Planning decisions in West Lothian
How long West Lothian takes to decide a planning application and how many it approves, from the 767 decisions it made in the twelve months to September 2026. Days run from validation to decision, the clock the council reports against; the wait from receipt is shown beside it. How the figures are made.
54 daysmedian from validation to decision (UK 54); 64 from receipt
56%decided within eight weeks (UK 66%), 91% within thirteen
80%approved (UK 90%): 564 approved, 137 refused, 44 withdrawn
208 of 388UK rank for speed, down 60 places on last year; 373 of 388 for approvals
By kind of application
| Kind | Median days | Within 8 weeks | Approved | Decisions | UK rank |
|---|---|---|---|---|---|
| Householder applications | 50 | 69% | 98% | 228 | 27 of 200 |
| Full applications | 60 | 28% | 74% | 209 | 206 of 359 |
| Lawful development certificates | 29 | 76% | 61% | 116 | 25 of 348 |
| Advertisement consent | 55 | 54% | 71% | 64 | 179 of 320 |
| Tree works | 34 | 87% | 89% | 51 | 88 of 324 |
| Listed building consent | 53 | 58% | 84% | 31 | 33 of 307 |
| Discharge of conditions * | 77 | 19% | 88% | 18 | 294 of 310 |
| Prior approvals * | 51 | 59% | 88% | 18 | 324 of 340 |
| Outline applications * | 86 | 0% | 18% | 15 | 81 of 110 |
Delegated or committee
| Route | Share | Median days | Approved | Decisions |
|---|---|---|---|---|
| Delegated to officers | 97% | 54 | 82% | 710 |
| Planning committee | 3% | 92 | 42% | 24 |
Where the register states how the decision was made. 33 decisions did not say.
By year
| Year decided | Median days | Within 8 weeks | Approved | Decisions |
|---|---|---|---|---|
| 2016 * | 42 | 85% | 98% | 50 |
| 2017 * | 32 | 75% | 100% | 42 |
| 2018 * | 61 | 39% | 92% | 39 |
| 2019 * | 68 | 32% | 97% | 37 |
| 2020 * | 180 | 8% | 100% | 26 |
| 2021 * | 30 | 62% | 84% | 59 |
| 2022 * | 67 | 24% | 88% | 46 |
| 2023 * | 63 | 38% | 97% | 35 |
| 2024 * | 63 | 26% | 93% | 49 |
| 2025 * | 65 | 23% | 87% | 36 |
| 2026 so far | 65 | 31% | 80% | 591 |
* Years from our archive, which carries no validation date: timed from receipt, so a few days longer than the live years above them.
Past their target date now
- Land South Of 53 Main Street BlackridgeErection of 2 housesdue 20 Sept 2025
- Raw Farm East Calder EH53 0ETFormation of hardstanding and use of land for car sales, car park for garden centre, delivery area for garden centre (part in retrospect)due 19 Oct 2025
- Land To South Of Station Mews Kirknewton West Lothian EH27 8DEErection of 43 houses and associated worksdue 18 Nov 2025
- Block HH3 Niddry Mains Farmhouse Niddry Mains Winchburgh West Lothian EH52 6QWRedevelopment of former farm steading and erection of 33 houses with roads, parking, landscaping and associated worksdue 24 Nov 2025
- 2 Deanswood Park Deans Livingston West Lothian EH54 8NXApplication for high hedge noticedue 29 Nov 2025
- Redcraig Caravan Storage Facility 1 Redcraig Morton East Calder West Lothian EH53 0JTPlanning permission in principle for the erection of a retirement dwelling housedue 29 Nov 2025
- Land North Of B7015 Mid CalderApproval of Matters Specified in Conditions of planning permission 1036/P/21 (appeal ref : PPA-400-2136) for the erection of 93 houses and 8due 22 Dec 2025
- Happy Valley Hotel 63A Bathgate Road Blackburn Bathgate West Lothian EH47 7JAChange of use from public house to a shop (Class 1A) and alterations to building and accessible rampdue 12 Jan 2026
Decided in the last three weeks
- St John Ogilvie Primary School Harburn Avenue Carmondean Livingston West Lothian EH54 8NQErection of a 422sqm extension and alterations to provide a new hall, storage and main entrance with associated alterations to hard and softApproved22 Oct 2026
- Land South Of Leyden Road Kirknewton EH27 8DQSolar PV array, battery energy storage system (BESS), substation, internal access tracks, improvements to existing junction accesses, and laApproved21 Oct 2026
- Pearie Law West Calder West Lothian EH55 8LTApplication under Section 42 for same development as planning permission 0124/FUL/21 (Erection of 3 wind turbines with maximum height to blaApproved21 Oct 2026
- Livingston Islamic Centre And Mosque 7 Main Street Deans Livingston West Lothian EH54 8BEInstallation of 2 air source heat pumps and solar panels, roof mountedApproved21 Oct 2026
- 106 Kirkfield East Livingston Village Livingston West Lothian EH54 7BBCertificate of lawfulness for erection of a conservatoryApproved20 Oct 2026
- 38 New Calder Mill Road Mid Calder West Lothian EH54 6FTCertificate of lawfulness for proposed single storey extension to the rear of existing dwelling house and garage conversionApproved20 Oct 2026
- Land To North Of 25 Gleneagles Court Whitburn West Lothian EH47 8PGChange of use from open space to private garden ground and erection of a 2.5 metre high timber fence (in retrospect).Approved20 Oct 2026
- Land At Union Canal, Preston Road, LinlithgowErection of waste container enclosure and associated worksApproved20 Oct 2026
Built nightly from West Lothian's planning register. Ranks are among the 388 published councils. See planning applications in West Lothian, or get alerts for West Lothian.
About these figures
How are decision times measured?
Days from the date the council validated the application to the date it decided it, for applications approved or refused in the window. That is the clock councils report against and the official statistics use. Each council’s page also shows the count from receipt, which is what the applicant actually waited. Withdrawn and undecided applications are not timed.
Why do these figures differ from the council’s own?
Councils count an agreed extension of time as decided on time; we treat the calendar as the calendar. Our figures are also live and rolling, where official statistics are quarterly and annual. So a council’s own within-eight-weeks figure will usually sit a little above ours.
What counts as approved?
Approval rate is approvals divided by approvals plus refusals. Withdrawals, and decisions whose outcome the register does not state, are counted in the totals but not in the rate.
Why is a council missing?
A council is published when it has at least 25 timed decisions in the window and its register’s decision data passes our consistency checks. Councils that fail are listed with the reason rather than shown with a number that would mislead.
How often is this updated?
Nightly, from the decisions we collect from every council register we monitor. The window is the twelve months to the last complete month.