Planning decisions in Ashford
How long Ashford takes to decide a planning application and how many it approves, from the 974 decisions it made in the twelve months to August 2026. Days run from validation to decision, the clock the council reports against; the wait from receipt is shown beside it. How the figures are made.
63 daysmedian from validation to decision (UK 52)
43%decided within eight weeks (UK 73%), 72% within thirteen
91%approved (UK 89%): 833 approved, 79 refused, 62 withdrawn
207 of 339UK rank for speed, down 63 places on last year; 164 of 339 for approvals
By year
| Year decided | Median days | Within 8 weeks | Approved | Decisions |
|---|---|---|---|---|
| 2016 * | 68 | 36% | 97% | 153 |
| 2017 * | 52 | 69% | 85% | 247 |
| 2018 * | 99 | 14% | 95% | 152 |
| 2019 * | 60 | 42% | 100% | 36 |
| 2020 * | 32 | 73% | 89% | 149 |
| 2021 * | 64 | 42% | 85% | 175 |
| 2022 * | 41 | 82% | 99% | 105 |
| 2023 * | 121 | 14% | 89% | 166 |
| 2024 * | 74 | 31% | 83% | 164 |
| 2025 * | 45 | 76% | 84% | 240 |
* Years from our archive, which carries no validation date: timed from receipt, so a few days longer than the live years above them.
Past their target date now
- Ashford Prep School, Ashford Road, Great Chart, TN23 3DJListed Building Consent for the repair of masonry garden wall; to include a section of the wall being removed in its entirety, from the gatedue 23 Mar 2026
- Ferramenta, Market Place, Charing, TN27 0LRListed Building Consent to replace windows with white slimline frames, including first floor window to front elevation to open inwards withdue 25 Mar 2026
- Agricutural Buildings rear of, Hornes Place Oast, Kenardington Road, AppledoreDetails submitted pursuant to Condition 3 (contamination) of planning permission PA/2025/2074.due 27 Mar 2026
- Land at Chilmington Green, Ashford Road, Great ChartDetails submitted pursuant to condition 16 (Surface Water Drainage Verification Report) of Planning Permission 21/00840/AS Phase 2due 2 Apr 2026
- Allotments A4 and A6, Chilmington Green, Ashford Road, Ashford, KentReserved matters application for the appearance, landscaping, layout, scale and access in respect of Allotment areas A4 and A6 pursuant to pdue 9 Apr 2026
- Tenterden Golf Club, Woodchurch Road, Tenterden, TN30 7DRVariation of condition 7 (Approved Plans) of Planning Permission 19/01194/AS "Proposed single storey front and side extensions with extendeddue 9 Apr 2026
- 1 Bargates, Kingsnorth, Ashford, TN23 5UDErection of a 1.8m high composite boundary fence and installation of associated access gates.due 14 Apr 2026
- 108-110, High Street, Ashford, TN24 8SDDisplay of 3 x exterior backlit signs and 2 x projecting/hanging backlit signs - Retrospectivedue 17 Apr 2026
Built nightly from Ashford's planning register. Ranks are among the 339 published councils. See planning applications in Ashford, appeals, or get alerts for Ashford.
About these figures
How are decision times measured?
Days from the date the council validated the application to the date it decided it, for applications approved or refused in the window. That is the clock councils report against and the official statistics use. Each council’s page also shows the count from receipt, which is what the applicant actually waited. Withdrawn and undecided applications are not timed.
Why do these figures differ from the council’s own?
Councils count an agreed extension of time as decided on time; we treat the calendar as the calendar. Our figures are also live and rolling, where official statistics are quarterly and annual. So a council’s own within-eight-weeks figure will usually sit a little above ours.
What counts as approved?
Approval rate is approvals divided by approvals plus refusals. Withdrawals, and decisions whose outcome the register does not state, are counted in the totals but not in the rate.
Why is a council missing?
A council is published when it has at least 25 timed decisions in the window and its register’s decision data passes our consistency checks. Councils that fail are listed with the reason rather than shown with a number that would mislead.
How often is this updated?
Nightly, from the decisions we collect from every council register we monitor. The window is the twelve months to the last complete month.