Fetteresso Substation Fetteresso Stonehaven Aberdeenshire AB39 3UX Data via plota.co.uk

Proposal

Upgrade to Existing 132kV Fetteresso Substation Including Installation of a Combined Gas Insulated Switchgear (GIS) / Control Building One Super Grid Transformer, One Grid Transformer, Two Busbars, Two Traction Transformers, Associated Plant and Equipment, Temporary Construction Compound and Access Track, Means of Access, Site Drainage, Landscaping and Other Associated Operations Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
8 Jul 2026
✓
PAC Agreed as Specified in Notice
28 Jul 2026

PAC Agreed as Specified in Notice on 28 Jul 2026 · Last checked 2 Sept 2026

Work with planning data?

Every application in Aberdeenshire - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Postcode
AB39 3UX
Received
8 Jul 2026
Validated
8 Jul 2026
Target decision
28 Jul 2026
Decision
PAC Agreed as Specified in Notice
Decision date
28 Jul 2026

Public comments

No public comments yet.

Last counted 2 Sept 2026