Plot 6 Northampton Gateway Rail Freight Interchange Northampton Data via plota.co.uk

2025/3738/MAF - Full Planning Permission (Major) Approved

Proposal

Construction of a storage and distribution building (B8 use), including ancillary office space, together with ancillary buildings with associated access, parking, service and yard areas, drainage, landscaping and associated infrastructure at Plot 6, Northampton Gateway SRFI, Northampton. Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
13 Aug 2025
✓
Validated
14 Aug 2025
✓
Approved
17 Apr 2026

Approved on 17 Apr 2026 · Committee · Last checked 22 Oct 2026

Documents 75

Plans & drawings 37

PDF Plan - Elevations (Proposed) Document · 1 Sept 2025 View ↗ PDF Plan - Elevations (Proposed) Document · 1 Sept 2025 View ↗ PDF Plan - Floor Document · 1 Sept 2025 View ↗ PDF Plan - Floor Document · 1 Sept 2025 View ↗ PDF Plan - Floor Document · 1 Sept 2025 View ↗ PDF Plan - Floor Document · 1 Sept 2025 View ↗ PDF Plan - Site Plan (Proposed) Document · 1 Sept 2025 View ↗ PDF Plan - Site Plan (Proposed) Document · 1 Sept 2025 View ↗ PDF Plan - Elevations Document · 13 Aug 2025 View ↗ PDF Plan - Elevations Document · 13 Aug 2025 View ↗ PDF Plan - Floor Document · 13 Aug 2025 View ↗ PDF Plan - General Document · 13 Aug 2025 View ↗ PDF Plan - General Document · 13 Aug 2025 View ↗ PDF Plan - General Document · 13 Aug 2025 View ↗ PDF Plan - General Document · 13 Aug 2025 View ↗ PDF Plan - General Document · 13 Aug 2025 View ↗ PDF Plan - General Document · 13 Aug 2025 View ↗ PDF Plan - General Document · 13 Aug 2025 View ↗ PDF Plan - General Document · 13 Aug 2025 View ↗ PDF Plan - General Document · 13 Aug 2025 View ↗ PDF Plan - Landscaping Document · 13 Aug 2025 View ↗ PDF Plan - Landscaping Document · 13 Aug 2025 View ↗ PDF Plan - Landscaping Document · 13 Aug 2025 View ↗ PDF Plan - Landscaping Document · 13 Aug 2025 View ↗ PDF Plan - Landscaping Document · 13 Aug 2025 View ↗ PDF Plan - Landscaping Document · 13 Aug 2025 View ↗ PDF Plan - Landscaping Document · 13 Aug 2025 View ↗ PDF Plan - Landscaping Document · 13 Aug 2025 View ↗ PDF Plan - Landscaping Document · 13 Aug 2025 View ↗ PDF Plan - Landscaping Document · 13 Aug 2025 View ↗ PDF Plan - MasterPlan Document · 13 Aug 2025 View ↗ PDF Plan - Roof Document · 13 Aug 2025 View ↗ PDF Plan - Sections (Proposed) Document · 13 Aug 2025 View ↗ PDF Plan - Sections (Proposed) Document · 13 Aug 2025 View ↗ PDF Plan - Sections (Proposed) Document · 13 Aug 2025 View ↗ PDF Plan - Sections (Proposed) Document · 13 Aug 2025 View ↗ PDF Site Location Plan Document · 13 Aug 2025 View ↗

All documents on the council site ↗

Associated applications 2

Site constraints 4

Agricultural land, grade 3b
Not best and most versatile land (grades 1, 2 and 3a). Source: the Predictive Agricultural Land Classification Map (Defra and Natural England, 2025; the Welsh Government's Predictive ALC Map 2 in Wales), a model rather than a site survey. Natural England's Provisional ALC map (1:250,000, 1970s) agrees.
Where development of farmland is needed, policy prefers poorer land over the best and most versatile (grades 1, 2 and 3a). Three sources: Natural England's post-1988 field surveys, which are definitive where they exist; the Defra predictive map for England (2025) and the Welsh Government predictive map, modelled from the soil map with 3a and 3b split; and the 1970s provisional map, which planners and other services still show, coarser and with grade 3 undivided. Where the provisional and predicted grades disagree, treat the predicted grade as the current estimate and expect an application to carry its own survey.
Public footpath about 21 m away
Matters where it crosses or adjoins the site: obstructing a path without a diversion order is an offence, and work cannot start until the order is confirmed.
Compiled from highway authority data, not the legal definitive map. A few authorities have not published, so no path shown is not proof there is none.
National infrastructure project about 671 m away: Northampton Gateway Rail Freight Interchange
The site is about 671 m from the project boundary. Rail freight interchange, decided. The project page says whether consent was granted.
Nationally significant infrastructure projects (power stations, electricity lines, pipelines, major roads and railways, harbours, airports and reservoirs) are consented by a Secretary of State under the Planning Act 2008, after an examination by the Planning Inspectorate, rather than by the council. The boundary is the one the Inspectorate consults on and can change as the scheme does. Projects are shown within 2 km of the site.
Planning Inspectorate project page ↗
Also on the record
Radon affected area, class 3.
Not affected
Outside flood zones 2 and 3 · Not green belt · No scheduled monument at the site

Checked on 17 October 2026. The pin for this application is the centre of its postcode rather than the building, so distances to nearby designations are measured from the postcode and can be out by the width of the postcode area. Historic England, the Environment Agency, Natural England, the Planning Inspectorate, the British Geological Survey and UK Health Security Agency (radon, contains BGS materials © UKRI) and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Work with planning data?

Every application in West Northamptonshire - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Application type
Full Planning Permission (Major)
Received
13 Aug 2025
Validated
14 Aug 2025
Ward
Hackleton and Roade Ward
Parish
Milton Malsor
Target decision
20 Apr 2026
Decision
Approval
Decision date
17 Apr 2026
Decision level
Committee
Applicant
Show
Agent
Oxalis Planning Ltd

How this decision compares

Decided in 246 days from validation, 147 days slower than West Northamptonshire's median of 99 for full applications. Approved, as 90% of full applications here are.

11%decided within 8 weeks
90%approved
6%go to committee

Plota live figures for full applications decided by West Northamptonshire in the last twelve months, from validation. West Northamptonshire decision record →

Consultation & key dates

Comments by
15 Dec 2025
Committee
16 Dec 2025
West Northamptonshire
Planning Authority Score
1.7/10
Poor
#280 of 296 councils
Relevant to this application:
Major dwellings

West Northamptonshire is one of the slowest councils in England for householder decisions, ranking #295 out of 296. The council extends the time limit on 79% of applications - one of the highest rates in England. Expect your application to take longer than the standard deadline. Householder applications are slightly more likely to be approved here (93%) than the national average (90%).

Among the slowest councils in England
for householder decisions
These figures are council-wide context, not a prediction for this application. View full council performance
West Northamptonshire decision statistics
Based on MHCLG data, the year to March 2026
90%
Overall approval rate
Above avg (87%) #123 of 296
93%
Householder approved
Above avg (90%) #144 of 296
18%
Decided in 8 weeks
Below avg (63%) #295 of 296
79%
Extended time limit
Above avg (41%) #295 of 296
81%
Minor dwellings approved
170 decided (1-9 homes)
83%
Major dwellings approved
24 decided (10+ homes)
86%
Change of use approved
207 decided
1,832
Total decisions
179 refused in the year to March 2026