Peninsular House 30 - 36 Monument Street London EC3R 8LJ Data via plota.co.uk

26/00952/FULMAJ - Full Major Application Under Consideration

Proposal

Refurbishment and extension of the existing building at the front, tenth and eleventh floors, alteration to City Walkway and all enabling works associated with the development and a change of use from Office (Class E(g)) to deliver a new Hotel (Class C1). Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
3 Jul 2026
✓
Validated
17 Jul 2026
✓
Consultation
26 Aug 2026
Decision
Expected by 16 Oct 2026

Under consideration

No decision has been issued yet. Plota predicted a decision soon after comments close on 30 Sept 2026; it is now day 84.

The consultation period closed on 30 Sept 2026.

Documents 121

Statements & assessments 43

PDF CLIMATE CHANGE RESLIENCE SUSTAINABILITY STATEMENT Accompanying report · 6 Jul 2026 View ↗ PDF CIRCULAR ECONOMY STATEMENT REPORT Accompanying report · 6 Jul 2026 View ↗ PDF CIRCULAR ECONOMY STATEMENT TEMPLATE Other · 6 Jul 2026 View ↗ PDF SUSTAINABILITY STATEMENT Accompanying report · 6 Jul 2026 View ↗ PDF WHOLE LIFECYCLE CARBON ASSESSMENT (WLCA) REPORT Accompanying report · 6 Jul 2026 View ↗ PDF WHOLE LIFECYCLE CARBON ASSESSMENT (WLCA) TEMPLATE Accompanying report · 6 Jul 2026 View ↗ PDF NOISE ASSESSMENT Report - Acoustic/Noise Report · 3 Jul 2026 View ↗ PDF AIR QUALITY ASSESSMENT Accompanying report · 3 Jul 2026 View ↗ PDF ARCHAEOLOGICAL DESK-BASED ASSESSMENT Report - Archaeological Report · 3 Jul 2026 View ↗ PDF DAS 01 INTRODUCTION Report - Design & Access Statement/Report · 3 Jul 2026 View ↗ PDF DAS 03 CONSULTATION Report - Design & Access Statement/Report · 3 Jul 2026 View ↗ PDF DAS 04 DESIGN EVALUATION AND PROPOSAL 3 OF 3 Report - Design & Access Statement/Report · 3 Jul 2026 View ↗ PDF DAS 05 PROPOSAL IN CONTEXT 1 OF 3 Report - Design & Access Statement/Report · 3 Jul 2026 View ↗ PDF DAS 05 PROPOSAL IN CONTEXT 2 OF 3 Report - Design & Access Statement/Report · 3 Jul 2026 View ↗ PDF DAS 05 PROPOSAL IN CONTEXT 3 OF 3 Report - Design & Access Statement/Report · 3 Jul 2026 View ↗ PDF DAS 07 ACCESSIBILITY Report - Design & Access Statement/Report · 3 Jul 2026 View ↗ PDF DAS 08 TRANSPORT AND SERVICING Report - Design & Access Statement/Report · 3 Jul 2026 View ↗ PDF DAS 09 LIGHTING STRATEGY Report - Design & Access Statement/Report · 3 Jul 2026 View ↗ PDF DAS 10 FIRE STRATEGY Report - Design & Access Statement/Report · 3 Jul 2026 View ↗ PDF DAS 11 SUICIDE PREVENTION STRATEGY Report - Design & Access Statement/Report · 3 Jul 2026 View ↗ PDF DAS 04 DESIGN EVALUATION AND PROPOSAL 1 OF 3_COMPRESSED Report - Design & Access Statement/Report · 3 Jul 2026 View ↗ PDF DAS 04 DESIGN EVALUATION AND PROPOSAL 2 OF 3_COMPRESSED Report - Design & Access Statement/Report · 3 Jul 2026 View ↗ PDF DAS 06 SUSTAINABILITY APPROACH_COMPRESSED Report - Design & Access Statement/Report · 3 Jul 2026 View ↗ PDF FIRE STATEMENT Accompanying report · 3 Jul 2026 View ↗ PDF SUSTAINABLE DRAINAGE STRATEGY Accompanying report · 3 Jul 2026 View ↗ PDF FINANCIAL VIABILITY ASSESSMENT & MARKETING REPORT Accompanying report · 3 Jul 2026 View ↗ PDF ACCESS STATEMENT Report - Access Statement · 3 Jul 2026 View ↗ PDF LANDSCAPE STATEMENT-PART1 Accompanying report · 3 Jul 2026 View ↗ PDF SOCIO-ECONOMIC STATEMENT Accompanying report · 3 Jul 2026 View ↗ PDF TRANSPORT STATEMENT Report - Transport Statement/Report · 3 Jul 2026 View ↗ PDF HERITAGE, TOWNSCAPE AND VISUAL IMPACT ASSESSMENT_PART2 Accompanying report · 3 Jul 2026 View ↗ PDF HERITAGE, TOWNSCAPE AND VISUAL IMPACT ASSESSMENT_PART3 Accompanying report · 3 Jul 2026 View ↗ PDF PENINSULAR HOUSE PLANNING STATEMENT (FINAL) Report - Planning Statement/Report · 3 Jul 2026 View ↗ PDF LANDSCAPE STATEMENT-PART3 Accompanying report · 3 Jul 2026 View ↗ PDF LANDSCAPE STATEMENT-PART4 Accompanying report · 3 Jul 2026 View ↗ PDF LANDSCAPE STATEMENT-PART2 Accompanying report · 3 Jul 2026 View ↗ PDF ENERGY AND SUSTAINABILITY ASSESSMENT Accompanying report · 3 Jul 2026 View ↗ PDF HERITAGE, TOWNSCAPE AND VISUAL IMPACT ASSESSMENT_PART1 Accompanying report · 3 Jul 2026 View ↗ PDF PRELIMINARY ECOLOGICAL ASSESSMENT Accompanying report · 3 Jul 2026 View ↗ PDF FLOOD RISK ASSESSMENT Accompanying report · 3 Jul 2026 View ↗ PDF STATEMENT OF COMMUNITY INVOLVEMENT Accompanying report · 3 Jul 2026 View ↗ PDF RAPID HEALTH IMPACT ASSESSMENT Accompanying report · 3 Jul 2026 View ↗ PDF HERITAGE, TOWNSCAPE AND VISUAL IMPACT ASSESSMENT_PART4 Accompanying report · 3 Jul 2026 View ↗

Plans & drawings 70

PDF PROPOSED SEVENTH FLOOR DEMOLITION PLAN Drawing · 17 Jul 2026 View ↗ PDF EXISTING SITE PLAN Site Plan · 3 Jul 2026 View ↗ PDF EXISTING BASEMENT -2 FLOOR PLAN P0 Drawing · 3 Jul 2026 View ↗ PDF EXISTING BASEMENT -1 FLOOR PLAN P0 Drawing · 3 Jul 2026 View ↗ PDF EXISTING GROUND FLOOR PLAN P0 Drawing · 3 Jul 2026 View ↗ PDF EXISTING FIRST FLOOR PLAN P0-A Drawing · 3 Jul 2026 View ↗ PDF EXISTING SECOND FLOOR PLAN P0 Drawing · 3 Jul 2026 View ↗ PDF EXISTING THIRD FLOOR PLAN P0 Drawing · 3 Jul 2026 View ↗ PDF EXISTING FOURTH FLOOR PLAN P0 Drawing · 3 Jul 2026 View ↗ PDF EXISTING FIFTH FLOOR PLAN P0 Drawing · 3 Jul 2026 View ↗ PDF EXISTING SIXTH FLOOR PLAN P0 Drawing · 3 Jul 2026 View ↗ PDF EXISTING SEVENTH FLOOR PLAN P0 Drawing · 3 Jul 2026 View ↗ PDF EXISTING EIGHTH FLOOR PLAN P0 Drawing · 3 Jul 2026 View ↗ PDF EXISTING NINTH FLOOR PLAN P0 Drawing · 3 Jul 2026 View ↗ PDF EXISTING ROOF PLAN P0 Drawing · 3 Jul 2026 View ↗ PDF EXISTING NORTH ELEVATION P0 Drawing · 3 Jul 2026 View ↗ PDF EXISTING WEST ELEVATION P0 Drawing · 3 Jul 2026 View ↗ PDF EXISTING EAST ELEVATION P0 Drawing · 3 Jul 2026 View ↗ PDF EXISTING SECTION B-B P0 Drawing · 3 Jul 2026 View ↗ PDF EXISTING SECTION C-C P0 Drawing · 3 Jul 2026 View ↗ PDF PROPOSED BASEMENT -2 DEMOLITION PLAN P0 Drawing · 3 Jul 2026 View ↗ PDF PROPOSED GROUND FLOOR DEMOLITION PLAN P0 Drawing · 3 Jul 2026 View ↗ PDF PROPOSED SECOND FLOOR DEMOLITION PLAN P0 Drawing · 3 Jul 2026 View ↗ PDF PROPOSED THIRD FLOOR DEMOLITION PLAN P0 Drawing · 3 Jul 2026 View ↗ PDF PROPOSED FOURTH FLOOR DEMOLITION PLAN P0 Drawing · 3 Jul 2026 View ↗ PDF PROPOSED FIFTH FLOOR DEMOLITION PLAN P0 Drawing · 3 Jul 2026 View ↗ PDF PROPOSED TENTH FLOOR DEMOLITION PLAN P0 Drawing · 3 Jul 2026 View ↗ PDF PROPOSED ROOF DEMOLITION PLAN P0 Drawing · 3 Jul 2026 View ↗ PDF PROPOSED DEMOLITION - SECTION A-A P0 Drawing · 3 Jul 2026 View ↗ PDF PROPOSED DEMOLITION - SECTION B-B P0 Drawing · 3 Jul 2026 View ↗ PDF PROPOSED DEMOLITION - EAST ELEVATION P0 Drawing · 3 Jul 2026 View ↗ PDF PROPOSED DEMOLITION - NORTH ELEVATION P0 Drawing · 3 Jul 2026 View ↗ PDF PROPOSED DEMOLITION - SOUTH ELEVATION P0 Drawing · 3 Jul 2026 View ↗ PDF PROPOSED DEMOLITION - WEST ELEVATION P0 Drawing · 3 Jul 2026 View ↗ PDF PROPOSED BASEMENT -1 FLOOR PLAN P0 Drawing · 3 Jul 2026 View ↗ PDF PROPOSED FIRST FLOOR PLAN P0 Drawing · 3 Jul 2026 View ↗ PDF PROPOSED SECOND FLOOR PLAN P0 Drawing · 3 Jul 2026 View ↗ PDF PROPOSED THIRD FLOOR PLAN P0 Drawing · 3 Jul 2026 View ↗ PDF PROPOSED FIFTH FLOOR PLAN P0 Drawing · 3 Jul 2026 View ↗ PDF PROPOSED SEVENTH FLOOR PLAN P0 Drawing · 3 Jul 2026 View ↗ PDF PROPOSED EIGHTH FLOOR PLAN P0 Drawing · 3 Jul 2026 View ↗ PDF PROPOSED TENTH FLOOR PLAN P0 Drawing · 3 Jul 2026 View ↗ PDF PROPOSED ELEVENTH FLOOR PLAN P0 Drawing · 3 Jul 2026 View ↗ PDF PROPOSED SOUTH ELEVATION P0 Drawing · 3 Jul 2026 View ↗ PDF PROPOSED EAST ELEVATION P0 Drawing · 3 Jul 2026 View ↗ PDF TRAVEL PLAN Report - Travel Plan · 3 Jul 2026 View ↗ PDF EXISTING SECTION A-A P0 Drawing · 3 Jul 2026 View ↗ PDF PROPOSED SITE PLAN P0 Drawing · 3 Jul 2026 View ↗ PDF PROPOSED GROUND FLOOR PLAN P0 Drawing · 3 Jul 2026 View ↗ PDF PROPOSED FOURTH FLOOR PLAN P0 Drawing · 3 Jul 2026 View ↗ PDF SITE LOCATION PLAN P0 Site Plan · 3 Jul 2026 View ↗ PDF EXISTING TENTH FLOOR PLAN P0 Drawing · 3 Jul 2026 View ↗ PDF EXISTING SOUTH ELEVATION P0 Drawing · 3 Jul 2026 View ↗ PDF PROPOSED FIRST FLOOR DEMOLITION PLAN P0 Drawing · 3 Jul 2026 View ↗ PDF PROPOSED SIXTH FLOOR DEMOLITION PLAN P0 Drawing · 3 Jul 2026 View ↗ PDF PROPOSED EIGHTH FLOOR DEMOLITION PLAN P0 Drawing · 3 Jul 2026 View ↗ PDF PROPOSED DEMOLITION - SECTION C-C P0 Drawing · 3 Jul 2026 View ↗ PDF PROPOSED BASEMENT -2 FLOOR PLAN P0 Drawing · 3 Jul 2026 View ↗ PDF PROPOSED ROOF PLAN P0 Drawing · 3 Jul 2026 View ↗ PDF PROPOSED SECTION A-A P0 Drawing · 3 Jul 2026 View ↗ PDF DELIVERY AND SERVICING MANAGEMENT PLAN Accompanying report · 3 Jul 2026 View ↗ PDF CONSTRUCTION AND DEMOLITION MANAGEMENT PLAN Accompanying report · 3 Jul 2026 View ↗ PDF PROPOSED BASEMENT -1 DEMOLITION PLAN P0 Drawing · 3 Jul 2026 View ↗ PDF PROPOSED NINTH FLOOR DEMOLITION PLAN P0 Drawing · 3 Jul 2026 View ↗ PDF PROPOSED SIXTH FLOOR PLAN P0 Drawing · 3 Jul 2026 View ↗ PDF PROPOSED NINTH FLOOR PLAN P0 Drawing · 3 Jul 2026 View ↗ PDF PROPOSED NORTH ELEVATION P0 Drawing · 3 Jul 2026 View ↗ PDF PROPOSED WEST ELEVATION P0 Drawing · 3 Jul 2026 View ↗ PDF PROPOSED SECTION B-B P0 Drawing · 3 Jul 2026 View ↗ PDF PROPOSED SECTION C-C P0 Drawing · 3 Jul 2026 View ↗

All documents on the council site ↗

Site constraints 11

Protected view corridor: 5A.2 Greenwich Park Wolfe statue to St Paul's Cathedral
Inside the landmark viewing corridor of a protected vista. A building that rises above the corridor's threshold height should be refused. How high that is depends on where along the view the site is. Also in the wider setting of 4A.1 Primrose Hill summit to St Paul's Cathedral.
The London Plan (policy HC4) designates strategic views, and the Mayor's London View Management Framework (March 2012) gives 13 of them a protected vista toward St Paul's Cathedral, the Palace of Westminster or the Tower of London. A vista has a threshold height that rises or falls with the line of sight. In the landmark viewing corridor, a building above it would harm the view and should be refused. In the wider setting consultation area around the corridor, a building above it is referred for consultation and its effect on the view is judged. The threshold changes along each view and is set out in the framework. A revised framework is out for consultation until 4 December 2026 and is not yet in force.
London View Management Framework ↗
Archaeological priority area
An assessment or field evaluation may be asked for before ground works.
The council or Historic England considers archaeology likely here. A desk-based assessment, and sometimes trial trenching, can be asked for with the application.
Air quality management area: City of London AQMA
The council has declared the area as failing an air quality objective.
Schemes that add traffic, parking or combustion plant are assessed against the area's action plan and may need an air quality assessment.
Council record ↗
National infrastructure project about 20 m away: Thames Tideway Tunnel
The site is about 20 m from the project boundary. Waste water treatment, decided. The project page says whether consent was granted. Also within 2 km: London Strategic Heat Main Project (at pre-application, about 378 m).
Nationally significant infrastructure projects (power stations, electricity lines, pipelines, major roads and railways, harbours, airports and reservoirs) are consented by a Secretary of State under the Planning Act 2008, after an examination by the Planning Inspectorate, rather than by the council. The boundary is the one the Inspectorate consults on and can change as the scheme does. Projects are shown within 2 km of the site.
Planning Inspectorate project page ↗
Scheduled monument about 66 m away: Monument
Its setting is a consideration for work nearby.
Nationally important archaeology protected by the Secretary of State. Work that affects the monument or its setting is rarely permitted.
Historic England ↗
Central activities zone
The core of central London in the London Plan.
Offices, culture and the other strategic functions of the centre take priority over new housing here.
16 listed buildings within 150 m of the postcode pin
Nearest: Church of St Magnus the Martyr, Grade I, about 61 m from the postcode pin · 4 Grade I, 2 Grade II*, 10 Grade II
The site itself is not listed. Listed building consent is needed for work that affects the special interest of a listed building, inside or out, on top of planning permission. Setting can be a consideration for buildings nearby; there is no fixed radius.
Show all 16 with distances
Historic England ↗
Also on the record
Conservation area about 26 m away: Eastcheap; Inside the City and County of the City of London built-up area; Public transport access: PTAL 6b (excellent), TfL 2023, for the 100 m square; Designated open space about 32 m away.
Not affected
Outside flood zones 2 and 3 · Not green belt

Checked on 6 October 2026. The pin for this application is the centre of its postcode rather than the building, so distances to nearby designations are measured from the postcode and can be out by the width of the postcode area. Historic England, the Environment Agency, Natural England, the Planning Inspectorate, Transport for London (public transport access levels, Powered by TfL Open Data, OGL v3.0, contains OS data © Crown copyright and database right 2025) and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Work with planning data?

Every application in City of London - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Application type
Full Major Application
Postcode
EC3R 8LJ
Received
3 Jul 2026
Validated
17 Jul 2026
Ward
Bridge And Bridge Without
Case officer
Show
Target decision
16 Oct 2026
Decision level
Delegated
Applicant
Show
Agent
DP9
Leaseholder
Show

Decision outlook

Day 84, past the statutory target. 68% of extensions in City of London are decided within thirteen weeks, which runs to 16 Oct 2026; extensions of time are common, and the council need not decide on the day. Last seen undecided on 7 Oct 2026.

Day 8428 days past the 56-day target
30%decided within 8 weeks
100%approved
115decided in the last year

Plota live figures for extensions decided by City of London in the last twelve months, from validation. City of London decision record →

Public comments

No public comments yet.

97 neighbours consulted · Last counted 7 Oct 2026

Read the comments on the council site ↗

Consultation & key dates

Alt. reference
PP-15048996
Planning Portal ref
PP-15048996
Neighbours
2 Sept 2026
Consultation
26 Aug 2026
Comments by
30 Sept 2026
Site or press notice
31 Jul 2026
Statutory expiry
16 Oct 2026
Env. assessment
No
City of London
Planning Authority Score
6.7/10
Good
#71 of 296 councils
Relevant to this application:
Change of use

City of London is one of the fastest councils in England for householder decisions, ranking #1 out of 296. The council extends the time limit on 84% of applications - one of the highest rates in England. Expect your application to take longer than the standard deadline. Householder applications are more likely to be approved here than most councils, with a 100% approval rate vs 90% nationally.

Among the fastest councils in England
for householder decisions
These figures are council-wide context, not a prediction for this application. View full council performance
City of London decision statistics
Based on MHCLG data, the year to March 2026
97%
Overall approval rate
Above avg (87%) #3 of 296
100%
Householder approved
Above avg (90%) #1 of 296
100%
Decided in 8 weeks
Above avg (63%) #1 of 296
84%
Extended time limit
Above avg (41%) #296 of 296
50%
Minor dwellings approved
4 decided (1-9 homes)
91%
Change of use approved
22 decided
460
Total decisions
14 refused in the year to March 2026

Leaseholders: Information produced by HM Land Registry. © Crown copyright 2026. Source: HM Land Registry, UK and overseas companies that own property in England and Wales, September 2026 release.