PA/26/01372/NC - Full Planning Permission Registered

Proposal

Proposal for the installation of a new flat roof covering, including the removal of the existing curved metal profile roof and supporting framework, demolition of the existing gable walls, installation of a warm deck flat roof over the original concrete roof slab, and provision of an edge protection system to facilitate safe roof access for maintenance. Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
8 Sept 2026
✓
Consultation
9 Sept 2026
Decision
Expected by 3 Nov 2026

Under consideration

No decision has been issued yet. Plota predicts a decision around 3 Nov 2026, from Tower Hamlets's recent extensions.

The consultation period closed on 1 Oct 2026.

Documents 26

Plans & drawings 23

PDF 35489-BGR-A4-ZZ-DR-A-001-P.O REV 01 SITE LOCATION PLAN Current Plan · 5 Aug 2026 View ↗ PDF 26028-OA-ZZ-ZZ-DR-A-8002 P01 PROPOSED ROOF DETAILS Current Plan · 5 Aug 2026 View ↗ PDF 26028-OA-ZZ-ZZ-DR-A-8001 P02 PROPOSED ROOF DETAILS Current Plan · 5 Aug 2026 View ↗ PDF 26028-OA-ZZ-ZZ-DR-A-8000 P02 PROPOSED ROOF DETAILS Current Plan · 5 Aug 2026 View ↗ PDF 26028-OA-ZZ-ZZ-DR-A-5052 P01 EXISTING ELEVATION - SOUTH DEMOLITION Current Plan · 5 Aug 2026 View ↗ PDF 26028-OA-ZZ-ZZ-DR-A-5051 P01 EXISTING ELEVATION - NORTH DEMOLITION Current Plan · 5 Aug 2026 View ↗ PDF 26028-OA-ZZ-ZZ-DR-A-5050 P01 EXISTING ELEVATION - WEST DEMOLITION Current Plan · 5 Aug 2026 View ↗ PDF 26028-OA-ZZ-ZZ-DR-A-5013 P03 PROPOSED ELEVATION - SOUTH Current Plan · 5 Aug 2026 View ↗ PDF 26028-OA-ZZ-ZZ-DR-A-5012 P01 PROPOSED ELEVATION - NORTH Current Plan · 5 Aug 2026 View ↗ PDF 26028-OA-ZZ-ZZ-DR-A-5011 P04 PROPOSED ELEVATION - EAST Current Plan · 5 Aug 2026 View ↗ PDF 26028-OA-ZZ-ZZ-DR-A-5010 P04 PROPOSED ELEVATION - WEST Current Plan · 5 Aug 2026 View ↗ PDF 26028-OA-ZZ-ZZ-DR-A-5003 P01 EXISTING ELEVATION - SOUTH Current Plan · 5 Aug 2026 View ↗ PDF 26028-OA-ZZ-ZZ-DR-A-5002 P01 EXISTING ELEVATION - NORTH Current Plan · 5 Aug 2026 View ↗ PDF 26028-OA-ZZ-ZZ-DR-A-5001 P01 EXISTING ELEVATION - EAST Current Plan · 5 Aug 2026 View ↗ PDF 26028-OA-ZZ-ZZ-DR-A-5000 P01 EXISTING ELEVATION - WEST Current Plan · 5 Aug 2026 View ↗ PDF 26028-OA-ZZ-ZZ-D-A-4003 P01 SECTION B-B - PROPOSED Current Plan · 5 Aug 2026 View ↗ PDF 26028-OA-ZZ-ZZ-D-A-4002 P01 SECTION A-A - PROPOSED Current Plan · 5 Aug 2026 View ↗ PDF 26028-OA-ZZ-ZZ-DR-A-4000 P02 SECTION A-A - EXISTING Current Plan · 5 Aug 2026 View ↗ PDF 26028-OA-ZZ-ZZ-D-A-4001 P02 SECTION B-B - EXISTING Current Plan · 5 Aug 2026 View ↗ PDF 26028-OA-ZZ-ZZ-DR-A-3020 P01 EXISTING ROOF PLAN Current Plan · 5 Aug 2026 View ↗ PDF 26028-OA-ZZ-ZZ-DR-A-3021 P03 PROPOSED ROOF PLAN DETAIL Current Plan · 5 Aug 2026 View ↗ PDF 26028-OA-ZZ-ZZ-DR-A-3021 P01 EXISTING ROOF DEMOLITION PLAN Current Plan · 5 Aug 2026 View ↗ PDF FIRE SERVICE SITE PLAN Current Plan · 5 Aug 2026 View ↗

All documents on the council site ↗

Site constraints 6

In flood zones plus climate change
Inside the extent flood zones 2 and 3 could reach with climate change: the Central allowance for the 2080s on rivers, the Upper End allowance for sea level rise to 2125. From the sea. Defences are not counted.
The Environment Agency flood map for planning. Councils use it to decide when a flood risk assessment and the sequential test are needed. It is indicative and does not show whether a particular property will flood.
Flood map ↗
National infrastructure project: Thames Tideway Tunnel
The site is inside the project boundary. Waste water treatment, decided. The project page says whether consent was granted.
Nationally significant infrastructure projects (power stations, electricity lines, pipelines, major roads and railways, harbours, airports and reservoirs) are consented by a Secretary of State under the Planning Act 2008, after an examination by the Planning Inspectorate, rather than by the council. The boundary is the one the Inspectorate consults on and can change as the scheme does. Projects are shown within 2 km of the site.
Planning Inspectorate project page ↗
Air quality management area: Tower Hamlets AQMA
The council has declared the area as failing an air quality objective.
Schemes that add traffic, parking or combustion plant are assessed against the area's action plan and may need an air quality assessment.
Council record ↗
Also on the record
Inside the Tower Hamlets built-up area; Public transport access: PTAL 4 (good), TfL 2023, for the 100 m square; Designated open space about 24 m away.
Not affected
Outside flood zones 2 and 3 · Not green belt · No scheduled monument at the site

Checked on 6 October 2026. The pin for this application is the centre of its postcode rather than the building, so distances to nearby designations are measured from the postcode and can be out by the width of the postcode area. Historic England, the Environment Agency, Natural England, the Planning Inspectorate, Transport for London (public transport access levels, Powered by TfL Open Data, OGL v3.0, contains OS data © Crown copyright and database right 2025) and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Work with planning data?

Every application in Tower Hamlets - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Application type
Full Planning Permission
Postcode
E14 6HS
Received
8 Sept 2026
Validated
8 Sept 2026
Ward
Mile End
Case officer
Show
Target decision
3 Nov 2026
Decision level
Delegated
Applicant
Show
Agent
Baily Garner

Decision outlook

Day 52 of the 56-day target. Tower Hamlets usually decides extensions by day 56.

Day 524 days to the 56-day target
67%decided within 8 weeks
89%approved
333decided in the last year

Plota live figures for extensions decided by Tower Hamlets in the last twelve months, from validation. Tower Hamlets decision record →

Consultation & key dates

Neighbours
9 Sept 2026
Consultation
9 Sept 2026
Comments by
1 Oct 2026
Statutory expiry
3 Nov 2026
Env. assessment
No
Tower Hamlets
Planning Authority Score
3.9/10
Below average
#201 of 296 councils
Relevant to this application:
Householder decisions

Tower Hamlets is slower than most councils at deciding householder applications, ranking #207 out of 296. Householder applications are slightly more likely to be approved here (92%) than the national average (90%).

Slower than most councils
for householder decisions
These figures are council-wide context, not a prediction for this application. View full council performance
Tower Hamlets decision statistics
Based on MHCLG data, the year to March 2026
84%
Overall approval rate
Below avg (87%) #229 of 296
92%
Householder approved
Above avg (90%) #167 of 296
56%
Decided in 8 weeks
Below avg (63%) #207 of 296
42%
Extended time limit
Above avg (41%) #167 of 296
63%
Minor dwellings approved
52 decided (1-9 homes)
80%
Major dwellings approved
15 decided (10+ homes)
55%
Change of use approved
67 decided
998
Total decisions
164 refused in the year to March 2026