Planning decisions in Blackburn
How long Blackburn takes to decide a planning application and how many it approves, from the 918 decisions it made in the twelve months to September 2026. Days run from validation to decision, the clock the council reports against; the wait from receipt is shown beside it. How the figures are made.
53 daysmedian from validation to decision (UK 54); 56 from receipt
64%decided within eight weeks (UK 66%), 83% within thirteen
96%approved (UK 90%): 797 approved, 36 refused, 58 withdrawn
175 of 388UK rank for speed, down 50 places on last year; 63 of 388 for approvals
By kind of application
| Kind | Median days | Within 8 weeks | Approved | Decisions | UK rank |
|---|---|---|---|---|---|
| Full applications | 55 | 57% | 97% | 438 | 83 of 359 |
| Discharge of conditions | 58 | 48% | 96% | 123 | 243 of 310 |
| Tree works | 12 | 91% | 94% | 103 | 11 of 324 |
| Amendments | 35 | 70% | 99% | 78 | 91 of 356 |
| Lawful development certificates | 50 | 81% | 83% | 49 | 139 of 348 |
| Householder applications | 27 | 100% | 100% | 38 | 1 of 200 |
| Prior approvals | 54 | 65% | 92% | 30 | 331 of 340 |
| Advertisement consent * | 52 | 57% | 100% | 25 | 95 of 320 |
| Listed building consent * | 57 | 47% | 100% | 18 | 139 of 307 |
Delegated or committee
| Route | Share | Median days | Approved | Decisions |
|---|---|---|---|---|
| Delegated to officers | 92% | 52 | 95% | 749 |
| Planning committee | 8% | 100 | 100% | 63 |
Where the register states how the decision was made. 106 decisions did not say.
By year
| Year decided | Median days | Within 8 weeks | Approved | Decisions |
|---|---|---|---|---|
| 2016 * | 56 | 51% | 96% | 53 |
| 2017 * | 55 | 53% | 85% | 47 |
| 2018 * | 48 | 62% | 93% | 58 |
| 2019 * | 13 | 97% | 97% | 77 |
| 2020 * | 50 | 67% | 89% | 61 |
| 2021 * | 55 | 60% | 96% | 25 |
| 2022 * | 17 | 99% | 96% | 67 |
| 2023 * | 41 | 69% | 87% | 39 |
| 2024 * | 50 | 58% | 93% | 72 |
| 2025 * | 56 | 54% | 88% | 100 |
| 2026 so far | 57 | 50% | 95% | 691 |
* Years from our archive, which carries no validation date: timed from receipt, so a few days longer than the live years above them.
Past their target date now
- Bull Hill Manor Bolton Road Darwen BB3 2TTDischarge Condition No 3 'drainage scheme' pursuant to planning application 10/25/0068due 27 Aug 2025
- Land off Redlam Brow BlackburnDischarge Condition Nos 5 'desk study', 8,'noise attenuation scheme', 12 'sustainable surface water and foul water drainage scheme',14 'surfdue 24 Nov 2025
- Land at Blackburn Road EdgworthErection of 19 dwellings, new boundary treatments and associated development together with the formation of a new vehicular access points frdue 5 Dec 2025
- Land at Bank Hey Farm Heys Lane BlackburnDischarge Condition Nos 8 'validation report for each phase', 14 'air quality impact assessment scheme', 34 'management and maintenance of tdue 12 Dec 2025
- 52 King William Street Blackburn BB1 7DP1 No. vinyl graphic, 3 No. taco letters, 3 No. bell logos, 3 No. bell letters, 1 No. projecting sign and 1 No. hanging neon tacos arrowdue 22 Dec 2025
- SUEZ Lower Eccleshill Road Darwen BB3 0RPVariation to S106 Agreement dated 2nd March 2023 pursant to planning application 10/22/1006 - 'Demolition of existing waste management operadue 20 Jan 2026
- Land off Redlam Brow BlackburnDischarge Condition Nos 22 'highway layout, drainage, construction details and streetlighting scheme', and 23 'junction details for Redlam Bdue 5 Feb 2026
- Former East Lancashire Coach Works Whalley New Road Blackburn BB1 6JSConstruction of Petrol Filling Station (Sui Generis) with associated parking & construction of 3No. units to be used as Food / Eating (Use Cdue 13 Feb 2026
Decided in the last three weeks
- 40 Cornelian Street, Blackburn, Blackburn With Darwen, BB1 9AWErection of single storey extension to rear. 4.5m from original rear wall, Max Height: 3.1m, Height to Eaves: 2.350mApproved26 Oct 2026
- Approved23 Oct 2026
- 7 Ravenswing Avenue, Blackburn, Blackburn With Darwen, BB2 6DXT16 (Beech) - Crown lift to 5m from ground level. Height and lateral reduction of 3m.Approved22 Oct 2026
- 5 Hollies Close, Livesey, Blackburn, Blackburn With Darwen, BB2 5AJProposed single storey rear extension and re-location of first floor bedroom windowApproved21 Oct 2026
- 4 Heaton Street, Blackburn, Blackburn With Darwen, BB2 2EFProposed change of use of ground floor from retail shop (Use Class E (a)) to a self-contained flat (Use Class C3)Approved21 Oct 2026
- 19 Whinney Lane, Blackburn, Blackburn With Darwen, BB2 7BXProposed single storey side extension and erection of front porchApproved21 Oct 2026
- Land off Haslingden Road, Blackburn, BB2 3HQDischarge Condition No.6 " desk study report" pursuant to planning application 10/26/0291Approved21 Oct 2026
- Reed Dawson Ltd, Basement And Ground Floor, 52 Preston New Road, Blackburn, Blackburn With Darwen, BB2 1AWStreet sign clearance under Highways instruction.Approved20 Oct 2026
Built nightly from Blackburn's planning register. Ranks are among the 388 published councils. See planning applications in Blackburn, appeals, or get alerts for Blackburn.
About these figures
How are decision times measured?
Days from the date the council validated the application to the date it decided it, for applications approved or refused in the window. That is the clock councils report against and the official statistics use. Each council’s page also shows the count from receipt, which is what the applicant actually waited. Withdrawn and undecided applications are not timed.
Why do these figures differ from the council’s own?
Councils count an agreed extension of time as decided on time; we treat the calendar as the calendar. Our figures are also live and rolling, where official statistics are quarterly and annual. So a council’s own within-eight-weeks figure will usually sit a little above ours.
What counts as approved?
Approval rate is approvals divided by approvals plus refusals. Withdrawals, and decisions whose outcome the register does not state, are counted in the totals but not in the rate.
Why is a council missing?
A council is published when it has at least 25 timed decisions in the window and its register’s decision data passes our consistency checks. Councils that fail are listed with the reason rather than shown with a number that would mislead.
How often is this updated?
Nightly, from the decisions we collect from every council register we monitor. The window is the twelve months to the last complete month.