Battery energy storage system at Tean Leys Farm, Tean Leys, Lower Tean
Summary of planning committee decision
Deferred by Staffordshire Moorlands Planning Applications Committee on 23 Apr 2026.
What was proposed
The application sought a 70MW battery storage facility with substations, underground cables, access, fencing and landscaping.
“This is full planning application which seeks consent for the construction of a Battery Energy Storage System (BESS) facility, associated infrastructure, customer substation, cable routing, access and landscaping.”
“The development would provide a facility with a 70MW capacity in total. This would be split into two sections with 50MW of storage connected to the approved new 132kv substation to the south (approved as part of a solar farm development), and 20MW connected to the 33kv substation off Cheadle Road in Upper Tean.”
Officer report
Site and surroundings
The main site was a 4.1-hectare agricultural field in open countryside, surrounded by fields, hedgerows, scattered trees, homes and infrastructure.
“The site predominantly relates to an agricultural field which extends to 4.1ha in area which is located within the open countryside as defined by the Local Plan Policies Map. The application boundary in total extends to 10.7ha and includes a series of narrow corridors of land. These includes:”
“The main application site parcel is generally open. There are slight land level changes with levels dropping north to south. Site boundaries comprise a mix of hedgerows, with scattered trees and fencing. The site is generally surrounded by open agricultural fields. To the east of the site is a telecommunications mast with Tean Leys Farm located further to the east. The wider landscape comprises…”
Officer report
What officers recommended
Officers recommended approval subject to a legal agreement, conditions and no objection from Staffordshire Wildlife Trust.
“Accordingly, the proposal is considered to comprise sustainable development under the terms of the NPPF, and is in general conformity with the Policies of the Staffordshire Moorlands Local Plan 2020 when considered as a whole, and the Checkley neighbourhood Plan, and is recommended for approval.”
“A. That the Head of Planning in conjunction with the Chair be given delegated authority to APPROVE subject to no objection from Staffordshire Wildlife Trust; and…”
Officer report
Who spoke
Speakers included three councillors and an objector against the application, and the agent for the application.
Members’ concerns
Members questioned the cable route, village disruption, traffic, parking, bridge capacity, diversion arrangements and missing consultee responses.
“Members discussed the location of the site and the proposed cable route, including the requirement to connect an additional site to the Tean substation. Concerns were raised regarding disruption through the village, traffic management arrangements, and the temporary loss of car park facilities during the construction period. Members also commented on the proposed route for construction traffic, noting that it was…”
“Members commented that the level of traffic using the affected roads during the construction period should be revisited, noting in particular that approximately 250 quarry vehicles currently use the route daily. They requested further information from Highways on the proposed diversion arrangements that would be in place during this time.”
Minutes
The committee’s decision
The committee deferred the application for further information about connections, emergency access, conditions, construction traffic and outstanding consultee comments.
“That the application be deferred to allow the applicant to provide further information to Planning Officers regarding:”
“- Reasoning behind 2 connection points - Single point of access to the site in an emergency - To address and minimise conditions - Cumulative impact of construction access on narrow lanes…”
Minutes
Sources
- Staffordshire Moorlands Planning Applications Committee minutes, 23 April 2026
- Agenda and papers (council website)
Source: Plota analysis of Staffordshire Moorlands's committee minutes and officer report. Quotations are the council's own words; headings and summaries are Plota's.
Committee decisions and nationwide planning applications, in one API
The Plota API returns planning applications from every council we cover, each with its decision, whether a committee or officers decided it, and the committee date. Build it into your own tools.
See the API →At the meeting
- Council
- Staffordshire Moorlands
- Date
- Thursday 23 April 2026
- Committee decided
- Deferred
- Minutes
- The council's minutes
- Meeting
- Agenda and papers (council website)
- Application
- The application (council website)
- All decisions
- Staffordshire Moorlands committee decisions →
This committee's year
34 decisions in the 12 months to this meeting, 4 against officer advice.
Source: Plota analysis of the committee's minutes.