Stone Lodge Main Street West Haddlesey North Yorkshire YO8 8QA Data via plota.co.uk

SELZG2026/0190/FUL - Full permission Registered

Proposal

Erection of a replacement dwelling Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
4 Mar 2026
✓
Validated
11 Mar 2026
✓
Consultation
8 Sept 2026
Decision
Expected by 6 May 2026

Under consideration

No decision has been issued yet. Plota predicted a decision soon after comments close on 2 Oct 2026; it is now day 212.

The consultation period closed on 2 Oct 2026.

Documents 22

All documents on the council site ↗

Site constraints 4

Flood zone 2, rivers and sea
Medium chance: between a 1 in 100 and 1 in 1,000 annual chance from rivers, or 1 in 200 to 1 in 1,000 from the sea. Any development here needs a flood risk assessment. Defences are not counted.
The Environment Agency flood map for planning. Homes in zone 3 must also pass the sequential test. Surface water flooding is a separate map.
Flood map ↗
National infrastructure project: Knottingley Power Project
The site is inside the project boundary. Generating station, decided. The project page says whether consent was granted. Also within 2 km: Eggborough CCGT (decided, 984 m); Ferrybridge Next Generation Power Station (at pre-application, 1320 m).
Nationally significant infrastructure projects (power stations, electricity lines, pipelines, major roads and railways, harbours, airports and reservoirs) are consented by a Secretary of State under the Planning Act 2008, after an examination by the Planning Inspectorate, rather than by the council. The boundary is the one the Inspectorate consults on and can change as the scheme does. Projects are shown within 2 km of the site.
Planning Inspectorate project page ↗
Agricultural land, grade 3a
Best and most versatile land (grades 1, 2 and 3a). Source: the Predictive Agricultural Land Classification Map (Defra and Natural England, 2025; the Welsh Government's Predictive ALC Map 2 in Wales), a model rather than a site survey. Natural England's Provisional ALC map (1:250,000, 1970s) agrees.
Where development of farmland is needed, policy prefers poorer land over the best and most versatile (grades 1, 2 and 3a). Three sources: Natural England's post-1988 field surveys, which are definitive where they exist; the Defra predictive map for England (2025) and the Welsh Government predictive map, modelled from the soil map with 3a and 3b split; and the 1970s provisional map, which planners and other services still show, coarser and with grade 3 undivided. Where the provisional and predicted grades disagree, treat the predicted grade as the current estimate and expect an application to carry its own survey.
Also on the record
Coalfield, development low risk area.
Not affected
Not green belt · No listed building at the site · No scheduled monument at the site

Checked on 6 October 2026. Historic England, the Environment Agency, Natural England, the Mining Remediation Authority, the Planning Inspectorate and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Sales history 1

Last sold for £507,500 in December 2025. Detached house, freehold.

23 December 2025£507,500

Sale prices from HM Land Registry's price paid record, matched to this application by its address.

Building

Floor area119 m² (1,281 sq ft)
Energy ratingE (42 out of 100), could reach B
PropertyDetached bungalow, 5 habitable rooms
Built1967 to 1975
HeatingWarm air, oil
WallsTimber frame, as built, partial insulation (assumed)

From the energy performance certificate lodged in May 2025, the latest held for this property. The building may have changed since. View the certificate

Work with planning data?

Every application in Selby - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Council
Selby
Application type
Full permission
Postcode
YO8 8QA
Received
4 Mar 2026
Validated
11 Mar 2026
Ward
Camblesforth & Carlton
Parish
West Haddlesey
Case officer
Show
Target decision
6 May 2026
Decision level
Delegated Decision
Applicant
Show
Agent
Rchitecture Ltd

Decision outlook

Day 212, past the statutory target. 86% of demolitions in Selby are decided within thirteen weeks; extensions of time are common, and the council need not decide on the day. Last seen undecided on 1 Oct 2026.

Day 212156 days past the 56-day target
56%decided within 8 weeks
81%approved
45decided in the last year

Plota live figures for demolitions decided by Selby in the last twelve months, from validation. Selby decision record →

Public comments

No public comments yet.

Last counted 1 Oct 2026

Read the comments on the council site ↗

Consultation & key dates

Alt. reference
PP-14750937
Planning Portal ref
PP-14750937
Consultation
8 Sept 2026
Comments by
2 Oct 2026
Site or press notice
23 Mar 2026
Statutory expiry
6 May 2026