What was proposed
Listed building consent was sought for four air source heat pumps, associated works and additional radiators.
“25/00427/LB Listed building consent for the installation of air source heat pumps with associated development including the installation of additional radiators. Castle Ward A”
Minutes
What officers recommended
Officers recommended approval subject to standard listed building timescale and approved plans conditions.
“That Listed Building Consent BE GRANTED subject to the following conditions:”
“Condition no. Description Type 1 Standard Listed Building Timescale Control 2 Approved plans Control…”
Officer report
Heritage impact
The heat pumps would cause a low level of less than substantial harm to the listed building, but the scheme would improve sustainability.
“The ASHPs previously approved as part of application ref 22/00388/FUL were more industrial in scale and form. The current scheme proposes four smaller ASHPs which are of a more domestic scale and as such there will be no requirement for acoustic enclosures. The units would cause some harm to the setting of the listed building and its bow window which overlooks this space.”
“The identified minor level of less than substantial harm to the listed building arising from the ASHPs and associated works is outweighed by the public benefits in the form the removing reliance upon non-renewable gas supplies and the decarbonisation and improved efficiency and sustainability of building stock.”
Officer report
Specialist advice
The Conservation Officer was satisfied that the internal plant, pipework, electrical supplies and additional radiators would not cause adverse heritage impacts.
“The scheme will involve the installation of associated plant equipment within the basement which is accessed via the courtyard. The necessary associated pipework will require two new 100mm diameter penetrations through the fabric of the building to allow for flow and return pipework to reach the plantroom and the electrical supplies for the ASHPs. This will be supplied from the new Molded Case Circuit Breaker (MCCB) panel board in the basement switch room.”
Officer report
Committee proposal
Councillor Martin Gawith proposed approval, seconded by Councillor Keith Budden, subject to the committee report conditions.
“It was proposed by Councillor Martin Gawith and seconded by Councillor Keith Budden:”
“That the application be approved subject to the conditions in the Committee Report.”
Minutes
Vote and decision
Ten councillors voted for approval, with none against or abstaining, and the application was approved with two conditions.
“Upon being put to the vote, 10 Councillors voted in favour of the proposal with none against and no abstentions, whereupon the Chair declared the proposal to have been carried.”
“That the application be approved subject to the following conditions:”
Minutes
Sources
- Lancaster Planning Regulatory Committee minutes, 23 June 2025
- Agenda and papers (council website)
Source: Plota analysis of Lancaster's committee minutes and officer report. Quotations are the council's own words; headings and summaries are Plota's.
Committee decisions and nationwide planning applications, in one API
The Plota API returns planning applications from every council we cover, each with its decision, whether a committee or officers decided it, and the committee date. Build it into your own tools.
See the API →At the meeting
- Council
- Lancaster
- Date
- Monday 23 June 2025
- Committee decided
- Approved
- Vote
- 10 for, 0 against
- Minutes
- The council's minutes
- Meeting
- Agenda and papers (council website)
- Application
- The application (council website)
- All decisions
- Lancaster committee decisions →
Source: Plota analysis of the minutes.
This committee's year
7 decisions in the 12 months to this meeting.
Source: Plota analysis of the committee's minutes.