Planning decisions in West Lancashire

How long West Lancashire takes to decide a planning application and how many it approves, from the 516 decisions it made in the twelve months to August 2026. Days run from validation to decision, the clock the council reports against; the wait from receipt is shown beside it. How the figures are made.

54 daysmedian from validation to decision (UK 52); 56 from receipt
60%decided within eight weeks (UK 73%), 92% within thirteen
86%approved (UK 89%): 398 approved, 65 refused, 12 withdrawn
216 of 321UK rank for speed, up 42 places on last year; 246 of 321 for approvals
056 September 2025: 62 days, 79 decisionsSeptOctober 2025: 51 days, 123 decisionsOctNovember 2025: 60 days, 88 decisionsNovDecember 2025: 61 days, 91 decisionsDecJanuary 2026: 11 days, 2 decisionsJanFebruary 2026: 42 days, 20 decisionsFebMarch 2026: 47 days, 69 decisionsMarApril 2026: 51 days, 100 decisionsAprMay 2026: 65 days, 83 decisionsMayJune 2026: 67 days, 71 decisionsJunJuly 2026: 56 days, 82 decisionsJulAugust 2026: 56 days, 89 decisionsAug
Median days from validation to decision, by month of decision. Dashed line: UK median (52 days). Grid at 56 and 91 days, the eight and thirteen week targets.

By kind of application

KindMedian daysWithin 8 weeksApprovedDecisionsUK rank
Full applications (including householder)6440%83%203280 of 302
Tree works3085%97%12165 of 259
Lawful development certificates5656%95%61236 of 253
Discharge of conditions5167%93%47103 of 175
Prior approvals *4194%25%4182 of 168
Outline applications *4979%57%1517 of 39
Amendments *25100%83%1239 of 263

Delegated or committee

RouteShareMedian daysApprovedDecisions
Delegated to officers99%5783%336
Planning committee1%12175%4

Where the register states how the decision was made. 176 decisions did not say.

Appeals

48 appeals against West Lancashire decisions were decided by the Planning Inspectorate in the window, 74 for every 100 refusals; 38% were allowed. Every appeal in West Lancashire.

By year

Year decidedMedian daysWithin 8 weeksApprovedDecisions
2016 *6428%85%579
2017 *5750%73%96
2018 *5453%100%147
2019 *4867%74%92
2020 *5453%74%76
2021 *1985%100%220
2022 *10515%85%30
2023 *3983%95%285
2024 *5750%100%174
2025 *4671%72%76
2026 so far5651%86%516

* Years from our archive, which carries no validation date: timed from receipt, so a few days longer than the live years above them.

Decided in the last three weeks

Built nightly from West Lancashire's planning register. Ranks are among the 321 published councils. See planning applications in West Lancashire, appeals, or get alerts for West Lancashire.

About these figures

How are decision times measured?
Days from the date the council validated the application to the date it decided it, for applications approved or refused in the window. That is the clock councils report against and the official statistics use. Each council’s page also shows the count from receipt, which is what the applicant actually waited. Withdrawn and undecided applications are not timed.
Why do these figures differ from the council’s own?
Councils count an agreed extension of time as decided on time; we treat the calendar as the calendar. Our figures are also live and rolling, where official statistics are quarterly and annual. So a council’s own within-eight-weeks figure will usually sit a little above ours.
What counts as approved?
Approval rate is approvals divided by approvals plus refusals. Withdrawals, and decisions whose outcome the register does not state, are counted in the totals but not in the rate.
Why is a council missing?
A council is published when it has at least 25 timed decisions in the window and its register’s decision data passes our consistency checks. Councils that fail are listed with the reason rather than shown with a number that would mislead.
How often is this updated?
Nightly, from the decisions we collect from every council register we monitor. The window is the twelve months to the last complete month.