Four residential dwellings at Forge and Forge Hall, Lytchett Minster

Summary of planning committee decision

Decided by Dorset Eastern Area Planning Committee on 24 Jun 2026.

P/FUL/2025/07220Approved

Consultation responses

Natural England, highways, ecology, trees and biodiversity consultees raised no objections, while the conservation officer preferred repair and reuse of Forge Hall.

“Consultations All consultee responses can be viewed in full on the website. Consultees 1. Natural England No objections raised on basis of the Appropriate Assessment concluding no adverse effects on European conservation sites and that appropriate mitigation will be secured & the purchase of nitrogen credits will mitigate the proposal’s impact on the nutrient neutrality of Poole Harbour 2. Scotia Gas Network (SGN) No objections raised.”

“DC Tree Officer No objections raised. Condition advised requiring compliance with the submitted Arboricultural Method Statement and Tree Protection Plan (via condition) 5. DC Natural Environment Team - Ecology No objections raised. Certificate of Approval issued for the submitted Ecological Impact Assessment (EcIA) 6. DC Natural Environment Team – Biodiversity Net gain No objections raised. Documents submitted reflect the habitat degradation which has taken place.”

Officer report

Objections and concerns

The parish council and one objector raised concerns about overdevelopment, heritage, design, access, privacy, outlook, drainage, biodiversity and asbestos.

“Lytchett Minster & Upton Parish Council Objection • Overdevelopment, adverse impact on character and appearance of the conservation area & street scene and harm setting of listed buildings. No clear and convincing justification provided for this harm, nor sufficient public benefit to outweigh it • Loss of hall regrettable as has historic importance to the local community. Development should make reference to it or its significance.”

“Summary of comments of objection: • Overlooking/loss of privacy • Reduced outlook/sense of enclosure • Loss of privacy • Need to prevent any windows in the side elevation facing Gavity • Impact on outlook at front of Gavity from boundary wall • Adverse impact on character of the area • No Heritage Impact Assessment • Proposal fails to show 10% Biodiversity Net Gain • Habitats Regulations Assessment required • Drainage Assessment required • Asbestos concerns…”

Officer report

The committee’s decision

The application was granted subject to conditions controlling commencement, contamination, drainage, construction, heritage recording, ecology, design, landscaping, parking and privacy.

“P/FUL/2025/07220 Location: Forge and Forge Hall Dorchester Road Lytchett Minster BH16 6HT Description: Demolition of existing building and erection of four residential dwellings, including associated landscaping. As amended by plans to amend access. Decision: That the application be granted subject to the following conditions. 1.”

“Prior to the commencement of development, and notwithstanding the submitted Drainage Strategy by GAP Ltd, a detailed surface water management scheme for the site, based upon the hydrological and hydrogeological context of the development, and providing clarification of how drainage is to be managed during construction and a timetable for implementation of the scheme shall be submitted to and approved in writing by the Local Planning Authority.”

Minutes

Main conditions

The permission requires nutrient credits, historic building recording, tree protection, ecological measures, approved materials, landscaping, parking and restrictions on windows and extensions.

“No development shall commence until the necessary nutrient mitigation credits to mitigate the impacts of the development on the Poole Harbour/River Avon/Somerset Levels and Moors Special Protection Area (SPA) and Ramsar have been secured from an accredited nutrient provider and a copy of the…”

“No demolition, works or development shall take place until a written scheme of historic building recording, post recording analysis and publication, has been submitted to and approved in writing by the Local Planning Authority. The development hereby approved shall only be implemented in full accordance with the approved historic building recording scheme.”

Minutes

Sources

  • Dorset Eastern Area Planning Committee minutes, 24 June 2026
  • Agenda and papers (council website)

Source: Plota analysis of Dorset's committee minutes and officer report. Quotations are the council's own words; headings and summaries are Plota's.

Committee decisions and nationwide planning applications, in one API

The Plota API returns planning applications from every council we cover, each with its decision, whether a committee or officers decided it, and the committee date. Build it into your own tools.

See the API →

At the meeting

Council
Dorset
Date
Wednesday 24 June 2026
Recommendation
Officers recommended approval
Committee decided
Approved
Minutes
The council's minutes
Meeting
Agenda and papers (council website)
Application
The application (council website)

This committee's year

31 decisions in the 12 months to this meeting, 4 against officer advice.