Eco Power Stadium Stadium Way Doncaster DN4 5JW Data via plota.co.uk

26/01503/FUL - Full Application Awaiting decision

Proposal

Installation of a small scale battery energy storage system ('BESS') to include solar inverters which are to be situated in the service area of this site. Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
10 Aug 2026
✓
Validated
11 Aug 2026
✓
Consultation
7 Sept 2026
Decision
Expected by 17 Nov 2026

Under consideration

No decision has been issued yet. Plota predicted a decision around 28 Oct 2026; it is now day 78.

The consultation period closed on 28 Sept 2026.

Site constraints 4

Article 4 direction
Article 4 (HMO) Boundary - Came into force 14 October 2019. Named permitted development rights are withdrawn here.
An Article 4 direction withdraws particular permitted development rights, so work that would normally need no application needs one here. Not every council has published its directions.
Habitat network: Network Expansion Zone
Where habitat is joined up enough to work as a network. Context, not a constraint on its own.
Also on the record
Coalfield, development low risk area; Inside the Doncaster built-up area.
Not affected
Outside flood zones 2 and 3 · Not green belt · No listed building at the site

Checked on 6 October 2026. Historic England, the Environment Agency, Natural England, the Mining Remediation Authority and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Work with planning data?

Every application in Doncaster - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Council
Doncaster
Application type
Full Application
Postcode
DN4 5JW
Received
10 Aug 2026
Validated
11 Aug 2026
Ward
Town
Target decision
17 Nov 2026
Applicant
Show
Agent
Eden Sustainable Ltd

Decision outlook

Day 78, past the statutory target. 85% of full applications in Doncaster are decided within thirteen weeks, which runs to 10 Nov 2026; extensions of time are common, and the council need not decide on the day. Last seen undecided on 27 Oct 2026.

Day 7822 days past the 56-day target
66%decided within 8 weeks
89%approved
627decided in the last year

Plota live figures for full applications decided by Doncaster in the last twelve months, from validation. Doncaster decision record →

Public comments

No public comments yet.

Last counted 27 Oct 2026

Read the comments on the council site ↗

Consultation & key dates

Alt. reference
PP-14968380
Planning Portal ref
PP-14968380
Consultation
7 Sept 2026
Comments by
28 Sept 2026
Site or press notice
24 Aug 2026
Statutory expiry
6 Oct 2026
Env. assessment
No
Doncaster
Planning Authority Score
7.7/10
Good
#36 of 296 councils
Relevant to this application:
Householder decisions

Doncaster is one of the fastest councils in England for householder decisions, ranking #27 out of 296. Householder applications are slightly more likely to be approved here (94%) than the national average (90%).

Among the fastest councils in England
for householder decisions
These figures are council-wide context, not a prediction for this application. View full council performance
Doncaster decision statistics
Based on MHCLG data, the year to March 2026
87%
Overall approval rate
Above avg (87%) #169 of 296
94%
Householder approved
Above avg (90%) #103 of 296
83%
Decided in 8 weeks
Above avg (63%) #27 of 296
33%
Extended time limit
Below avg (41%) #75 of 296
67%
Minor dwellings approved
135 decided (1-9 homes)
93%
Major dwellings approved
27 decided (10+ homes)
90%
Change of use approved
48 decided
928
Total decisions
122 refused in the year to March 2026