Planning decisions in Norwich

How long Norwich takes to decide a planning application and how many it approves, from the 525 decisions it made in the twelve months to August 2026. Days run from validation to decision, the clock the council reports against; the wait from receipt is shown beside it. How the figures are made.

50 daysmedian from validation to decision (UK 52); 54 from receipt
81%decided within eight weeks (UK 73%), 93% within thirteen
94%approved (UK 89%): 370 approved, 24 refused, 10 withdrawn
112 of 321UK rank for speed, down 97 places on last year; 103 of 321 for approvals
056 September 2025: 46 days, 90 decisionsSeptOctober 2025: 41 days, 97 decisionsOctNovember 2025: 46 days, 87 decisionsNovDecember 2025: 42 days, 135 decisionsDecJanuary 2026: 13 days, 2 decisionsJanFebruary 2026: 44 days, 36 decisionsFebMarch 2026: 50 days, 85 decisionsMarApril 2026: 52 days, 78 decisionsAprMay 2026: 51 days, 89 decisionsMayJune 2026: 55 days, 70 decisionsJunJuly 2026: 55 days, 92 decisionsJulAugust 2026: 56 days, 73 decisionsAug
Median days from validation to decision, by month of decision. Dashed line: UK median (52 days). Grid at 56 and 91 days, the eight and thirteen week targets.

By kind of application

KindMedian daysWithin 8 weeksApprovedDecisionsUK rank
Tree works42100%91%166162 of 259
Full applications (including householder)5276%94%16249 of 302
Listed building consent5382%99%7137 of 200
Discharge of conditions5170%97%34107 of 175
Amendments3580%97%32135 of 263
Advertisement consent *5191%73%2252 of 190
Lawful development certificates *4892%92%1790 of 253
Prior approvals *5454%100%17155 of 168

Delegated or committee

RouteShareMedian daysApprovedDecisions
Delegated to officers98%5094%481
Planning committee2%87100%10

Where the register states how the decision was made. 34 decisions did not say.

Appeals

13 appeals against Norwich decisions were decided by the Planning Inspectorate in the window, 54 for every 100 refusals; 23% were allowed. Every appeal in Norwich.

By year

Year decidedMedian daysWithin 8 weeksApprovedDecisions
2016 *6736%92%52
2017 *5563%100%83
2018 *7625%98%106
2019 *5572%98%62
2020 *4870%94%97
2021 *3795%98%371
2022 *5555%89%56
2023 *6527%98%57
2024 *5366%87%63
2025 *5657%99%97
2026 so far5464%94%525

* Years from our archive, which carries no validation date: timed from receipt, so a few days longer than the live years above them.

Past their target date now

Decided in the last three weeks

Built nightly from Norwich's planning register. Ranks are among the 321 published councils. See planning applications in Norwich, appeals, or get alerts for Norwich.

About these figures

How are decision times measured?
Days from the date the council validated the application to the date it decided it, for applications approved or refused in the window. That is the clock councils report against and the official statistics use. Each council’s page also shows the count from receipt, which is what the applicant actually waited. Withdrawn and undecided applications are not timed.
Why do these figures differ from the council’s own?
Councils count an agreed extension of time as decided on time; we treat the calendar as the calendar. Our figures are also live and rolling, where official statistics are quarterly and annual. So a council’s own within-eight-weeks figure will usually sit a little above ours.
What counts as approved?
Approval rate is approvals divided by approvals plus refusals. Withdrawals, and decisions whose outcome the register does not state, are counted in the totals but not in the rate.
Why is a council missing?
A council is published when it has at least 25 timed decisions in the window and its register’s decision data passes our consistency checks. Councils that fail are listed with the reason rather than shown with a number that would mislead.
How often is this updated?
Nightly, from the decisions we collect from every council register we monitor. The window is the twelve months to the last complete month.