Hop Poles 17 - 19 King Street London W6 9HR Data via plota.co.uk

2025/02609/LBC - Listed Building Consent Approved

Proposal

Display of 1no internally illuminated fascia sign, 1no externally illuminated projecting sign, 2no. non-illuminated fascia signs to replace 1no existing projecting sign, 2no existing fascia signs at the front elevation and painting of existing painted elements of shopfront on front elevation at ground floor level in Little Basalt Green. Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
24 Sept 2025
✓
Validated
3 Oct 2025
✓
Approved
10 Feb 2026
✗
Appeal dismissed
13 May 2026

Approved on 10 Feb 2026 · Last checked 12 Oct 2026

Documents 29

All documents on the council site ↗

Site constraints 9

Grade II listed: Hop Poles Public House
List entry 1079826 · 2 m away · 8 more listed buildings within 150 m (1 Grade II*, 6 Grade II)
Listed building consent is needed for work that affects the special interest of a listed building, inside or out, on top of planning permission. Setting can be a consideration for buildings nearby; there is no fixed radius.
Show the other 8 with distances
Historic England ↗
Flood zone 3, rivers and sea
High chance: a 1 in 100 or greater annual chance from rivers, or 1 in 200 from the sea. Any development here needs a flood risk assessment. Defences are not counted.
The Environment Agency flood map for planning. Homes in zone 3 must also pass the sequential test. Surface water flooding is a separate map.
Flood map ↗
Hammersmith Broadway conservation area
Demolition needs planning permission and permitted development is restricted.
The council must give weight to preserving or enhancing the area's character and appearance. Not every council has published its boundaries as open data.
National infrastructure project: Thames Tideway Tunnel
The site is inside the project boundary. Waste water treatment, decided. The project page says whether consent was granted.
Nationally significant infrastructure projects (power stations, electricity lines, pipelines, major roads and railways, harbours, airports and reservoirs) are consented by a Secretary of State under the Planning Act 2008, after an examination by the Planning Inspectorate, rather than by the council. The boundary is the one the Inspectorate consults on and can change as the scheme does. Projects are shown within 2 km of the site.
Planning Inspectorate project page ↗
Archaeological priority area: Possible original Saxon settlement of Hammersmith around Creek mouth
An assessment or field evaluation may be asked for before ground works.
The council or Historic England considers archaeology likely here. A desk-based assessment, and sometimes trial trenching, can be asked for with the application.
Air quality management area: Hammersmith and Fulham AQMA
The council has declared the area as failing an air quality objective.
Schemes that add traffic, parking or combustion plant are assessed against the area's action plan and may need an air quality assessment.
Council record ↗
Town centre: Hammersmith Town Centre
A designated centre in the London Plan.
Shops, services and active frontages are protected in centres, and main town centre uses are steered here first.
Also on the record
Inside the Hammersmith and Fulham built-up area; Public transport access: PTAL 6b (excellent), TfL 2023, for the 100 m square.
Not affected
Not green belt · No scheduled monument at the site

Checked on 12 October 2026. Historic England, the Environment Agency, Natural England, the Planning Inspectorate, Transport for London (public transport access levels, Powered by TfL Open Data, OGL v3.0, contains OS data © Crown copyright and database right 2025) and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Building

Floor area820 m² (8,826 sq ft)
Energy ratingC (asset rating 63)
UseRestaurants and Cafes/Drinking Establishments/Takeaways
HeatingHeating and Natural Ventilation

From the energy performance certificate lodged in September 2026, the latest held for this property. The building may have changed since. View the certificate

Work with planning data?

Every application in Hammersmith and Fulham - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Application type
Listed Building Consent
Postcode
W6 9HR
Received
24 Sept 2025
Validated
3 Oct 2025
Ward
Hammersmith Broadway
Case officer
Show
Decision
APPLICATION APPROVED
Decision date
10 Feb 2026
Appeal
Dismissed · 13 May 2026 · Written Representations · Inspectorate case 6005038 ↗
Applicant
Show
Leaseholder
Show

How this decision compares

Decided in 130 days from validation, 25 days slower than Hammersmith and Fulham's median of 105 for listed building works. Approved, as 100% of listed building works here are.

21%decided within 8 weeks
100%approved
35decided in the last year

Plota live figures for listed building works decided by Hammersmith and Fulham in the last twelve months, from validation. Hammersmith and Fulham decision record →

Consultation & key dates

Consultation
7 Oct 2025
Comments by
28 Nov 2025
Site or press notice
28 Jan 2026
Statutory expiry
10 Feb 2029
Hammersmith and Fulham
Planning Authority Score
3.7/10
Below average
#210 of 296 councils
Relevant to this application:
Other decisions

Hammersmith and Fulham is one of the slowest councils in England for householder decisions, ranking #281 out of 296. The council extends the time limit on 63% of applications - one of the highest rates in England. Expect your application to take longer than the standard deadline. Householder applications are more likely to be approved here than most councils, with a 99% approval rate vs 90% nationally.

Among the slowest councils in England
for householder decisions
These figures are council-wide context, not a prediction for this application. View full council performance
Hammersmith and Fulham decision statistics
Based on MHCLG data, the year to March 2026
95%
Overall approval rate
Above avg (87%) #20 of 296
99%
Householder approved
Above avg (90%) #4 of 296
33%
Decided in 8 weeks
Below avg (63%) #281 of 296
63%
Extended time limit
Above avg (41%) #275 of 296
97%
Minor dwellings approved
209 decided (1-9 homes)
100%
Major dwellings approved
1 decided (10+ homes)
92%
Change of use approved
37 decided
1,321
Total decisions
60 refused in the year to March 2026

Energy performance: Energy performance certificates from the Energy Performance of Buildings Register, Ministry of Housing, Communities and Local Government. Contains public sector information licensed under the Open Government Licence v3.0. © Crown copyright 2026.