Planning decisions in Burnley

How long Burnley takes to decide a planning application and how many it approves, from the 446 decisions it made in the twelve months to September 2026. Days run from validation to decision, the clock the council reports against; the wait from receipt is shown beside it. How the figures are made.

52 daysmedian from validation to decision (UK 54); 56 from receipt
69%decided within eight weeks (UK 66%), 88% within thirteen
86%approved (UK 90%): 358 approved, 60 refused, 17 withdrawn
151 of 388UK rank for speed, up 104 places on last year; 325 of 388 for approvals
056 October 2025: 44 days, 35 decisionsOctNovember 2025: 56 days, 32 decisionsNovDecember 2025: 57 days, 33 decisionsDecJanuary 2026: 53 days, 30 decisionsJanFebruary 2026: 76 days, 29 decisionsFebMarch 2026: 54 days, 45 decisionsMarApril 2026: 57 days, 38 decisionsAprMay 2026: 64 days, 32 decisionsMayJune 2026: 66 days, 48 decisionsJunJuly 2026: 54 days, 40 decisionsJulAugust 2026: 57 days, 41 decisionsAugSeptember 2026: 56 days, 43 decisionsSept
Median days from validation to decision, by month of decision. Dashed line: UK median (54 days). Grid at 56 and 91 days, the eight and thirteen week targets.

By kind of application

KindMedian daysWithin 8 weeksApprovedDecisionsUK rank
Full applications5561%82%13574 of 359
Householder applications5276%89%10642 of 200
Discharge of conditions4570%95%4666 of 310
Lawful development certificates5181%75%34144 of 348
Prior approvals4190%81%34250 of 340
Amendments3768%96%27108 of 356
Advertisement consent *5178%78%2369 of 320
Tree works *7733%95%22318 of 324
Listed building consent *5575%92%1449 of 307

Delegated or committee

RouteShareMedian daysApprovedDecisions
Delegated to officers96%5286%428
Planning committee4%8489%18

Where the register states how the decision was made.

Appeals

23 appeals against Burnley decisions were decided by the Planning Inspectorate in the window, 38 for every 100 refusals; 17% were allowed. Every appeal in Burnley.

By year

Year decidedMedian daysWithin 8 weeksApprovedDecisions
2016 *5742%100%26
2017 *5749%89%35
2018 *6428%96%27
2019 *5655%97%33
2020 *7129%85%52
2021 *5651%38%39
2022 *6436%84%25
2023 *5748%96%28
2024 *5748%92%25
2025 *5064%80%25
2026 so far5749%83%346

* Years from our archive, which carries no validation date: timed from receipt, so a few days longer than the live years above them.

Past their target date now

Decided in the last three weeks

Built nightly from Burnley's planning register. Ranks are among the 388 published councils. See planning applications in Burnley, appeals, or get alerts for Burnley.

About these figures

How are decision times measured?
Days from the date the council validated the application to the date it decided it, for applications approved or refused in the window. That is the clock councils report against and the official statistics use. Each council’s page also shows the count from receipt, which is what the applicant actually waited. Withdrawn and undecided applications are not timed.
Why do these figures differ from the council’s own?
Councils count an agreed extension of time as decided on time; we treat the calendar as the calendar. Our figures are also live and rolling, where official statistics are quarterly and annual. So a council’s own within-eight-weeks figure will usually sit a little above ours.
What counts as approved?
Approval rate is approvals divided by approvals plus refusals. Withdrawals, and decisions whose outcome the register does not state, are counted in the totals but not in the rate.
Why is a council missing?
A council is published when it has at least 25 timed decisions in the window and its register’s decision data passes our consistency checks. Councils that fail are listed with the reason rather than shown with a number that would mislead.
How often is this updated?
Nightly, from the decisions we collect from every council register we monitor. The window is the twelve months to the last complete month.