Cayman Court, 9 Salter Street, London, E14 8NW Data via plota.co.uk

PA/26/01680/NC - Cert. of Law. Proposed Dev. (TCPA S192) Registered

Proposal

Application for Certificate of Lawfullness for proposed in respect of proposed works: ? Remove cladding and insulation required to expose compartment lines, top of the cavity wall, openings, junctions with EW02 and service penetrations ? At vertical and horizontal compartment lines, top of the cavity and junctions with EW02, install appropriately specified and certified cavity barriers, mechanically fixed back to substrate. ? Install appropriately specified, certified cavity barriers at openings, ensuring the cavity is fully closed at all openings. ? At service penetrations and install appropriately specified, certified cavity barriers/fire stopping/fire collars where none present. ? Reinstate cladding. Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
around 2 Oct 2026
Decision
Expected by 27 Nov 2026

Under consideration

No decision has been issued yet. Plota predicts a decision around 27 Nov 2026, from Tower Hamlets's recent extensions.

Documents 25

Plans & drawings 22

PDF LOCATION PLAN OS Extract · 5 Oct 2026 View ↗ PDF CAY-PRP-XX-ZZ-DR-A-48103 P01 PROPOSED CAVITY BARRIERS NORTH ELEVATION Current Plan · 5 Oct 2026 View ↗ PDF CAY-PRP-XX-ZZ-DR-A-48003 P01 EXISTING NORTH ELEVATION Current Plan · 5 Oct 2026 View ↗ PDF CAY-PRP-XX-ZZ-DR-A-48101 P01 PROPOSED CAVITY BARRIERS SOUTH ELEVATION Current Plan · 5 Oct 2026 View ↗ PDF CAY-PRP-XX-ZZ-DR-A-48102 P01 PROPOSED CAVITY BARRIERS WEST ELEVATION Current Plan · 5 Oct 2026 View ↗ PDF CAY-PRP-XX-ZZ-DR-A-48002 P01 EXISTING WEST ELEVATION Current Plan · 5 Oct 2026 View ↗ PDF CAY-PRP-XX-ZZ-DR-A-48100 P01 PROPOSED CAVITY BARRIERS EAST ELEVATION Current Plan · 5 Oct 2026 View ↗ PDF CAY-PRP-XX-ZZ-DR-A-48001 P01 EXISTING SOUTH ELEVATION Current Plan · 5 Oct 2026 View ↗ PDF CAY-PRP-XX-02-DR-A-23102 P01 PROPOSED SECOND FLOOR CAVITY BARRIER PLAN Current Plan · 5 Oct 2026 View ↗ PDF CAY-PRP-XX-ZZ-DR-A-20000 P01 SITE LOCATION PLAN Current Plan · 5 Oct 2026 View ↗ PDF CAY-PRP-XX-ZZ-DR-A-48000 P01 EXISTING EAST ELEVATION Current Plan · 5 Oct 2026 View ↗ PDF CAY-PRP-XX-05-DR-A-23005 P01 EXISTING FIFTH FLOOR PLAN Current Plan · 5 Oct 2026 View ↗ PDF CAY-PRP-XX-05-DR-A-23105 P01 PROPOSED FIFTH FLOOR CAVITY BARRIER PLAN Current Plan · 5 Oct 2026 View ↗ PDF CAY-PRP-XX-04-DR-A-23104 P01 PROPOSED FOURTH FLOOR CAVITY BARRIER PLAN Current Plan · 5 Oct 2026 View ↗ PDF CAY-PRP-XX-03-DR-A-23103 P01 PROPOSED THIRD FLOOR CAVITY BARRIER PLAN Current Plan · 5 Oct 2026 View ↗ PDF CAY-PRP-XX-04-DR-A-23004 P01 EXISTING FOURTH FLOOR PLAN Current Plan · 5 Oct 2026 View ↗ PDF CAY-PRP-XX-03-DR-A-23003 P01 EXISTING THIRD FLOOR PLAN Current Plan · 5 Oct 2026 View ↗ PDF CAY-PRP-XX-00-DR-A-23000 P01 EXISTING GROUND FLOOR PLAN Current Plan · 5 Oct 2026 View ↗ PDF CAY-PRP-XX-00-DR-A-23100 P01 PROPOSED GROUND FLOOR CAVITY BARRIER PLAN Current Plan · 5 Oct 2026 View ↗ PDF CAY-PRP-XX-01-DR-A-23001 P01 EXISTING FIRST FLOOR PLAN Current Plan · 5 Oct 2026 View ↗ PDF CAY-PRP-XX-02-DR-A-23002 P01 EXISTING SECOND FLOOR PLAN Current Plan · 5 Oct 2026 View ↗ PDF CAY-PRP-XX-01-DR-A-23101 P01 PROPOSED FIRST FLOOR CAVITY BARRIER PLAN Current Plan · 5 Oct 2026 View ↗

All documents on the council site ↗

Site constraints 7

Flood zone 3, rivers and sea
High chance: a 1 in 100 or greater annual chance from rivers, or 1 in 200 from the sea. Any development here needs a flood risk assessment. Defences are not counted.
The Environment Agency flood map for planning. Homes in zone 3 must also pass the sequential test. Surface water flooding is a separate map.
Flood map ↗
National infrastructure project: Thames Tideway Tunnel
The site is inside the project boundary. Waste water treatment, decided. The project page says whether consent was granted.
Nationally significant infrastructure projects (power stations, electricity lines, pipelines, major roads and railways, harbours, airports and reservoirs) are consented by a Secretary of State under the Planning Act 2008, after an examination by the Planning Inspectorate, rather than by the council. The boundary is the one the Inspectorate consults on and can change as the scheme does. Projects are shown within 2 km of the site.
Planning Inspectorate project page ↗
Archaeological priority area: Tower Hamlets APA 2.15
An assessment or field evaluation may be asked for before ground works.
The council or Historic England considers archaeology likely here. A desk-based assessment, and sometimes trial trenching, can be asked for with the application.
Air quality management area: Tower Hamlets AQMA
The council has declared the area as failing an air quality objective.
Schemes that add traffic, parking or combustion plant are assessed against the area's action plan and may need an air quality assessment.
Council record ↗
Opportunity area
Where the London Plan expects significant growth.
Boundaries are indicative and the borough holds the detailed plan.
Also on the record
Inside the Tower Hamlets built-up area; Public transport access: PTAL 6a (excellent), TfL 2023, for the 100 m square.
Not affected
Not green belt · No scheduled monument at the site

Checked on 9 October 2026. Historic England, the Environment Agency, Natural England, the Planning Inspectorate, Transport for London (public transport access levels, Powered by TfL Open Data, OGL v3.0, contains OS data © Crown copyright and database right 2025) and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Work with planning data?

Every application in Tower Hamlets - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Application type
Cert. of Law. Proposed Dev. (TCPA S192)
Postcode
E14 8NW
Received
around 2 Oct 2026
Validated
2 Oct 2026
Ward
Limehouse
Case officer
Show
Target decision
27 Nov 2026
Decision level
Delegated
Applicant
Show
Agent
PRP Architects

Decision outlook

Day 26 of the 56-day target. Tower Hamlets usually decides extensions by day 56.

Day 2630 days to the 56-day target
67%decided within 8 weeks
89%approved
333decided in the last year

Plota live figures for extensions decided by Tower Hamlets in the last twelve months, from validation. Tower Hamlets decision record →

Consultation & key dates

Statutory expiry
27 Nov 2026
Env. assessment
No
Tower Hamlets
Planning Authority Score
3.9/10
Below average
#201 of 296 councils
Relevant to this application:
Householder decisions

Tower Hamlets is slower than most councils at deciding householder applications, ranking #207 out of 296. Householder applications are slightly more likely to be approved here (92%) than the national average (90%).

Slower than most councils
for householder decisions
These figures are council-wide context, not a prediction for this application. View full council performance
Tower Hamlets decision statistics
Based on MHCLG data, the year to March 2026
84%
Overall approval rate
Below avg (87%) #229 of 296
92%
Householder approved
Above avg (90%) #167 of 296
56%
Decided in 8 weeks
Below avg (63%) #207 of 296
42%
Extended time limit
Above avg (41%) #167 of 296
63%
Minor dwellings approved
52 decided (1-9 homes)
80%
Major dwellings approved
15 decided (10+ homes)
55%
Change of use approved
67 decided
998
Total decisions
164 refused in the year to March 2026