Planning decisions in Telford
How long Telford takes to decide a planning application and how many it approves, from the 919 decisions it made in the twelve months to September 2026. Days run from validation to decision, the clock the council reports against; the wait from receipt is shown beside it. How the figures are made.
48 daysmedian from validation to decision (UK 54); 48 from receipt
95%decided within eight weeks (UK 66%), 98% within thirteen
93%approved (UK 90%): 764 approved, 60 refused, 92 withdrawn
57 of 388UK rank for speed, up 55 places on last year; 160 of 388 for approvals
By kind of application
| Kind | Median days | Within 8 weeks | Approved | Decisions | UK rank |
|---|---|---|---|---|---|
| Full applications | 50 | 93% | 93% | 521 | 10 of 359 |
| Tree works | 34 | 100% | 94% | 106 | 89 of 324 |
| Lawful development certificates * | 42 | 100% | 86% | 65 | 56 of 348 |
| Prior approvals * | 38 | 88% | 92% | 57 | 201 of 340 |
| Advertisement consent * | 49 | 100% | 92% | 54 | 37 of 320 |
| Listed building consent * | 51 | 90% | 93% | 54 | 15 of 307 |
| Amendments * | 52 | 100% | 100% | 44 | 232 of 356 |
By year
| Year decided | Median days | Within 8 weeks | Approved | Decisions |
|---|---|---|---|---|
| 2016 * | 56 | 53% | 95% | 44 |
| 2017 * | 59 | 46% | 97% | 39 |
| 2018 * | 39 | 90% | 99% | 90 |
| 2019 * | 39 | 84% | 99% | 80 |
| 2020 * | 35 | 70% | 91% | 48 |
| 2021 * | 46 | 73% | 97% | 33 |
| 2022 * | 42 | 68% | 95% | 41 |
| 2023 * | 54 | 59% | 98% | 63 |
| 2024 * | 57 | 44% | 100% | 33 |
| 2025 * | 62 | 38% | 97% | 39 |
| 2026 so far | 48 | 95% | 93% | 705 |
* Years from our archive, which carries no validation date: timed from receipt, so a few days longer than the live years above them.
Decided in the last three weeks
- 9 Aldermead Close, Admaston, Telford, Shropshire, TF5 0DDErection of a single storey side and rear extension and half rear extension to the existing garage to provide a workshop and annexe accommodApproved23 Oct 2026
- Braeside, 43 Belmont Road, Ironbridge, Telford, Shropshire, TF8 7QTFelling of 1no. Sycamore tree and 1no. Holly Bush treeApproved23 Oct 2026
- 65 Pepper Mill, Lawley Village, Telford, Shropshire, TF4 2FBErection of a summer houseApproved21 Oct 2026
- 12 Greenacres Way, Newport, Shropshire, TF10 7PQErection of a first floor side extension with proposed car port below and erection of a single storey rear extensionApproved21 Oct 2026
- The Place, Limes Walk, Oakengates, Telford, Shropshire, TF2 6EPVariation of Conditions 3 (wayfinding), 7 (sound insulation), 8 (noise levels), 9 (car parking improvements), 14 (air handling units and airApproved21 Oct 2026
- 212 The Tuckies, Salthouse Road, Jackfield, Telford, Shropshire, TF8 7LTRemoval of 1no. Common Ash treeApproved20 Oct 2026
- 167 Masons Place, Newport, Shropshire, TF10 7JXReduce overextended limbs encroaching over the Western Power transformer and associated distribution plant, reshape and reduce the remainingApproved20 Oct 2026
- 16 Church Hill, Ironbridge, Telford, Shropshire, TF8 7PWRemoval of 1no. Silver Birch treeApproved20 Oct 2026
Built nightly from Telford's planning register. Ranks are among the 388 published councils. See planning applications in Telford, appeals, or get alerts for Telford.
About these figures
How are decision times measured?
Days from the date the council validated the application to the date it decided it, for applications approved or refused in the window. That is the clock councils report against and the official statistics use. Each council’s page also shows the count from receipt, which is what the applicant actually waited. Withdrawn and undecided applications are not timed.
Why do these figures differ from the council’s own?
Councils count an agreed extension of time as decided on time; we treat the calendar as the calendar. Our figures are also live and rolling, where official statistics are quarterly and annual. So a council’s own within-eight-weeks figure will usually sit a little above ours.
What counts as approved?
Approval rate is approvals divided by approvals plus refusals. Withdrawals, and decisions whose outcome the register does not state, are counted in the totals but not in the rate.
Why is a council missing?
A council is published when it has at least 25 timed decisions in the window and its register’s decision data passes our consistency checks. Councils that fail are listed with the reason rather than shown with a number that would mislead.
How often is this updated?
Nightly, from the decisions we collect from every council register we monitor. The window is the twelve months to the last complete month.