Planning decisions in Ards And North Down
How long Ards And North Down takes to decide a planning application and how many it approves, from the 272 decisions it made in the twelve months to August 2026. Days run from validation to decision, the clock the council reports against; the wait from receipt is shown beside it. How the figures are made.
57 daysmedian from validation to decision (UK 52); 61 from receipt
50%decided within eight weeks (UK 73%), 79% within thirteen
95%approved (UK 89%): 207 approved, 12 refused, 12 withdrawn
301 of 321UK rank for speed, up 38 places on last year; 90 of 321 for approvals
By kind of application
| Kind | Median days | Within 8 weeks | Approved | Decisions | UK rank |
|---|---|---|---|---|---|
| Full applications (including householder) | 57 | 49% | 99% | 184 | 249 of 302 |
| Amendments * | 45 | 78% | 44% | 21 | 186 of 263 |
| Advertisement consent * | 62 | 29% | 100% | 18 | 174 of 190 |
By year
| Year decided | Median days | Within 8 weeks | Approved | Decisions |
|---|---|---|---|---|
| 2016 * | 147 | 8% | 92% | 26 |
| 2017 * | 89 | 10% | 95% | 61 |
| 2018 * | 71 | 36% | 82% | 28 |
| 2019 * | 42 | 61% | 63% | 54 |
| 2020 * | 309 | 0% | 84% | 70 |
| 2021 * | 81 | 26% | 92% | 54 |
| 2022 * | 47 | 51% | 88% | 42 |
| 2023 * | 95 | 30% | 98% | 86 |
| 2024 * | 286 | 1% | 79% | 89 |
| 2025 * | 70 | 48% | 65% | 48 |
| 2026 so far | 61 | 42% | 95% | 272 |
* Years from our archive, which carries no validation date: timed from receipt, so a few days longer than the live years above them.
Decided in the last three weeks
- 95 Ballybarnes Road, Newtownards, BT23 4TDProposed two storey rear extension to existing dwelling including minor extension of domestic curtilage to relocate driveway entrance gatesApproved9 Sept 2026
- 1 Seapark Avenue Holywood BT18 0LLReplacement dwelling including installation of PV panels and heat pump and creating new access along with associated hard and sort landscapiApproved9 Sept 2026
- 16 Hanover Dale, Bangor, BT19 7NUSingle-storey extension to rear.Approved7 Sept 2026
- 9 Marine Drive Donaghadee BT21 0HSSingle-storey extensions (front, side and rear) including car port; demolition of garage and lean-to structure (amended drawings uploaded toApproved4 Sept 2026
- 104 Princetown Road, Bangor, BT20 3TGDemolition of existing rear return: two-storey side-to-rear extension; single-storey side extension; relocation of access and all associatedApproved4 Sept 2026
- 79a Whinney Hill, Dundonald, BT16 1UASingle storey side sunroom and double garage with link to main dwelling.Approved3 Sept 2026
- 62 Jackson's Road, Holywood, BT18 9EZRoofspace conversion including rear dormerApproved2 Sept 2026
- 2 Cypress Close Donaghadee BT21 0QFRear dormer window with roofspace conversion (Amended Plan)Approved2 Sept 2026
Built nightly from Ards And North Down's planning register. Ranks are among the 321 published councils. See planning applications in Ards And North Down, or get alerts for Ards And North Down.
About these figures
How are decision times measured?
Days from the date the council validated the application to the date it decided it, for applications approved or refused in the window. That is the clock councils report against and the official statistics use. Each council’s page also shows the count from receipt, which is what the applicant actually waited. Withdrawn and undecided applications are not timed.
Why do these figures differ from the council’s own?
Councils count an agreed extension of time as decided on time; we treat the calendar as the calendar. Our figures are also live and rolling, where official statistics are quarterly and annual. So a council’s own within-eight-weeks figure will usually sit a little above ours.
What counts as approved?
Approval rate is approvals divided by approvals plus refusals. Withdrawals, and decisions whose outcome the register does not state, are counted in the totals but not in the rate.
Why is a council missing?
A council is published when it has at least 25 timed decisions in the window and its register’s decision data passes our consistency checks. Councils that fail are listed with the reason rather than shown with a number that would mislead.
How often is this updated?
Nightly, from the decisions we collect from every council register we monitor. The window is the twelve months to the last complete month.