATION P0 Drawing · 3 Jul 2026 View ↗ PDF EXISTING WEST ELEVATION P0 Drawing · 3 Jul 2026 View ↗ PDF EXISTING EAST ELEVATION P0 Drawing · 3 Jul 2026 View ↗ PDF EXISTING SECTION B-B P0 Drawing · 3 Jul 2026 View ↗ PDF EXISTING SECTION C-C P0 Drawing · 3 Jul 2026 View ↗ PDF PROPOSED BASEMENT -2 DEMOLITION PLAN P0 Drawing · 3 Jul 2026 View ↗ PDF PROPOSED GROUND FLOOR DEMOLITION PLAN P0 Drawing · 3 Jul 2026 View ↗ PDF PROPOSED SECOND FLOOR DEMOLITION PLAN P0 Drawing · 3 Jul 2026 View ↗ PDF PROPOSED THIRD FLOOR DEMOLITION PLAN P0 Drawing · 3 Jul 2026 View ↗ PDF PROPOSED FOURTH FLOOR DEMOLITION PLAN P0 Drawing · 3 Jul 2026 View ↗ PDF PROPOSED FIFTH FLOOR DEMOLITION PLAN P0 Drawing · 3 Jul 2026 View ↗ PDF PROPOSED TENTH FLOOR DEMOLITION PLAN P0 Drawing · 3 Jul 2026 View ↗ PDF PROPOSED ROOF DEMOLITION PLAN P0 Drawing · 3 Jul 2026 View ↗ PDF PROPOSED DEMOLITION - SECTION A-A P0 Drawing · 3 Jul 2026 View ↗ PDF PROPOSED DEMOLITION - SECTION B-B P0 Drawing · 3 Jul 2026 View ↗ PDF PROPOSED DEMOLITION - EAST ELEVATION P0 Drawing · 3 Jul 2026 View ↗ PDF PROPOSED DEMOLITION - NORTH ELEVATION P0 Drawing · 3 Jul 2026 View ↗ PDF PROPOSED DEMOLITION - SOUTH ELEVATION P0 Drawing · 3 Jul 2026 View ↗ PDF PROPOSED DEMOLITION - WEST ELEVATION P0 Drawing · 3 Jul 2026 View ↗ PDF PROPOSED BASEMENT -1 FLOOR PLAN P0 Drawing · 3 Jul 2026 View ↗ PDF PROPOSED FIRST FLOOR PLAN P0 Drawing · 3 Jul 2026 View ↗ PDF PROPOSED SECOND FLOOR PLAN P0 Drawing · 3 Jul 2026 View ↗ PDF PROPOSED THIRD FLOOR PLAN P0 Drawing · 3 Jul 2026 View ↗ PDF PROPOSED FIFTH FLOOR PLAN P0 Drawing · 3 Jul 2026 View ↗ PDF PROPOSED SEVENTH FLOOR PLAN P0 Drawing · 3 Jul 2026 View ↗ PDF PROPOSED EIGHTH FLOOR PLAN P0 Drawing · 3 Jul 2026 View ↗ PDF PROPOSED TENTH FLOOR PLAN P0 Drawing · 3 Jul 2026 View ↗ PDF PROPOSED ELEVENTH FLOOR PLAN P0 Drawing · 3 Jul 2026 View ↗ PDF PROPOSED SOUTH ELEVATION P0 Drawing · 3 Jul 2026 View ↗ PDF PROPOSED EAST ELEVATION P0 Drawing · 3 Jul 2026 View ↗ PDF TRAVEL PLAN Report - Travel Plan · 3 Jul 2026 View ↗ PDF EXISTING SECTION A-A P0 Drawing · 3 Jul 2026 View ↗ PDF PROPOSED SITE PLAN P0 Drawing · 3 Jul 2026 View ↗ PDF PROPOSED GROUND FLOOR PLAN P0 Drawing · 3 Jul 2026 View ↗ PDF PROPOSED FOURTH FLOOR PLAN P0 Drawing · 3 Jul 2026 View ↗ PDF SITE LOCATION PLAN P0 Site Plan · 3 Jul 2026 View ↗ PDF EXISTING TENTH FLOOR PLAN P0 Drawing · 3 Jul 2026 View ↗ PDF EXISTING SOUTH ELEVATION P0 Drawing · 3 Jul 2026 View ↗ PDF PROPOSED FIRST FLOOR DEMOLITION PLAN P0 Drawing · 3 Jul 2026 View ↗ PDF PROPOSED SIXTH FLOOR DEMOLITION PLAN P0 Drawing · 3 Jul 2026 View ↗ PDF PROPOSED EIGHTH FLOOR DEMOLITION PLAN P0 Drawing · 3 Jul 2026 View ↗ PDF PROPOSED DEMOLITION - SECTION C-C P0 Drawing · 3 Jul 2026 View ↗ PDF PROPOSED BASEMENT -2 FLOOR PLAN P0 Drawing · 3 Jul 2026 View ↗ PDF PROPOSED ROOF PLAN P0 Drawing · 3 Jul 2026 View ↗ PDF PROPOSED SECTION A-A P0 Drawing · 3 Jul 2026 View ↗ PDF DELIVERY AND SERVICING MANAGEMENT PLAN Accompanying report · 3 Jul 2026 View ↗ PDF CONSTRUCTION AND DEMOLITION MANAGEMENT PLAN Accompanying report · 3 Jul 2026 View ↗ PDF PROPOSED BASEMENT -1 DEMOLITION PLAN P0 Drawing · 3 Jul 2026 View ↗ PDF PROPOSED NINTH FLOOR DEMOLITION PLAN P0 Drawing · 3 Jul 2026 View ↗ PDF PROPOSED SIXTH FLOOR PLAN P0 Drawing · 3 Jul 2026 View ↗ PDF PROPOSED NINTH FLOOR PLAN P0 Drawing · 3 Jul 2026 View ↗ PDF PROPOSED NORTH ELEVATION P0 Drawing · 3 Jul 2026 View ↗ PDF PROPOSED WEST ELEVATION P0 Drawing · 3 Jul 2026 View ↗ PDF PROPOSED SECTION B-B P0 Drawing · 3 Jul 2026 View ↗ PDF PROPOSED SECTION C-C P0 Drawing · 3 Jul 2026 View ↗

All documents on the council site ↗

Work with planning data? Every application in City of London - and every UK council - as a live feed or API. About Plota's data service

Important details

Application type
Full Major Application
Postcode
EC3R 8LJ
Received
3 Jul 2026
Validated
17 Jul 2026
Ward
Bridge And Bridge Without
Case officer
Show
Target decision
16 Oct 2026
Decision level
Delegated
Applicant
Show
Agent
DP9

Public comments

No public comments yet.

98 neighbours consulted · Last counted 17 Aug 2026

Read the comments on the council site ↗

Consultation & key dates

Alt. reference
PP-15048996
Neighbours
27 Jul 2026
Consultation
22 Jul 2026
Comments by
21 Aug 2026
Site notice
31 Jul 2026
Press notice
21 Jul 2026
Env. assessment
No
City of London
Planning Authority Score
6.7/10
Good
#71 of 296 councils
Relevant to this application:
Change of use

City of London is one of the fastest councils in England for householder decisions, ranking #1 out of 296. The council extends the time limit on 84% of applications - one of the highest rates in England. Expect your application to take longer than the standard deadline. Householder applications are more likely to be approved here than most councils, with a 100% approval rate vs 90% nationally.

Among the fastest councils in England
for householder decisions
These figures are council-wide context, not a prediction for this application. View full council performance
City of London decision performance
Based on MHCLG data, the year to March 2026
97%
Overall approval rate
Above avg (87%) #3 of 296
100%
Householder approved
Above avg (90%) #1 of 296
100%
Decided in 8 weeks
Above avg (63%) #1 of 296
84%
Extended time limit
Above avg (41%) #296 of 296
50%
Minor dwellings approved
4 decided (1-9 homes)
91%
Change of use approved
22 decided
460
Total decisions
14 refused in the year to March 2026