Battery energy storage system at Land 295M South Of Mill House Stainland, Thurso
Summary of planning committee decision
Decided by Highland Planning Applications Committee on 10 Jun 2026.
What was proposed
The application sought to extend the existing permission by one year and amend the battery storage system’s siting, design and ancillary infrastructure.
“PROPOSED DEVELOPMENT 1.1 This application has been submitted under Section 42 of the Town and Country Planning (Scotland) Act 1997 (as amended). It seeks to amend the wording of Condition 14 attached to planning permission 22/02054/FUL, as well as to approve subsequent changes to the siting, design and ancillary infrastructure.”
“The previously approved development comprised up to 50 battery storage containers (with integrated air conditioning units and external inverters) arranged in paired units with shared transformers, a Distribution Network Operator (DNO) control building, site office and storage containers, security and acoustic fencing, CCTV infrastructure, areas of hardstanding, parking provision, a new access onto the A9(T), surface water drainage, and associated landscaping.”
Officer report
The site and surroundings
The site is 1.85 hectares of agricultural land in a rolling landscape about 1.7 kilometres south-east of Thurso, near homes and the Thurso South substation.
“Supporting Information: • Supporting Statement • Biodiversity Net Gain Report • Supporting Letter • Noise Impact Assessment • Landscape Management Plan • Acoustic Fencing Details • Visualisations (Viewpoints 1–7) • Viewpoint 5 Comparative Wireline • Cumulative Assessment Plan • Drainage Report • Ecological Assessment • Pre Application Consultation Report 1.10 Variations: Multiple variations to submitted drawings occurred during the assessment of this application in line…”
“The surrounding pattern of development is characterised by dispersed housing and agricultural businesses, with the nearest properties being Upper Geiselittle (250m), Bainstown House (315m), Mill House Stainland (470m), and Four Winds (700m). Of relevance to this proposal lies the Thurso South substation, approximately 1km to the southwest.”
Officer report
Consultation responses
Environmental Health, transport bodies, SEPA, heritage services, ecology and other consultees raised no objection, with some requesting conditions.
“Transport Planning: No objection. Advised that whilst the revisions include changes to the layout and overall scale of the development, these generally reflect a reduction in the extent of development, including a lower number of units and a reduced footprint.”
“Following revisions, advised the latest surface water drainage design is more comprehensive than the info received for the previous application 22/02054/FUL. As such, the Flood Team remain content with the proposals and request a condition on the final drainage design. Ecology: No objection informally responded stating that the Ecology Service are content with the proposals. Requested conditions regarding Habitat Management and GIS Data.”
Officer report
The committee decision
The committee agreed to grant planning permission subject to the conditions detailed in the report.
“25/03236/S42) (PLN/038/26) Location: Land 295M South of Mill House, Stainland, Thurso (Ward 03). Nature of Development: Application for S42 to amend the wording of condition 14 of planning consent 22/02054/FUL and subsequent changes to siting, design and ancillary infrastructure. . Recommendation: GRANT”
“The Committee AGREED to GRANT planning permission subject to the conditions detailed in the report.”
Minutes
Sources
- Highland Planning Applications Committee minutes, 10 June 2026
- Agenda and papers (council website)
Source: Plota analysis of Highland's committee minutes and officer report. Quotations are the council's own words; headings and summaries are Plota's.
Committee decisions and nationwide planning applications, in one API
The Plota API returns planning applications from every council we cover, each with its decision, whether a committee or officers decided it, and the committee date. Build it into your own tools.
See the API →At the meeting
- Council
- Highland
- Date
- Wednesday 10 June 2026
- Recommendation
- Officers recommended approval
- Committee decided
- Approved
- Minutes
- The council's minutes
- Meeting
- Agenda and papers (council website)
- Application
- The application (council website)
- All decisions
- Highland committee decisions →
This committee's year
10 decisions in the 12 months to this meeting.
Source: Plota analysis of the committee's minutes.