Planning decisions in East Ayrshire
How long East Ayrshire takes to decide a planning application and how many it approves, from the 615 decisions it made in the twelve months to September 2026. Days run from validation to decision, the clock the council reports against; the wait from receipt is shown beside it. How the figures are made.
55 daysmedian from validation to decision (UK 54); 66 from receipt
55%decided within eight weeks (UK 66%), 83% within thirteen
95%approved (UK 90%): 537 approved, 26 refused, 27 withdrawn
261 of 388UK rank for speed, down 232 places on last year; 72 of 388 for approvals
By kind of application
| Kind | Median days | Within 8 weeks | Approved | Decisions | UK rank |
|---|---|---|---|---|---|
| Full applications | 57 | 45% | 96% | 284 | 175 of 359 |
| Discharge of conditions | 48 | 63% | 99% | 113 | 94 of 310 |
| Listed building consent | 57 | 45% | 94% | 33 | 143 of 307 |
| Prior approvals | 24 | 97% | 94% | 32 | 39 of 340 |
| Tree works | 56 | 53% | 100% | 32 | 300 of 324 |
| Lawful development certificates | 49 | 74% | 89% | 29 | 126 of 348 |
| Amendments | 28 | 81% | 93% | 28 | 38 of 356 |
| Advertisement consent * | 57 | 36% | 91% | 22 | 257 of 320 |
Delegated or committee
| Route | Share | Median days | Approved | Decisions |
|---|---|---|---|---|
| Delegated to officers | 99% | 55 | 96% | 602 |
| Planning committee | 1% | 126 | 78% | 9 |
Where the register states how the decision was made. 4 decisions did not say.
By year
| Year decided | Median days | Within 8 weeks | Approved | Decisions |
|---|---|---|---|---|
| 2016 * | 55 | 51% | 97% | 37 |
| 2017 * | 55 | 52% | 100% | 34 |
| 2018 * | 28 | 80% | 94% | 107 |
| 2019 * | 61 | 40% | 97% | 36 |
| 2020 * | 34 | 56% | 87% | 59 |
| 2021 * | 32 | 72% | 89% | 59 |
| 2022 * | 70 | 18% | 87% | 43 |
| 2023 * | 55 | 52% | 90% | 52 |
| 2024 * | 50 | 57% | 90% | 69 |
| 2025 * | 50 | 58% | 89% | 39 |
| 2026 so far | 67 | 33% | 94% | 473 |
* Years from our archive, which carries no validation date: timed from receipt, so a few days longer than the live years above them.
Past their target date now
- Land Within The North Kyle Forest, Approximately 5.5km East Of Patna, 6km West Of New Cumnock And 2.5km North East Of Dalmellington.Non Material Variation: To relocate the approved telecoms mast and create 165m of new track to access telecoms mast of Planning Consent 22/0due 20 Oct 2025
- Site Of Existing Kirklandside Hospital U63 Wheatriggs From A76 At Kirklandside Hospital To Whatriggs Road Kilmarnock East Ayrshire KA1 5LHErection of industrial storage and distribution units, with ancillary infrastructure, parking and landscaping.due 31 Dec 2025
- Land At Kilwinning Road StewartonResidential development to include access, roads, open space, landscaping, drainage and other associated worksdue 16 Jan 2026
- Vacant Land Adjacent To Industrial Park, Unit 9 Moorfield Roundabout, Kilmarnock KA2 0FEProposed Erection of detached industrial unit, associated car parking and secure yard space.due 25 Jan 2026
- Land To The North Of Newmilns Cemetery C133 Newmilns From Dalwhatswood Road NewmilnsChange of use of land to form 6 gypsy / traveller pitches including chalets, day lodges, shower and washing block, area providing temporarydue 26 Jan 2026
- Brownfield Site South Of Station Court, Littlemill Road, DronganProposed 25 house development with new private road, visitor parking and green space.due 9 Feb 2026
- Little Creoch Farm New Cumnock East Ayrshire KA18 4QEProposal of applciation Notice for 3 x 64K Hen Houses; 3 single storey chicken shed units proposed each with footprint area 5760m2 housing 6due 3 Mar 2026
- Hare Hill Repowering Site Harehill Wind Farm New CumnockConsultation under Section 36 of the Electricity Act 1989 for the proposed Hare Hill Repowering wind farm.due 12 Mar 2026
Decided in the last three weeks
- Bonded Warehouses Townhead Catrine East AyrshireErection of canopy building, anchored to existing concrete base.Approved22 Oct 2026
- The Braes 30 Burn Road Darvel East Ayrshire KA17 0DBNo 1, Tag 1160, Lawson Cypress - Health and safety and structural issues now require tree to be felled.Approved22 Oct 2026
- 8 East Donington Street Darvel East Ayrshire KA17 0JRReplacement of 7 windows within the front elevationApproved21 Oct 2026
- Baptist Church Fowlds Street Kilmarnock East Ayrshire KA1 3DGChange of use from Class 10 (non-residential institution) to Class 1A (shop, financial, professional or other service)Approved21 Oct 2026
- Open Space At Corner Of Glaisnock And Holmburn Road Holmburn Road Netherthird Cumnock East AyrshireDischarge of Conditions (2) (SUDS Details) and (4) (External Materials) of Planning Consent 25/0484/PP Proposed erection of a two-storey offApproved21 Oct 2026
- 16 Ballochmyle Street Catrine East Ayrshire KA5 6QPChange of use of dwellinghouse (Class 9) to use as Short Term Let (Sui Generis) (5 bedrooms) and change of use of residential garden groundApproved21 Oct 2026
- 21 Thomas Howie Drive Dunlop KILMARNOCK KA3 4FASingle storey side and link extensions and external alterations to facilitate garage conversionApproved21 Oct 2026
- Laurel Cottage 1 Friendliehead Farmhouse Courtyard Mauchline East Ayrshire KA5 6EXRear extension to south east corner of existing dwellingApproved20 Oct 2026
Built nightly from East Ayrshire's planning register. Ranks are among the 388 published councils. See planning applications in East Ayrshire, or get alerts for East Ayrshire.
About these figures
How are decision times measured?
Days from the date the council validated the application to the date it decided it, for applications approved or refused in the window. That is the clock councils report against and the official statistics use. Each council’s page also shows the count from receipt, which is what the applicant actually waited. Withdrawn and undecided applications are not timed.
Why do these figures differ from the council’s own?
Councils count an agreed extension of time as decided on time; we treat the calendar as the calendar. Our figures are also live and rolling, where official statistics are quarterly and annual. So a council’s own within-eight-weeks figure will usually sit a little above ours.
What counts as approved?
Approval rate is approvals divided by approvals plus refusals. Withdrawals, and decisions whose outcome the register does not state, are counted in the totals but not in the rate.
Why is a council missing?
A council is published when it has at least 25 timed decisions in the window and its register’s decision data passes our consistency checks. Councils that fail are listed with the reason rather than shown with a number that would mislead.
How often is this updated?
Nightly, from the decisions we collect from every council register we monitor. The window is the twelve months to the last complete month.