Planning decisions in Moray
How long Moray takes to decide a planning application and how many it approves, from the 573 decisions it made in the twelve months to September 2026. Days run from validation to decision, the clock the council reports against; the wait from receipt is shown beside it. How the figures are made.
73 daysmedian from validation to decision (UK 54); 85 from receipt
36%decided within eight weeks (UK 66%), 65% within thirteen
98%approved (UK 90%): 505 approved, 11 refused, 43 withdrawn
374 of 388UK rank for speed, down 40 places on last year; 22 of 388 for approvals
By kind of application
| Kind | Median days | Within 8 weeks | Approved | Decisions | UK rank |
|---|---|---|---|---|---|
| Full applications | 81 | 28% | 99% | 416 | 308 of 359 |
| Listed building consent | 63 | 35% | 96% | 63 | 179 of 307 |
| Prior approvals | 25 | 98% | 100% | 46 | 46 of 340 |
| Lawful development certificates * | 55 | 54% | 85% | 13 | 261 of 348 |
| Advertisement consent * | 78 | 40% | 90% | 10 | 302 of 320 |
Delegated or committee
| Route | Share | Median days | Approved | Decisions |
|---|---|---|---|---|
| Delegated to officers | 99% | 82 | 98% | 464 |
| Planning committee | 1% | 162 | 100% | 6 |
Where the register states how the decision was made. 103 decisions did not say.
By year
| Year decided | Median days | Within 8 weeks | Approved | Decisions |
|---|---|---|---|---|
| 2016 * | 55 | 65% | 98% | 57 |
| 2017 * | 50 | 64% | 95% | 696 |
| 2018 * | 49 | 62% | 89% | 89 |
| 2019 * | 7 | 88% | 100% | 50 |
| 2020 * | 57 | 49% | 95% | 57 |
| 2021 * | 58 | 48% | 94% | 55 |
| 2022 * | 37 | 71% | 92% | 79 |
| 2023 * | 76 | 6% | 100% | 32 |
| 2024 * | 77 | 25% | 99% | 69 |
| 2025 * | 30 | 73% | 94% | 54 |
| 2026 so far | 94 | 27% | 98% | 474 |
* Years from our archive, which carries no validation date: timed from receipt, so a few days longer than the live years above them.
Past their target date now
- Millburn Linkwood Road Elgin Moray IV30 8RDForm new opening and reduce height of existing walldue 1 Oct 2025
- Land Adjacent To Callaly Forres MorayProposed demolition of disused sheds and erection of dwellinghouse ondue 15 Oct 2025
- R2 Bilbohall Elgin MorayAmendment of S75 legal agreement attached to planning permission 20/00905/APP, as modified as a result of application 24/00705/APP to includdue 16 Oct 2025
- R5 Balnageith Forres MorayErect 9 detached dwellings atdue 16 Oct 2025
- Burncrook Warehouses Station Street Rothes Aberlour Moray AB38 7ADHazardous substance consent ondue 20 Oct 2025
- Findhorn Sands Findhorn Forres Moray IV36 3YZErect storage building with staff area atdue 21 Oct 2025
- Site 12 Elgin Business Park Elgin MorayConstruction of new pot ale processing plant and associated reception office and associated roads and hard standings ondue 21 Oct 2025
- Thorabella Farm Dallas Forres Moray IV36 2RZRetrospective consent to site new catering container storage container polytunnel associated with catering unit with picnic and play area andue 27 Oct 2025
Decided in the last three weeks
- 45 Mayne Road Elgin Moray IV30 1PFAlter and extend dwellinghouse atApproved20 Oct 2026
- Grampian Motors Morriston Road Elgin Moray IV30 4EAChange of use to form cafe and ice-cream shop atApproved19 Oct 2026
- 19 East Street Fochabers Moray IV32 7DYProposed alterations and replacement extension atApproved14 Oct 2026
- St Giles And St Columbas South Church Office Duff Avenue Elgin Moray IV30 1QSReplace existing plain glass window on the south elevation with a new stain glass window atApproved14 Oct 2026
- Ivybank Bridge Street Elgin Moray IV30 4DERetrospective consent to site ancillary garden annexe atApproved14 Oct 2026
- 9 North Guildry Street Elgin Moray IV30 1JRChange of use from office to dance and performing arts college atApproved14 Oct 2026
- Arndilly House Craigellachie Aberlour Moray AB38 9QSErect 108 solar PV panels atApproved14 Oct 2026
- 6 Seapark Lane Kinloss Forres Moray IV36 3SZRetrospective consent to site ancillary accommodation atApproved14 Oct 2026
Built nightly from Moray's planning register. Ranks are among the 388 published councils. See planning applications in Moray, or get alerts for Moray.
About these figures
How are decision times measured?
Days from the date the council validated the application to the date it decided it, for applications approved or refused in the window. That is the clock councils report against and the official statistics use. Each council’s page also shows the count from receipt, which is what the applicant actually waited. Withdrawn and undecided applications are not timed.
Why do these figures differ from the council’s own?
Councils count an agreed extension of time as decided on time; we treat the calendar as the calendar. Our figures are also live and rolling, where official statistics are quarterly and annual. So a council’s own within-eight-weeks figure will usually sit a little above ours.
What counts as approved?
Approval rate is approvals divided by approvals plus refusals. Withdrawals, and decisions whose outcome the register does not state, are counted in the totals but not in the rate.
Why is a council missing?
A council is published when it has at least 25 timed decisions in the window and its register’s decision data passes our consistency checks. Councils that fail are listed with the reason rather than shown with a number that would mislead.
How often is this updated?
Nightly, from the decisions we collect from every council register we monitor. The window is the twelve months to the last complete month.