Planning decisions in Pembroke Coast
How long Pembroke Coast takes to decide a planning application and how many it approves, from the 587 decisions it made in the twelve months to September 2026. Days run from validation to decision, the clock the council reports against; the wait from receipt is shown beside it. How the figures are made.
55 daysmedian from validation to decision (UK 54); 55 from receipt
60%decided within eight weeks (UK 66%), 80% within thirteen
85%approved (UK 90%): 389 approved, 69 refused, 38 withdrawn
244 of 388UK rank for speed, down 195 places on last year; 330 of 388 for approvals
By kind of application
| Kind | Median days | Within 8 weeks | Approved | Decisions | UK rank |
|---|---|---|---|---|---|
| Full applications | 58 | 48% | 85% | 300 | 182 of 359 |
| Discharge of conditions * | 54 | 78% | 70% | 99 | 170 of 310 |
| Amendments | 41 | 76% | 89% | 63 | 122 of 356 |
| Tree works | 37 | 95% | 100% | 46 | 137 of 324 |
| Listed building consent | 49 | 87% | 100% | 26 | 9 of 307 |
| Lawful development certificates * | 76 | 38% | 42% | 19 | 345 of 348 |
| Advertisement consent * | 53 | 70% | 83% | 13 | 98 of 320 |
Delegated or committee
| Route | Share | Median days | Approved | Decisions |
|---|---|---|---|---|
| Delegated to officers | 97% | 54 | 85% | 484 |
| Planning committee | 3% | 96 | 85% | 14 |
Where the register states how the decision was made. 89 decisions did not say.
By year
| Year decided | Median days | Within 8 weeks | Approved | Decisions |
|---|---|---|---|---|
| 2016 * | 30 | 96% | 98% | 56 |
| 2017 * | 50 | 82% | 99% | 78 |
| 2018 * | 50 | 65% | 96% | 30 |
| 2019 * | 63 | 40% | 88% | 27 |
| 2020 * | 71 | 43% | 79% | 30 |
| 2021 * | 32 | 64% | 89% | 29 |
| 2022 * | 44 | 64% | 100% | 44 |
| 2023 * | 50 | 59% | 94% | 35 |
| 2024 * | 48 | 70% | 100% | 56 |
| 2025 * | 100 | 20% | 92% | 25 |
| 2026 so far | 55 | 54% | 85% | 477 |
* Years from our archive, which carries no validation date: timed from receipt, so a few days longer than the live years above them.
Past their target date now
- Elm House, Jameston, Tenby, Pembrokeshire, SA70 8QJConstruction of a farm track to provide access for agricultural use (fully retrospective)due 6 Nov 2025
- Y Fagal, Moylegrove, Cardigan, Pembrokeshire, SA43 3BUErection of potting shed/ workshop and re-grading of land.due 18 Nov 2025
- Upper House, Llandruidion, Haverfordwest, Pembrokeshire, SA62 6UGDivision of existing farmhouse to form 1no. 2 bed and 1no. 3 Bed Property, conversion of existing outbuildings for residential use 3no. 2 &due 17 Dec 2025
- Caerwen, Pontfaen, Fishguard, Pembrokeshire, SA65 9TPRetrospective Rural Enterprise Dwellingdue 25 Dec 2025
- Land north of Whitlow, Narberth Road, Saundersfoot, Pembrokeshire, SA69 9BEReconfiguration of part of site layout and substitution of approved residential apartments with dwellinghouse types (known as Phase 3) upondue 13 Jan 2026
- Conifers, Feidr Brenin, Parrog, Newport, Pembrokeshire, SA42 0RZCertificate for Lawful Development for campervan and campsitedue 15 Jan 2026
- Southern Pits Farm, Lawrenny, Kilgetty, Pembrokeshire, SA68 0PYRetrospective siting of 2no. agricultural workers static caravans for a period of 12 yearsdue 28 Jan 2026
- 4, Temple Terrace, Upper West Street, Newport, Pembrokeshire, SA42 0THDischarge of condition 5 (photographic survey) of NP/22/0408/FULdue 9 Feb 2026
Decided in the last three weeks
- 6, Southlands, Tenby, Pembrokeshire, SA70 8HUT1 Holm Oak - prune in accordance with annotated plan, T2 Ash - prune in accordaApproved26 Oct 2026
- Gwynne House, Bridge Street, Tenby, Pembrokeshire, SA70 7BUCertificate of lawfulness (4 Year Rule) for the use of the ground & upper floorsApproved26 Oct 2026
- Rose Cottage, 7, Glanhafan, Solva, Haverfordwest, Pembrokeshire, SA62 6TAProposed change of use from a residential C3(a) Dwellinghouse, to a new tearoomApproved26 Oct 2026
- Rowston Holiday Park, New Hedges, Tenby, Pembrokeshire, SA70 8TLAmendments to NP/25/0149/FUL due to safeguarding of retained treesApproved23 Oct 2026
- White Berries, Long Street, Newport, Pembrokeshire, SA42 0TJ1 x Silver Birch - thin canopy by 20 percent with overall reduction of 30 percenApproved23 Oct 2026
- Sands Cafe, Newgale Hill, Newgale, Haverfordwest, Pembrokeshire, SA62 6ASDesign amendment to NP/21/0133/FUL & NP/22/0701/NMAApproved23 Oct 2026
- White Gates, Stammers Road, Saundersfoot, Pembrokeshire, SA69 9HHT1 Oak - prune in accordance with annotated images & raise crown above road 5.2mApproved23 Oct 2026
- 8, Nyth Gwennol, Saundersfoot, Pembrokeshire, SA69 9PW2 x Oak - raise crown, deadwood, selective 10 percent crown thinApproved23 Oct 2026
Built nightly from Pembroke Coast's planning register. Ranks are among the 388 published councils. See planning applications in Pembroke Coast, or get alerts for Pembroke Coast.
About these figures
How are decision times measured?
Days from the date the council validated the application to the date it decided it, for applications approved or refused in the window. That is the clock councils report against and the official statistics use. Each council’s page also shows the count from receipt, which is what the applicant actually waited. Withdrawn and undecided applications are not timed.
Why do these figures differ from the council’s own?
Councils count an agreed extension of time as decided on time; we treat the calendar as the calendar. Our figures are also live and rolling, where official statistics are quarterly and annual. So a council’s own within-eight-weeks figure will usually sit a little above ours.
What counts as approved?
Approval rate is approvals divided by approvals plus refusals. Withdrawals, and decisions whose outcome the register does not state, are counted in the totals but not in the rate.
Why is a council missing?
A council is published when it has at least 25 timed decisions in the window and its register’s decision data passes our consistency checks. Councils that fail are listed with the reason rather than shown with a number that would mislead.
How often is this updated?
Nightly, from the decisions we collect from every council register we monitor. The window is the twelve months to the last complete month.