1 Undershaft London EC3A 8EE Data via plota.co.uk

2024/4603/P - Request for Observations to Adjoining Borough WITHDRAWN

Proposal

Demolition of the existing buildings, retention and partial expansion of existing basement plus construction of a ground, plus 73 storey building (plus plant) for office use (Use Class E(g)); Retail/food and beverage (Use Class E(a)-(b)); Public amenity space (Flexible Class E(a)-(d) / Class F1 / Sui Generis); publicly accessible education space and viewing gallery at levels 72 and 73 (Sui Generis); public cycle hub (Sui Generis); plus podium garden at level 11, installation of a digital screen, public realm improvement works, ancillary basement cycle parking, servicing, plant, highway works and other works associated with the proposed development. Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
24 Oct 2024
Decision
Target date was 19 Dec 2024

Under consideration

No decision has been issued yet. Plota predicted a decision around 9 Nov 2026; it is now day 746.

Site constraints 10

Archaeological priority area
An assessment or field evaluation may be asked for before ground works.
The council or Historic England considers archaeology likely here. A desk-based assessment, and sometimes trial trenching, can be asked for with the application.
Air quality management area: City of London AQMA
The council has declared the area as failing an air quality objective.
Schemes that add traffic, parking or combustion plant are assessed against the area's action plan and may need an air quality assessment.
Council record ↗
National infrastructure project about 527 m away: Thames Tideway Tunnel
The site is about 527 m from the project boundary. Waste water treatment, decided. The project page says whether consent was granted. Also within 2 km: London Strategic Heat Main Project (at pre-application, about 163 m).
Nationally significant infrastructure projects (power stations, electricity lines, pipelines, major roads and railways, harbours, airports and reservoirs) are consented by a Secretary of State under the Planning Act 2008, after an examination by the Planning Inspectorate, rather than by the council. The boundary is the one the Inspectorate consults on and can change as the scheme does. Projects are shown within 2 km of the site.
Planning Inspectorate project page ↗
Central activities zone
The core of central London in the London Plan.
Offices, culture and the other strategic functions of the centre take priority over new housing here.
17 listed buildings within 150 m of the postcode pin
Nearest: Church of St Helen, Grade I, about 43 m from the postcode pin · 5 Grade I, 1 Grade II*, 8 Grade II
The site itself is not listed. Listed building consent is needed for work that affects the special interest of a listed building, inside or out, on top of planning permission. Setting can be a consideration for buildings nearby; there is no fixed radius.
Show all 17 with distances
Historic England ↗
Also on the record
Conservation area about 41 m away: St Helen's Place; Scheduled monument about 188 m away: London Wall: remains of Roman wall and bastion, Camomile Street; Inside the City and County of the City of London built-up area; Public transport access: PTAL 6b (excellent), TfL 2023, for the 100 m square; Designated open space about 13 m away.
Not affected
Outside flood zones 2 and 3 · Not green belt

Checked on 3 November 2026. The pin for this application is the centre of its postcode rather than the building, so distances to nearby designations are measured from the postcode and can be out by the width of the postcode area. Historic England, the Environment Agency, Natural England, the Planning Inspectorate, Transport for London (public transport access levels, Powered by TfL Open Data, OGL v3.0, contains OS data © Crown copyright and database right 2025) and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Work with planning data?

Every application in Camden - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Council
Camden
Application type
Request for Observations to Adjoining Borough
Postcode
EC3A 8EE
Validated
24 Oct 2024
Ward
Holborn and Covent Garden
Case officer
Show
Decision level
Withdrawn-Council
Applicant
Show

Decision outlook

Day 746, past the statutory target. 41% of commercial and major works in Camden are decided within thirteen weeks; extensions of time are common, and the council need not decide on the day. Last seen undecided on 2 Oct 2026.

Day 746690 days past the 56-day target
31%decided within 8 weeks
96%approved
31%go to committee

Plota live figures for commercial and major works decided by Camden in the last twelve months, from validation. Camden decision record →

Camden
Planning Authority Score
3.1/10
Poor
#231 of 296 councils
Relevant to this application:
Householder decisions

Camden is slower than most councils at deciding householder applications, ranking #242 out of 296. Householder applications are slightly less likely to be approved here (88%) than the national average (90%).

Slower than most councils
for householder decisions
These figures are council-wide context, not a prediction for this application. View full council performance
Camden decision statistics
Based on MHCLG data, the year to March 2026
88%
Overall approval rate
Above avg (87%) #149 of 296
88%
Householder approved
Below avg (90%) #215 of 296
49%
Decided in 8 weeks
Below avg (63%) #242 of 296
41%
Extended time limit
Below avg (41%) #158 of 296
90%
Minor dwellings approved
467 decided (1-9 homes)
80%
Major dwellings approved
10 decided (10+ homes)
93%
Change of use approved
46 decided
1,973
Total decisions
234 refused in the year to March 2026