Automated container storage building at Container Storage Yard London Gateway Drive, Stanford-le-Hope
Summary of planning committee decision
Decided by Thurrock Planning Committee on 9 Dec 2025.
What was proposed
The application proposed a fully automated high-bay facility for empty shipping containers, with associated offices, access, drainage, lighting and utilities.
“The proposal is for a fully automated high-bay storage facility for empty storage containers known as ‘BoxBay’. It has been developed to provide more efficient loading/unloading of ships and HGVs. The storage facility will be encased within a building which measures 323.5m x 163.2m and has a maximum height of 57m from floor level (62.9m AOD). The proposed building exceeds the height restrictions in the HEO therefore full planning permission is required.”
“PROPOSAL: The construction and operational use of an empty shipping container storage building (use class B8) within London Gateway Port with associated office/storage buildings, HGV/Shuttle carrier interchanges, access roadways/walkways, drainage facilities, lighting, boundary treatments and utility connections.”
Officer report
Planning background
Port development is principally authorised by the Harbour Empowerment Order, but this building required planning permission because it exceeds the Order’s height limits.
“Development within the Port has principally been carried out under the London Gateway Port Harbour Empowerment Order 2008 (“the HEO”) which authorises its construction and operation. The proposed building exceeds the height restrictions in the HEO therefore full planning permission is required.”
Officer report
What officers recommended
Officers recommended approval because the proposal supports port efficiency and economic development, with visual, technical and environmental matters addressed through conditions.
“The principle of the development is acceptable as it supports economic development within a Key Strategic Economic Hub in accordance with CSSP2.”
“The Traffic and Transportation information provided within Section 5.3 of the Planning Statement sets out that the proposal is expected to improve Port efficiency by reducing the number of movements anticipated to be undertaken by the Automated Stacking Cranes (ASCs) and reducing the time required to load / unload full containers.”
Officer report
Consultation and public views
Consultees raised no objections subject to conditions or advice, and no public comments or objections were received.
“Standing advice on need to support a modal shift away from car travel.”
“Site notices were displayed on site, and the application was publicised in the press. No comments or objections have been received.”
Officer report
Who spoke
A speaker gave a statement supporting the application and answered a question about crane heights.
Members’ discussion
A co-optee asked about crane heights, and there were no further questions or debate.
“The Co-optee sought clarification on the height of the cranes. The speaker confirmed it was dependent on the type of crane. One is approximately 35 metres the key cranes that load the ships are up to 145 metres. With the boon down it would be half the height.”
“There were no further questions for the speaker or officers. There was no debate.”
Minutes
The decision
The recommendations were approved, including the finding on protected European sites and authority to grant permission subject to conditions.
“1.Formally determine, on the basis of the information available, that the development proposed will not adversely affect the integrity of a European site or a European offshore marine site either alone or in combination with other plans or projects.”
“If recommendation 1 agreed, the Chief Planning Officer be authorised to GRANT permission for the development subject to those items set out in section 16 of the report - A. Conditions…”
Minutes
Sources
- Thurrock Planning Committee minutes, 9 December 2025
- Agenda and papers (council website)
Source: Plota analysis of Thurrock's committee minutes and officer report. Quotations are the council's own words; headings and summaries are Plota's.
Committee decisions and nationwide planning applications, in one API
The Plota API returns planning applications from every council we cover, each with its decision, whether a committee or officers decided it, and the committee date. Build it into your own tools.
See the API →At the meeting
- Committee
- Thurrock Planning Committee
- Council
- Thurrock
- Date
- Tuesday 9 December 2025
- Recommendation
- Officers recommended approval
- Committee decided
- Approved
- Vote
- 5 for, 0 against
- Minutes
- The council's minutes
- Meeting
- Agenda and papers (council website)
- Application
- The application (council website)
- All decisions
- Thurrock committee decisions →
Source: Plota analysis of the minutes.
This committee's year
19 decisions in the 12 months to this meeting, 2 against officer advice.
Source: Plota analysis of the committee's minutes.