Malt Street Regeneration Site Land Bounded By Bianca Road Latona Road Haymerle Road Frensham Street And Malt… Data via plota.co.uk

26/AP/2160 - Approval of Details Awaiting decision

Proposal

Details of Condition 33 'Outline (Phase 2 and Phase 3) - External Materials and Mock Ups' required by planning permission , which gave consent for: "Hybrid application comprising a full planning application for Phase 1 the Detailed Component and outline planning permission (the 'Outline Component') for Phases 2 & 3 [...] Totals: Up to 1,300 homes and up to 7,000sqm commercial floorspace". Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
22 Jul 2026
✓
Validated
5 Aug 2026
Decision
Target date was 29 Sept 2026

Under consideration

No decision has been issued yet. Plota predicted a decision around 28 Oct 2026; it is now day 84.

Associated applications 2

  • Part of

    FullApprovedcouncil archive

    Conditions 33 awaiting decision

    • ConditionsDetails of Condition 33 'Outline (Phase 2 and Phase 3) - External Materials and Mock Ups'This application26/AP/2160

Site constraints 9

Flood zone 3, rivers and sea
High chance: a 1 in 100 or greater annual chance from rivers, or 1 in 200 from the sea. Any development here needs a flood risk assessment. Defences are not counted.
The Environment Agency flood map for planning. Homes in zone 3 must also pass the sequential test. Surface water flooding is a separate map.
Flood map ↗
Article 4 direction
Old Kent Road South District Town Centre. Named permitted development rights are withdrawn here.
An Article 4 direction withdraws particular permitted development rights, so work that would normally need no application needs one here. Not every council has published its directions.
Archaeological priority area: North Southwark and Roman Roads
An assessment or field evaluation may be asked for before ground works.
The council or Historic England considers archaeology likely here. A desk-based assessment, and sometimes trial trenching, can be asked for with the application.
Air quality management area: Southwark AQMA
The council has declared the area as failing an air quality objective.
Schemes that add traffic, parking or combustion plant are assessed against the area's action plan and may need an air quality assessment.
Council record ↗
National infrastructure project 1031 m away: Thames Tideway Tunnel
The site is 1031 m from the project boundary. Waste water treatment, decided. The project page says whether consent was granted. Also within 2 km: London Strategic Heat Main Project (at pre-application, 1207 m).
Nationally significant infrastructure projects (power stations, electricity lines, pipelines, major roads and railways, harbours, airports and reservoirs) are consented by a Secretary of State under the Planning Act 2008, after an examination by the Planning Inspectorate, rather than by the council. The boundary is the one the Inspectorate consults on and can change as the scheme does. Projects are shown within 2 km of the site.
Planning Inspectorate project page ↗
Opportunity area
Where the London Plan expects significant growth.
Boundaries are indicative and the borough holds the detailed plan.
Also on the record
Radon affected area, class 2; Inside the Southwark built-up area; Public transport access: PTAL 4 (good), TfL 2023, for the 100 m square.
Not affected
Not green belt · No listed building at the site · No scheduled monument at the site

Checked on 6 October 2026. Historic England, the Environment Agency, Natural England, the Planning Inspectorate, the British Geological Survey and UK Health Security Agency (radon, contains BGS materials © UKRI), Transport for London (public transport access levels, Powered by TfL Open Data, OGL v3.0, contains OS data © Crown copyright and database right 2025) and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Work with planning data?

Every application in Southwark - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Council
Southwark
Application type
Approval of Details
Received
22 Jul 2026
Validated
5 Aug 2026
Ward
Old Kent Road
Parish
Peckham And Nunhead
Case officer
Show
Target decision
29 Sept 2026
Applicant
Show

Decision outlook

Day 84, past the statutory target. 63% of commercial and major works in Southwark are decided within thirteen weeks, which runs to 4 Nov 2026; extensions of time are common, and the council need not decide on the day. Last seen undecided on 27 Oct 2026.

Day 8428 days past the 56-day target
46%decided within 8 weeks
92%approved
8%go to committee

Plota live figures for commercial and major works decided by Southwark in the last twelve months, from validation. Southwark decision record →

Public comments

No public comments yet.

Last counted 27 Oct 2026

Read the comments on the council site ↗

Consultation & key dates

Statutory expiry
29 Sept 2026
Env. assessment
No
Southwark
Planning Authority Score
7/10
Good
#64 of 296 councils
Relevant to this application:
Major dwellings

Southwark is faster than most councils at deciding householder applications, ranking #54 out of 296. Householder applications are slightly more likely to be approved here (95%) than the national average (90%).

Faster than most councils
for householder decisions
These figures are council-wide context, not a prediction for this application. View full council performance
Southwark decision statistics
Based on MHCLG data, the year to March 2026
92%
Overall approval rate
Above avg (87%) #93 of 296
95%
Householder approved
Above avg (90%) #92 of 296
78%
Decided in 8 weeks
Above avg (63%) #54 of 296
37%
Extended time limit
Below avg (41%) #122 of 296
92%
Minor dwellings approved
259 decided (1-9 homes)
86%
Major dwellings approved
14 decided (10+ homes)
82%
Change of use approved
38 decided
1,622
Total decisions
132 refused in the year to March 2026