Planning decisions in Worthing

How long Worthing takes to decide a planning application and how many it approves, from the 399 decisions it made in the twelve months to August 2026. Days run from validation to decision, the clock the council reports against; the wait from receipt is shown beside it. How the figures are made.

55 daysmedian from validation to decision (UK 52); 57 from receipt
66%decided within eight weeks (UK 73%), 92% within thirteen
90%approved (UK 89%): 337 approved, 36 refused, 8 withdrawn
233 of 321UK rank for speed; 174 of 321 for approvals
056 January 2026: 5 days, 3 decisionsJanFebruary 2026: 46 days, 15 decisionsFebMarch 2026: 49 days, 59 decisionsMarApril 2026: 55 days, 68 decisionsAprMay 2026: 64 days, 62 decisionsMayJune 2026: 63 days, 65 decisionsJunJuly 2026: 57 days, 70 decisionsJulAugust 2026: 70 days, 57 decisionsAug
Median days from validation to decision, by month of decision. Dashed line: UK median (52 days). Grid at 56 and 91 days, the eight and thirteen week targets.

By kind of application

KindMedian daysWithin 8 weeksApprovedDecisionsUK rank
Full applications (including householder)5471%89%19898 of 302
Tree works5934%97%65251 of 259
Lawful development certificates2985%93%4723 of 253
Amendments *4484%95%19180 of 263
Discharge of conditions *5567%100%18144 of 175
Advertisement consent *5650%67%12123 of 190
Listed building consent *5273%73%1130 of 200

Delegated or committee

RouteShareMedian daysApprovedDecisions
Delegated to officers98%5590%380
Planning committee2%8983%6

Where the register states how the decision was made. 13 decisions did not say.

Appeals

14 appeals against Worthing decisions were decided by the Planning Inspectorate in the window, 39 for every 100 refusals; 36% were allowed. Every appeal in Worthing.

By year

Year decidedMedian daysWithin 8 weeksApprovedDecisions
2026 so far5750%90%399

Past their target date now

Decided in the last three weeks

Built nightly from Worthing's planning register. Ranks are among the 321 published councils. See planning applications in Worthing, appeals, or get alerts for Worthing.

About these figures

How are decision times measured?
Days from the date the council validated the application to the date it decided it, for applications approved or refused in the window. That is the clock councils report against and the official statistics use. Each council’s page also shows the count from receipt, which is what the applicant actually waited. Withdrawn and undecided applications are not timed.
Why do these figures differ from the council’s own?
Councils count an agreed extension of time as decided on time; we treat the calendar as the calendar. Our figures are also live and rolling, where official statistics are quarterly and annual. So a council’s own within-eight-weeks figure will usually sit a little above ours.
What counts as approved?
Approval rate is approvals divided by approvals plus refusals. Withdrawals, and decisions whose outcome the register does not state, are counted in the totals but not in the rate.
Why is a council missing?
A council is published when it has at least 25 timed decisions in the window and its register’s decision data passes our consistency checks. Councils that fail are listed with the reason rather than shown with a number that would mislead.
How often is this updated?
Nightly, from the decisions we collect from every council register we monitor. The window is the twelve months to the last complete month.