What was proposed

The application sought ground, first and second floor extensions, internal and external alterations, and modernisation of the care home.

“Full planning permission is sought for the construction of ground, first and second floor extensions, along with internal and external alterations, at Pontypridd Nursing Home, Maesycoed Road, Maesycoed, Pontypridd.”

“The proposal would see the two existing buildings on site combined via a new extension to create one larger structure, together with the creation of a full second floor spanning the full area of the building. In addition, the proposal would see the construction of a number of single storey extensions and a first floor conservatory type extension along the south west elevation.”

Officer report

The site and its history

The vacant care home has 56 rooms in two buildings, with 14 ensuite rooms, parking near the entrance and residential surroundings.

“The application site relates to Pontypridd Nursing Home which is a residential care home located within Maesycoed, Pontypridd. Access to the site is gained via a shared access from Maesycoed Road with the site set back and elevated from the highway.”

“The site is currently vacant although it has been in operation for many years. The home consists of 56 rooms and was registered with Care Inspectorate Wales (CIW) to provide accommodation and personal care to a maximum of 56 elderly and disabled people. Out of 56 existing rooms only 14 are facilitated with an ensuite. The property currently forms two detached buildings located centrally with an area for parking towards the site entrance.”

Officer report

What officers recommended

Officers recommended approval because the scheme would meet local care needs, address a care home shortfall and comply with planning requirements.

“REASONS: The site offers an opportunity for a tailored scheme to meet local needs and will aid in addressing the known care home shortfall in the County Borough. The proposal would be developed at an existing care home, within the defined settlement limits of Pontypridd and is considered acceptable in terms of the requirements of planning policy and all relating material planning considerations.”

Officer report

The main planning impacts

The extensions were considered acceptable in principle, visually appropriate and unlikely to cause unacceptable effects on neighbouring privacy, overshadowing or disturbance.

“Concerns regarding potential overshadowing have been raised by objectors in relation to the proposed development. It is acknowledged that the introduction of a second floor would result in some degree of additional overshadowing to neighbouring properties. However, as evidenced by the submitted shadow analysis, the existing built form already generates substantial shadowing across the adjacent plots.”

“Finally, existing residents living close to the site will have experienced the impact of the day- to-day operation of the property in its previous guise. As such, whilst it is considered that the operation of the new care home may result in some intensification of the site given its greater scale, it is not considered that the level of noise and disturbance would exacerbate existing levels experienced by neighbouring occupiers.”

Officer report

Consultation responses

Transport, ecology, drainage, fire, police, water, public health and mining consultees raised no objection, subject to specified conditions or controls.

“No objection although condition suggested in relation to surface water drainage.”

“No objection although conditions recommended in relation to hours of construction, noise, dust and waste.”

Officer report

Objections from neighbours

Four neighbouring households objected over overshadowing, access, noise, construction, privacy, bats, overdevelopment, parking, pollution and nuisance odours.

“Overshadowing of neighbouring properties. • Rights of access. • Noise and disturbance associated with the use. • Construction impacts. • Loss of privacy…”

“Impact upon bats • Overdevelopment of the site. • Lack of parking • Air pollution • Information provided in supporting information is inaccurate. • Nuisance odours from cooking and staff/resident smoking.”

Officer report

The committee decision

The committee approved the application in line with the recommendation, but amended Condition 3 to remove wording allowing later written agreement.

“The Head of Planning presented the application to Committee and following consideration it was RESOLVED to approve the application in accordance with the recommendation of the Director, Prosperity and Development subject to the amendment of Condition 3 to remove the words “unless otherwise agreed in writing by the Local Planning Authority” so the condition is as follows:”

“No development shall take place, including any works of site clearance, until a Construction Method Statement has been submitted and approved in writing by the Local Planning Authority to provide for;”

Minutes

Sources

  • Rhondda Planning and Development Committee minutes, 18 September 2025
  • Agenda and papers (council website)

Source: Plota analysis of Rhondda's committee minutes and officer report. Quotations are the council's own words; headings and summaries are Plota's.

Committee decisions and nationwide planning applications, in one API

The Plota API returns planning applications from every council we cover, each with its decision, whether a committee or officers decided it, and the committee date. Build it into your own tools.

See the API →

At the meeting

Council
Rhondda
Date
Thursday 18 September 2025
Recommendation
Officers recommended approval
Committee decided
Approved
Minutes
The council's minutes
Meeting
Agenda and papers (council website)
Application
The application (council website)

This committee's year

22 decisions in the 12 months to this meeting, 2 against officer advice.

Source: Plota analysis of the committee's minutes.

Every decision by this council's committees →