Quarry operations extension at Blackhillock Quarry, Keith
Summary of planning committee decision
Decided by Moray Planning and Regulatory Services Committee on 5 Mar 2026.
What was proposed
The application sought to vary two conditions to extend quarry operations until 31 October 2040 and enable work under an amended site design.
“This application under section 42 of the Town and Country Planning (Scotland) Act 1997 seeks to vary the terms of condition 2 and 11 of planning permission 03/01286/MIN, granted on 12 February 2004 for the expansion of working area of Blackhillock Quarry, Keith. • A 1.98-hectare extension to Blackhillock Quarry was granted planning consent in February 2026 (25/00917/APP).”
“Condition 11 provides that no extraction shall occur beyond 6 months of the date of the consent unless details showing the proposed extraction levels of the site have been submitted to and approved by the planning authority. The current application seeks to vary this condition to provide for working to take place in accordance with the proposed amended site design.”
Officer report
The site
The working quarry covers about 10.33 hectares south of Keith, near homes, another quarry, a roads depot and agricultural land.
“The site is a working quarry extending to approx. 10.33 hectares (including recently approved extension). • Areas of the original consent (03/01286/MIN) are now occupied by the Trunk Roads Depot or are part of the permission (22/00499/APP) for the adjacent Cairdshill Quarry. • The site is located approx. 1.6 km to the south of Keith.”
“The site is bounded by Cairdshill Quarry to the east, the Amey Keith Roads Depot to the northwest, a minor public road immediately to the north, and agricultural land to the south and southwest. The A96 lies further to the east and the Blackhillock substation further to the west. • The nearest dwellings to the site are Blackhillock Cottages, located approx. 20m from the site boundary.”
Officer report
Planning history
The quarry has operated under permissions granted in 1999, 2004 and 2006, with a further southern extension approved recently.
“Application site - Blackhillock Quarry 25/00917/APP - Application for planning permission for extension to southern boundary of the existing quarry – granted planning permission recently under delegated powers.”
“05/0809/MIN – Application for planning permission for extension to southern boundary of the existing quarry at Blackhillock Quarry – granted planning permission 27 February 2006 under delegated powers.”
Officer report
What officers recommended
Officers recommended approval because the proposal supported the approved extension, retained existing controls and complied with relevant planning policies.
“Conclusion and Recommendation This application relates to the proposed extension of the duration of an existing permission and to provide for working to take place in accordance with proposed amended site design for Blackhillock Quarry. This is necessary for the recently approved extension (25/00917/APP) to Blackhillock Quarry.”
“The proposed variation to conditions 2 and 11 of planning consent 03/01286/MIN to extend the operational life of the existing permitted site until 31 October 2040 and to provide for working to take place in accordance with proposed amended site design, subject to other updated conditions, is considered to comply with relevant policies of National Planning Framework 4 and the Moray Local Development Plan 2020, and there are no material considerations that indicate otherwise.”
Officer report
Main effects considered
The assessment found no unacceptable effects on the natural or built environment, with landscape, water, biodiversity, amenity and transport impacts controlled by conditions.
“The proposal seeks to extend the operational lifetime of the existing quarry within its currently approved footprint to allow for the approved extension to the quarry (25/00917/APP) to operate. There are no changes to the nature of operations or to the conditions under which the quarry currently operates.”
“As detailed in the assessment and set out in the accompanying report, the continuation of quarrying activities would not result in any unacceptable adverse impacts on either the natural or built environment. All potential effects associated with the development have previously been considered and are adequately controlled through the conditions attached to the existing planning permissions.”
Officer report
Consultation responses
consultees raised no objection, although Environmental Health and Transportation requested conditions covering quarry operations, noise, blasting, dust, visibility and vehicle routing.
“Environmental Health – No objection subject to conditions (if permitted) relating to permitted quarry operating hours, noise levels, blasting operations, ground vibrations and dust management.”
“Transportation Manager – No objection subject to conditions (if permitted) related to a visibility splay, vehicle routing and no water or loose material being carried onto the public road.”
Officer report
The committee vote
The committee unanimously agreed to grant planning permission subject to the listed conditions and reasons.
“Following consideration, the Committee unanimously agreed to grant planning permission in respect of Planning Application 25/00916/APP subject to the following conditions and reasons:”
Minutes
The final decision
Permission was granted until 31 October 2040, with conditions requiring the approved quarry design, restoration, transport controls and protection of local amenity.
“The permission hereby granted shall be for a limited period only and shall cease on 31 October 2040 (the ‘cessation’ date).”
“Unless otherwise agree in writing with the Council, as Planning Authority, the development must comply with condition 11 relating to vehicle routing of planning permission (reference number 99/00130/FUL) approved on the 21 October 1999 and Condition 9 of planning permission 03/01286/MIN approved on 12 February 2004.”
Minutes
The members' reasons
“The Committee noted that the application had been referred to Committee as this is a major application.”
Minutes
Approved subject to 5 conditions, set out in the minutes.
Source: the council's minutes, quoted word for word.
Sources
- Moray Planning and Regulatory Services Committee minutes, 5 March 2026
- Agenda and papers (council website)
Source: Plota analysis of Moray's committee minutes and officer report. Quotations are the council's own words; headings and summaries are Plota's.
Committee decisions and nationwide planning applications, in one API
The Plota API returns planning applications from every council we cover, each with its decision, whether a committee or officers decided it, and the committee date. Build it into your own tools.
See the API →At the meeting
- Council
- Moray
- Date
- Thursday 5 March 2026
- Recommendation
- Officers recommended approval
- Committee decided
- Approved
- Vote
- Unanimous
- Minutes
- The council's minutes