24-hour gym use at 215 Upper Richmond Road, Putney, London SW15
Summary of planning committee decision
Decided by Wandsworth Planning Applications Committee on 18 Dec 2025.
What was proposed
The application sought removal of the opening-hours condition so the existing gym could operate for customers 24 hours a day.
“This application proposes a removal of condition 3, originally imposed to restrict opening hours, to allow for 24-hour operation.”
“The premises shall not be open to customers other than between the hours of 06:00 and 22:00 Mondays to Saturdays and between 07:00 and 18:00 on Sundays and Bank Holidays, and at no other times. To safeguard the amenities of the neighbourhood, in accordance with Council policy DMS1”
Officer report
The site and surroundings
The gym occupies the ground floor of a six-storey building with residential uses above, near homes, flats and a burial ground.
“Currently operated as a gym/fitness centre at the ground floor level, part of a six-storey building commercial at ground floor and residential above. Directly opposite the site across Upper Richmond Road are three-storey terraced properties with commercial ground uses and flats above, a pair of two-storey semi-detached properties comprising ground floor commercial with residential above adjoin to the West, two/four-storey flats adjoining to the South (rear), St Mary's Burial…”
Officer report
Earlier planning permission
The proposal followed permission for changing a retail shop into a health club and gymnasium, which included restricted opening hours.
“Parent’ application: 2014/3180 – pp: Change of use from Class A1 (retail shop) to Class D2 (health club and gymnasium).”
Officer report
Consultation responses
Environmental Health raised no objection subject to a noise management plan, transport officers raised no objection and TfL had no comments.
“Number of letters sent 90 Site Notice Yes Press Notice Yes Number of responses received 10 Number of neighbour objections 10 Number of neighbour support 0 Number of neighbour comments 0”
“Internal Consultation (and external consultants on behalf of Council) Responses: summarised as: Environmental Health (Noise) – No objections, subject to the provision of a noise management plan.”
Officer report
Neighbour concerns
Ten neighbours objected, citing noise, rear-door security, odour from air-conditioning ducts, light pollution and inconsistency with the area.
“Neighbour Consultation Summary OBJECTIONS: summarised as: - Noise impacts - Security issues from open doors at the rear - Odour from air conditioning ducts…”
“Official Official - Light pollution - Inconsistent with the local area…”
Officer report
Committee discussion
Members discussed overnight staffing, fob access, weight noise, basement equipment, limited night use, monitoring and the absence of night classes or music.
“Members sought clarification on how the late-night operation would be staffed and referred to members of the gym who were able to gain access through the use of a fob. Members also asked about whether the premises would be entirely staff free and what would happen if there were to be any issues that neighbours may raise, given their concerns were about noise and disturbance.”
“In response, the Area Team Manager (West Team) explained of the applicants’ intention in that there would not be any staff on site in the night time as members of the gym would already have fob access to the premises.”
Minutes
Extra safeguards
The approved noise management plan restricted overnight weights, required warnings and signage, and allowed membership cancellation for repeated disturbance.
“Official Official 4. Condition NSTD – Noise management plan (additional condition) The gym shall be operated in accordance with the approved noise management plan ref: Anytime Fitness Putney – Noise Management Plan 14/11/2025, and shall adhere to the following conditions: i. The use of weights is restricted to the basement level free weight area during the period 2100hrs to 0700 hours. ii.”
Officer report
The vote
The committee unanimously agreed an 18-month temporary period so the operation could be reviewed after that time.
“The Chair suggested a condition of 18 months to 2 years for this proposal in order to see how successful it could operate, without causing problems for the neighbours. It was noted that this could then be reviewed after that period of time. A period of 18 months was agreed unanimously by the Committee.”
Minutes
The decision
Planning permission was granted as recommended, but only for a temporary period of 18 months.
“RESOLVED – (unanimous) that planning permission be granted as set out in the report, subject to Members’ resolution to grant permission for a temporary period of 18 months.”
Minutes
Sources
- Wandsworth Planning Applications Committee minutes, 18 December 2025
- Agenda and papers (council website)
Source: Plota analysis of Wandsworth's committee minutes and officer report. Quotations are the council's own words; headings and summaries are Plota's.
Committee decisions and nationwide planning applications, in one API
The Plota API returns planning applications from every council we cover, each with its decision, whether a committee or officers decided it, and the committee date. Build it into your own tools.
See the API →At the meeting
- Council
- Wandsworth
- Date
- Thursday 18 December 2025
- Recommendation
- Officers recommended approval
- Committee decided
- Approved
- Vote
- Unanimous
- Minutes
- The council's minutes
- Meeting
- Agenda and papers (council website)
- Application
- The application (council website)
- All decisions
- Wandsworth committee decisions →
This committee's year
23 decisions in the 12 months to this meeting, 1 against officer advice.
Source: Plota analysis of the committee's minutes.