Planning decisions in Huntingdonshire
How long Huntingdonshire takes to decide a planning application and how many it approves, from the 987 decisions it made in the twelve months to August 2026. Days run from validation to decision, the clock the council reports against; the wait from receipt is shown beside it. How the figures are made.
By kind of application
| Kind | Median days | Within 8 weeks | Approved | Decisions | UK rank |
|---|---|---|---|---|---|
| Full applications (including householder) | 57 | 49% | 92% | 351 | 250 of 302 |
| Tree works | 19 | 87% | 97% | 198 | 19 of 259 |
| Discharge of conditions | 56 | 62% | 92% | 143 | 151 of 175 |
| Amendments | 51 | 65% | 95% | 74 | 218 of 263 |
| Lawful development certificates | 56 | 68% | 79% | 66 | 228 of 253 |
| Listed building consent | 62 | 43% | 95% | 48 | 153 of 200 |
| Prior approvals * | 55 | 92% | 69% | 34 | 157 of 168 |
| Outline applications | 49 | 65% | 58% | 32 | 18 of 39 |
| Advertisement consent * | 56 | 71% | 93% | 15 | 139 of 190 |
Delegated or committee
| Route | Share | Median days | Approved | Decisions |
|---|---|---|---|---|
| Delegated to officers | 99% | 56 | 91% | 955 |
| Planning committee | 1% | 105 | 100% | 6 |
Where the register states how the decision was made. 26 decisions did not say.
Appeals
40 appeals against Huntingdonshire decisions were decided by the Planning Inspectorate in the window, 49 for every 100 refusals; 35% were allowed. Every appeal in Huntingdonshire.
By year
| Year decided | Median days | Within 8 weeks | Approved | Decisions |
|---|---|---|---|---|
| 2016 * | 55 | 76% | 98% | 50 |
| 2017 * | 27 | 92% | 100% | 27 |
| 2018 * | 22 | 98% | 91% | 46 |
| 2019 * | 96 | 10% | 93% | 30 |
| 2020 * | 27 | 95% | 100% | 43 |
| 2021 * | 27 | 80% | 100% | 32 |
| 2022 * | 30 | 86% | 100% | 30 |
| 2023 * | 71 | 33% | 72% | 188 |
| 2024 * | 73 | 22% | 100% | 42 |
| 2025 * | 68 | 29% | 93% | 28 |
| 2026 so far | 58 | 47% | 91% | 987 |
* Years from our archive, which carries no validation date: timed from receipt, so a few days longer than the live years above them.
Decided in the last three weeks
- 6 Brook Farm Drive Colne Huntingdon PE28 3PDPermission in Principle for a single dwellingApproved11 Sept 2026
- Collmart Growers Ltd The Drove Pondersbridge Huntingdon PE26 2TPDischarge of Conditions 4 (Hard and Soft Landscape Works), 5 (SWD Drainage), 6 (SWD Maintenance) and 7 (Construction Drainage) of 24/00066/SApproved9 Sept 2026
- 2 Cooper Thornhill Road Stilton Peterborough PE7 3XDLawful development certificate for proposed rear/side extensionRefused7 Sept 2026
- 42A Station Road Tilbrook Huntingdon PE28 0JTErection of single storey rear extension and porchApproved7 Sept 2026
- 66A Berkley Street Eynesbury St Neots PE19 2NFProposed (part retrospective) double gates & railings including brick pillarsApproved7 Sept 2026
- 3 - 4 Morley Court Enterprise Way Enterprise Park YaxleySolar PV installation on roofApproved4 Sept 2026
- Shop 18A Bridge Street St Ives PE27 5EGPainting of shop frontApproved4 Sept 2026
- Public House White Swan 30 High Street Bluntisham Huntingdon PE28 3LDConstruction of proposed single storey outbuilding for use as part of the operation of the existing public houseApproved4 Sept 2026
Built nightly from Huntingdonshire's planning register. Ranks are among the 321 published councils. See planning applications in Huntingdonshire, appeals, or get alerts for Huntingdonshire.