Joyce Avenue And Snells Park Estate London N18 Data via plota.co.uk

26/03486/CND - Discharge Condition Application in Progress

Proposal

Details submitted pursuant to reference : facing materials (F2) in respect of hybrid planning application (part detailed/part outline) for the phased demolition of all existing buildings and structures, site preparation works and the comprehensive residential-led mixed use redevelopment comprising: Detailed planning application for Phases 0-3 comprising demolition of 12no.existing residential blocks, associated structures and Boundary Hall. Construction of residential and mixed-use buildings providing ground floor flexible commercial floorspace (Use Class E(a, b, c and e)) and community floorspace (Use Class F2(b)), residential dwellings (Use Class C3) with associated road layout, means of access including new pedestrian crossing over Sterling Way, highways works including alterations to junction of College Close and Sterling Way, car and cycle parking, hard and soft landscaping, amenity space, public, communal and private realm, ancillary plant and structures including new substation and associated works. Outline planning application (with all matters reserved) for Phases 4-10 including the demolition of all remaining buildings and structures. Construction of buildings for residential dwellings (Use Class C3), flexible commercial floorspace (Use Class E) including allowance for a drinking establishment (Sui Generis), civic and community floorspace and facilities including temporary re-provision of Boundary Hall (Use Classes F1 and F2) with associated road layout, means of access including new pedestrian walkway connecting to existing bridge to Bridport Road, highways works, car and cycle parking, landscaping including improvements to the boundary of St John and St James Church of England Primary School, amenity space, public, communal and private realm, ancillary plant and structures and other associated works. (An Environmental Statement, including a non-technical summary, also accompanies the planning application in accordance with the Town and Coun Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
18 Aug 2026
✓
Consultation
7 Sept 2026
Decision
Target date was 13 Oct 2026

Under consideration

No decision has been issued yet. Plota predicted a decision around 28 Oct 2026; it is now day 71.

The consultation period closed on 28 Sept 2026.

Associated applications 9

Site constraints 10

Article 4 direction
Borough wide. Named permitted development rights are withdrawn here.
An Article 4 direction withdraws particular permitted development rights, so work that would normally need no application needs one here. Not every council has published its directions.
Air quality management area: Enfield AQMA
The council has declared the area as failing an air quality objective.
Schemes that add traffic, parking or combustion plant are assessed against the area's action plan and may need an air quality assessment.
Council record ↗
National infrastructure project 863 m away: North London (Electricity Line) Reinforcement
The site is 863 m from the project boundary. Electricity line, decided. The project page says whether consent was granted. Also within 2 km: North London Heat and Power Project (decided, 1648 m).
Nationally significant infrastructure projects (power stations, electricity lines, pipelines, major roads and railways, harbours, airports and reservoirs) are consented by a Secretary of State under the Planning Act 2008, after an examination by the Planning Inspectorate, rather than by the council. The boundary is the one the Inspectorate consults on and can change as the scheme does. Projects are shown within 2 km of the site.
Planning Inspectorate project page ↗
Opportunity area
Where the London Plan expects significant growth.
Boundaries are indicative and the borough holds the detailed plan.
Also on the record
Conservation area 42 m away: Fore Street South; Heritage at risk 42 m away: Fore Street, Edmonton; Inside the Enfield built-up area; Public transport access: PTAL 5 (very good), TfL 2023, for the 100 m square; Designated open space 6 m away; Town centre 33 m away: Angel Edmonton.
Not affected
Outside flood zones 2 and 3 · Not green belt · No listed building at the site

Checked on 6 October 2026. Historic England, the Environment Agency, Natural England, the Planning Inspectorate, Transport for London (public transport access levels, Powered by TfL Open Data, OGL v3.0, contains OS data © Crown copyright and database right 2025) and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Work with planning data?

Every application in Enfield - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Council
Enfield
Application type
Discharge Condition
Postcode
N18 2TQ
Received
18 Aug 2026
Validated
18 Aug 2026
Ward
Upper Edmonton
Case officer
Show
Target decision
13 Oct 2026
Decision level
Delegated Decision
Applicant
Show
Agent
HTA Design LLP

Decision outlook

Day 71, past the statutory target. 96% of commercial and major works in Enfield are decided within thirteen weeks, which runs to 17 Nov 2026; extensions of time are common, and the council need not decide on the day. Last seen undecided on 26 Oct 2026.

Day 7115 days past the 56-day target
81%decided within 8 weeks
81%approved
81decided in the last year

Plota live figures for commercial and major works decided by Enfield in the last twelve months, from validation. Enfield decision record →

Public comments

No public comments yet.

Last counted 26 Oct 2026

Read the comments on the council site ↗

Consultation & key dates

Alt. reference
PP-15160777
Planning Portal ref
PP-15160777
Consultation
7 Sept 2026
Comments by
28 Sept 2026
Statutory expiry
13 Oct 2026
Env. assessment
No
Enfield
Planning Authority Score
6.9/10
Good
#65 of 296 councils
Relevant to this application:
Householder decisions

Enfield is one of the fastest councils in England for householder decisions, ranking #15 out of 296. Only 5% of applications have the time limit extended, well below the 41% national average - the council usually decides on time. Enfield is also one of the strictest councils - it refuses more householder applications than almost any other, with only 83% approved vs 90% nationally.

Among the fastest councils in England
for householder decisions
These figures are council-wide context, not a prediction for this application. View full council performance
Enfield decision statistics
Based on MHCLG data, the year to March 2026
78%
Overall approval rate
Below avg (87%) #271 of 296
83%
Householder approved
Below avg (90%) #260 of 296
90%
Decided in 8 weeks
Above avg (63%) #15 of 296
5%
Extended time limit
Below avg (41%) #1 of 296
60%
Minor dwellings approved
265 decided (1-9 homes)
63%
Major dwellings approved
8 decided (10+ homes)
72%
Change of use approved
322 decided
1,939
Total decisions
433 refused in the year to March 2026