Planning decisions in Hambleton
How long Hambleton takes to decide a planning application and how many it approves, from the 1,001 decisions it made in the twelve months to September 2026. Days run from validation to decision, the clock the council reports against; the wait from receipt is shown beside it. How the figures are made.
55 daysmedian from validation to decision (UK 54); 58 from receipt
63%decided within eight weeks (UK 66%), 87% within thirteen
92%approved (UK 90%): 848 approved, 74 refused, 59 withdrawn
240 of 388UK rank for speed, down 5 places on last year; 180 of 388 for approvals
By kind of application
| Kind | Median days | Within 8 weeks | Approved | Decisions | UK rank |
|---|---|---|---|---|---|
| Full applications | 56 | 52% | 94% | 428 | 147 of 359 |
| Tree works | 41 | 92% | 84% | 165 | 187 of 324 |
| Discharge of conditions | 56 | 56% | 100% | 112 | 225 of 310 |
| Prior approvals | 28 | 93% | 90% | 86 | 92 of 340 |
| Amendments | 52 | 70% | 99% | 82 | 237 of 356 |
| Listed building consent | 67 | 30% | 84% | 69 | 207 of 307 |
| Lawful development certificates | 55 | 62% | 92% | 29 | 253 of 348 |
| Outline applications * | 106 | 25% | 75% | 15 | 95 of 110 |
Delegated or committee
| Route | Share | Median days | Approved | Decisions |
|---|---|---|---|---|
| Delegated to officers | over 99% | 54 | 94% | 703 |
| Planning committee | under 1% | 210 | 100% | 1 |
Where the register states how the decision was made. 297 decisions did not say.
By year
| Year decided | Median days | Within 8 weeks | Approved | Decisions |
|---|---|---|---|---|
| 2016 * | 60 | 37% | 85% | 27 |
| 2017 * | 75 | 32% | 93% | 28 |
| 2018 * | 72 | 22% | 84% | 34 |
| 2019 * | 56 | 51% | 96% | 319 |
| 2020 * | 72 | 24% | 96% | 100 |
| 2021 * | 74 | 18% | 97% | 107 |
| 2022 * | 155 | 15% | 97% | 102 |
| 2023 * | 63 | 34% | 100% | 81 |
| 2024 * | 83 | 16% | 94% | 97 |
| 2025 * | 77 | 30% | 89% | 39 |
| 2026 so far | 59 | 47% | 92% | 987 |
* Years from our archive, which carries no validation date: timed from receipt, so a few days longer than the live years above them.
Past their target date now
- Goulton Grange Farm Potto Northallerton North Yorkshire DL6 3HPProposed agricultural workers' dwellingdue 1 Sept 2025
- Land On The South West Side Of 11 Harkness Drive Leeming Bar North Yorkshire DL7 9BBApplication for approval of details reserved by condition numbers, 3 (Engineering Drawings), 6 (Surface Water Drainage Details), 8 (Drainagedue 4 Sept 2025
- Plum Tree Cottage Crathorne Yarm North Yorkshire TS15 0BAApplication for demolition of rear lobby/porch and outbuilding to build single storey extention to rear and side.due 9 Sept 2025
- Plum Tree Cottage Crathorne Yarm North Yorkshire TS15 0BAListed Building application for demolition of rear lobby/porch and build single storey extension to rear and side. New Windows and Internaldue 9 Sept 2025
- Ayton Firs Green Lane Great Ayton North Yorkshire TS9 6JBChange of use of building to dwellingdue 16 Sept 2025
- Land Adjacent 53 Water End Brompton North YorkshireRevised full plans application for a detached dwelling with integral garagedue 22 Sept 2025
- Fir Tree Farm House Easby Middlesbrough North Yorkshire TS9 6LHGeneral purpose steel framed agricultural buildingdue 23 Sept 2025
- Springwell Nurseries Stainton Road Seamer Middlesbrough North Yorkshire TS9 5NAApplication for Approval of Details Reserved by Condition: 4 (Site levels), 6 (contamination report), 7 (Foul and surface water), 8 (Road andue 29 Sept 2025
Decided in the last three weeks
- Former Ingleby Arncliffe Church Of England Vc Primary School Ingleby Arncliffe Village Ingleby Arncliffe North Yorkshire DL6 3NAApplication for a non-material amendment (Plots 01 to 04: Minor elevation revision: PV panelling located to both sides of the roof rather thApproved26 Oct 2026
- Shire Cottage Thirkleby Hall Thirkleby Park Thirkleby North Yorkshire YO7 3ARListed Building consent for the replacement of Two existing first-floor windows.Approved26 Oct 2026
- 22 Phoenix Grove Northallerton North Yorkshire DL7 8PNAlterations to existing dwelling to form a glazed sun canopy and sliding/folding patio doors.Approved26 Oct 2026
- Monk Park Farm Visitors Centre Monk Park Farm Green Lane Balk North Yorkshire YO7 2AGProposed Amenity BuildingApproved23 Oct 2026
- 33 Cooper Lane Potto North Yorkshire DL6 3HEAlterations and extensions to existing dwelling, including an increase in roof heightApproved23 Oct 2026
- Broughton Grange Farm High Street Great Broughton North Yorkshire TS9 7HEPrior approval for the change of use of an agricultural building to a new flexible Class E use (Commercial, business or service) under the pApproved23 Oct 2026
- 9A St Giles Close Thirsk North Yorkshire YO7 3BUApplication for the construction of a single storey side extension to east elevationApproved23 Oct 2026
- Storage Section Next To Unit 6, Olive Grove Plews Way, Leeming Bar Ind Estate Leeming Bar DL7 9UGApplication for change of use of an outdoor storage area into a community wellness hub and the addition of an enclosed open wooden externalApproved23 Oct 2026
Built nightly from Hambleton's planning register. Ranks are among the 388 published councils. See planning applications in Hambleton, appeals, or get alerts for Hambleton.
About these figures
How are decision times measured?
Days from the date the council validated the application to the date it decided it, for applications approved or refused in the window. That is the clock councils report against and the official statistics use. Each council’s page also shows the count from receipt, which is what the applicant actually waited. Withdrawn and undecided applications are not timed.
Why do these figures differ from the council’s own?
Councils count an agreed extension of time as decided on time; we treat the calendar as the calendar. Our figures are also live and rolling, where official statistics are quarterly and annual. So a council’s own within-eight-weeks figure will usually sit a little above ours.
What counts as approved?
Approval rate is approvals divided by approvals plus refusals. Withdrawals, and decisions whose outcome the register does not state, are counted in the totals but not in the rate.
Why is a council missing?
A council is published when it has at least 25 timed decisions in the window and its register’s decision data passes our consistency checks. Councils that fail are listed with the reason rather than shown with a number that would mislead.
How often is this updated?
Nightly, from the decisions we collect from every council register we monitor. The window is the twelve months to the last complete month.