Development Site Of Former Ram Brewery Wandsworth Data via plota.co.uk

2026/0627 - Non-Material Amendment Approved

Proposal

Non-material amendment to planning permission dated 01/05/2020 ref [Variation of conditions 55 (retail locations) and 64 (control of ground floor use classes) pursuant to planning permission dated 06/12/2013 ref (A mixed use development comprising alterations and change of use of retained former brewery buildings, demolition of non-Listed Buildings and the construction of new buildings 2-12 storeys in height and a tower of 36 storeys in height. Provision of of retail (Class A1-A4), 661 residential units, continued small scale brewery use (Class B2), museum (Class D1), ancillary gym. The creation of public areas and river walkway; new and repositioned vehicular and pedestrian access points and provision of servicing areas, energy centre and basement car and cycle parking.) so as to allow additional uses in the ground floor commercial uses including D1 (Non-residential institutions), D2 (Assembly and Leisure) and B1a (Office). Variation of the Schedule 14 Part 1 of the S106 agreement to include changes to the permitted commercial unit mix and commercial units size restrictions] to allow the addition of balconies to homes that currently have no amenity provision, this affects two elevations: the inwards facing podium elevation and the river facing elevation at Level 01, 02, 03, 04 and 05. Minor amendments at ground floor level to pick up louvre detailing required for substations and related services and an escape door to the car park entry port facing the passage way between B04 and Phase 3. Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
13 Feb 2026
✓
Validated
19 Feb 2026
✓
Approved
12 Mar 2026

Approved on 12 Mar 2026 · Delegated Standard · Last checked 31 Jul 2026

Associated applications 7

Site constraints 9

7 listed buildings within 150 m of the postcode pin
Nearest: The Ram Inn, Grade II, about 3 m from the postcode pin · 1 Grade II*, 6 Grade II
The site itself is not listed. Listed building consent is needed for work that affects the special interest of a listed building, inside or out, on top of planning permission. Setting can be a consideration for buildings nearby; there is no fixed radius.
Show all 7 with distances
Historic England ↗
Flood zone 3, rivers and sea
High chance: a 1 in 100 or greater annual chance from rivers, or 1 in 200 from the sea. Any development here needs a flood risk assessment. Defences are not counted.
The Environment Agency flood map for planning. Homes in zone 3 must also pass the sequential test. Surface water flooding is a separate map.
Flood map ↗
Wandsworth Town conservation area
Demolition needs planning permission and permitted development is restricted.
The council must give weight to preserving or enhancing the area's character and appearance. Not every council has published its boundaries as open data.
Council document ↗
National infrastructure project: Thames Tideway Tunnel
The site is inside the project boundary. Waste water treatment, decided. The project page says whether consent was granted.
Nationally significant infrastructure projects (power stations, electricity lines, pipelines, major roads and railways, harbours, airports and reservoirs) are consented by a Secretary of State under the Planning Act 2008, after an examination by the Planning Inspectorate, rather than by the council. The boundary is the one the Inspectorate consults on and can change as the scheme does. Projects are shown within 2 km of the site.
Planning Inspectorate project page ↗
Archaeological priority area
An assessment or field evaluation may be asked for before ground works.
The council or Historic England considers archaeology likely here. A desk-based assessment, and sometimes trial trenching, can be asked for with the application.
Air quality management area: Wandsworth AQMA
The council has declared the area as failing an air quality objective.
Schemes that add traffic, parking or combustion plant are assessed against the area's action plan and may need an air quality assessment.
Council record ↗
Town centre: Wandsworth
A designated centre in the London Plan.
Shops, services and active frontages are protected in centres, and main town centre uses are steered here first.
Also on the record
Inside the Wandsworth built-up area; Public transport access: PTAL 5 (very good), TfL 2023, for the 100 m square.
Not affected
Not green belt · No scheduled monument at the site

Checked on 6 October 2026. The pin for this application is the centre of its postcode rather than the building, so distances to nearby designations are measured from the postcode and can be out by the width of the postcode area. Historic England, the Environment Agency, Natural England, the Planning Inspectorate, Transport for London (public transport access levels, Powered by TfL Open Data, OGL v3.0, contains OS data © Crown copyright and database right 2025) and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Work with planning data?

Every application in Wandsworth - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Council
Wandsworth
Application type
Non-Material Amendment
Received
13 Feb 2026
Validated
19 Feb 2026
Ward
Wandsworth Town
Case officer
Show
Decision
Approve No Conditions
Decision date
12 Mar 2026
Decision level
Delegated Standard
Applicant
Show
Agent
St George City Ltd

Consultation & key dates

Comments by
30 Mar 2026
Statutory expiry
13 Mar 2026
Wandsworth
Planning Authority Score
4.8/10
Below average
#164 of 296 councils
Relevant to this application:
Change of use

Wandsworth ranks #172 out of 296 councils for householder decision speed. Householder applications are slightly more likely to be approved here (92%) than the national average (90%).

These figures are council-wide context, not a prediction for this application. View full council performance
Wandsworth decision statistics
Based on MHCLG data, the year to March 2026
90%
Overall approval rate
Above avg (87%) #120 of 296
92%
Householder approved
Above avg (90%) #168 of 296
62%
Decided in 8 weeks
Below avg (63%) #172 of 296
37%
Extended time limit
Below avg (41%) #124 of 296
89%
Minor dwellings approved
680 decided (1-9 homes)
81%
Major dwellings approved
16 decided (10+ homes)
72%
Change of use approved
36 decided
2,062
Total decisions
206 refused in the year to March 2026