Battery energy storage system at Hurst Farm, Tibshelf, Alfreton

Summary of planning committee decision

Decided by Bolsover Planning Committee on 10 Dec 2025.

25/00302/FULApproved

What was proposed

The application proposed a 99.9MWac battery energy storage system, substation, access, landscaping and associated infrastructure for 40 years.

“The application proposes the ‘Installation and Operation of Energy Storage System (ESS) including Energy Storage Units, Substation, Site Access, Landscaping & Associated Infrastructure’. This comprises the following elements:”

“The ESS stores electricity in batteries and releases it when needed, helping to balance energy supply and demand. The proposed development is projected to have a storage capacity of 99.9MWac. The planning application seeks temporary permission for a period of 40 years from the date it is first brought into use.”

Officer report

The site and surroundings

The site covered about 7.9 hectares of agricultural land beside the M1, with public footpaths, surrounding fields and nearby industrial land.

“The site comprises approximately 7.9 hectares of agricultural land at Hurst Farm, Tibshelf. The farm building complex sits at the end of a long access road off Mansfield Road, to the east of the M1 motorway. The main part of the application site comprises a detached and distinct agricultural field to the north of the farm complex, with topography that drops from west to east.”

Officer report

What officers recommended

Officers recommended approval because the benefits of energy security and renewable energy outweighed countryside-policy conflict and limited visual and heritage harm.

“While the proposed development does not directly generate renewable energy, it does provide for the storage of energy produced by renewable sources that would otherwise be wasted if the full demand does not exist at the time it is generated.”

“On balance, the conflict with countryside policies of the Local Plan and harm identified is considered to be outweighed by benefits of the development, having regard to the importance of energy security, the importance of supporting the provision and use of renewable energy, national policy and guidance on the subject and related appeal decisions.”

Officer report

Public views

One landowner supported the proposal, citing farm income, continued agricultural use, screening and no unacceptable construction or operational effects.

“The proposed development will provide us with an additional income stream, supporting the diversification of activities at Hurst Farm. This would help the farm become more resilient to volatile energy prices and future market conditions, supporting its viability and therefore the continued agricultural use of land at Hurst Farm.”

Officer report

Members’ discussion

Members discussed screening, the site’s distance from historic assets, energy storage, environmental and national-security benefits, landscaping, noise and lighting.

“A Member provided thanks to the report and stated the site proved a substantial distance from the site of historical importance and that with natural tree foliage would be likely hidden / partially hidden for all but the winter months.”

“A Member added to the previously raised environmental benefits the national security benefits such a proposal would bring.”

Minutes

The committee vote

The committee voted nine in favour and none against, following a proposal moved by Councillor Tom Munro and seconded by Councillor Phil Smith.

“Moved by Councillor Tom Munro and seconded by Councillor Phil Smith RESOLVED that application no. 25/00302/FUL be APPROVED subject to the following conditions:”

Minutes

Conditions

Approved subject to 4 conditions, set out in the minutes.

Sources

  • Bolsover Planning Committee minutes, 10 December 2025
  • Agenda and papers (council website)

Source: Plota analysis of Bolsover's committee minutes and officer report. Quotations are the council's own words; headings and summaries are Plota's.

Committee decisions and nationwide planning applications, in one API

The Plota API returns planning applications from every council we cover, each with its decision, whether a committee or officers decided it, and the committee date. Build it into your own tools.

See the API →

At the meeting

Council
Bolsover
Date
Wednesday 10 December 2025
Recommendation
Officers recommended approval
Committee decided
Approved
Minutes
The council's minutes
Meeting
Agenda and papers (council website)
Application
The application (council website)

This committee's year

17 decisions in the 12 months to this meeting, 1 against officer advice.

Source: Plota analysis of the committee's minutes.

Every decision by this council's committees →