Motorway Services North Service Area At Junction 5 M18 Junction 5 To Junction 6 Doncaster DN8 5GS Data via plota.co.uk

26/01150/FUL - Full Application Approved

Proposal

Installation of 3 No new EV Charging posts with canopies, and associated electrical hardware Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
15 Jun 2026
✓
Consultation
2 Jul 2026
✓
Approved
10 Aug 2026

Approved on 10 Aug 2026 · Delegated · Last checked 11 Aug 2026

Site constraints 7

Flood zone 3, rivers and sea
High chance: a 1 in 100 or greater annual chance from rivers, or 1 in 200 from the sea. Any development here needs a flood risk assessment. Defences are not counted.
The Environment Agency flood map for planning. Homes in zone 3 must also pass the sequential test. Surface water flooding is a separate map.
Flood map ↗
Agricultural land, grade 3b
Not best and most versatile land (grades 1, 2 and 3a). Source: the Predictive Agricultural Land Classification Map (Defra and Natural England, 2025; the Welsh Government's Predictive ALC Map 2 in Wales), a model rather than a site survey. Natural England's Provisional ALC map (1:250,000, 1970s) agrees.
Where development of farmland is needed, policy prefers poorer land over the best and most versatile (grades 1, 2 and 3a). Three sources: Natural England's post-1988 field surveys, which are definitive where they exist; the Defra predictive map for England (2025) and the Welsh Government predictive map, modelled from the soil map with 3a and 3b split; and the 1970s provisional map, which planners and other services still show, coarser and with grade 3 undivided. Where the provisional and predicted grades disagree, treat the predicted grade as the current estimate and expect an application to carry its own survey.
National infrastructure project 639 m away: Yorkshire and Humber CCS Cross Country Pipeline
The site is 639 m from the project boundary. Pipeline, decided. The project page says whether consent was granted.
Nationally significant infrastructure projects (power stations, electricity lines, pipelines, major roads and railways, harbours, airports and reservoirs) are consented by a Secretary of State under the Planning Act 2008, after an examination by the Planning Inspectorate, rather than by the council. The boundary is the one the Inspectorate consults on and can change as the scheme does. Projects are shown within 2 km of the site.
Planning Inspectorate project page ↗
Habitat network: Network Enhancement Zone 1
Where habitat is joined up enough to work as a network. Context, not a constraint on its own.
Also on the record
Public footpath 30 m away; Coalfield, development low risk area; Priority habitat 19 m away: Coastal and floodplain grazing marsh.
Not affected
Not green belt · No listed building at the site · No scheduled monument at the site

Checked on 6 October 2026. Historic England, the Environment Agency, Natural England, the Mining Remediation Authority, the Planning Inspectorate and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Building

Floor area1,328 m² (14,294 sq ft)
Energy ratingC (asset rating 70)
UseRetail/Financial and Professional Services
HeatingHeating and Mechanical Ventilation

From the energy performance certificate lodged in January 2023, the latest held for this property. The building may have changed since. View the certificate

Work with planning data?

Every application in Doncaster - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Council
Doncaster
Application type
Full Application
Postcode
DN8 5GS
Received
15 Jun 2026
Validated
15 Jun 2026
Ward
Hatfield
Parish
Hatfield Parish Council
Target decision
10 Aug 2026
Decision
Planning Permission GRANTED
Decision date
10 Aug 2026
Decision level
Delegated
Applicant
Show
Agent
KMB Ltd

How this decision compares

Decided in 56 days from validation, 7 days slower than Doncaster's median of 49 for utility and infrastructure works. Approved, as 97% of utility and infrastructure works here are.

62%decided within 8 weeks
97%approved
54decided in the last year

Plota live figures for utility and infrastructure works decided by Doncaster in the last twelve months, from validation. Doncaster decision record →

Public comments

No public comments yet.

2 neighbours consulted · Last counted 11 Aug 2026

Read the comments on the council site ↗

Consultation & key dates

Alt. reference
PP-14894226
Planning Portal ref
PP-14894226
Neighbours
23 Jun 2026
Consultation
2 Jul 2026
Comments by
23 Jul 2026
Site or press notice
23 Jun 2026
Statutory expiry
10 Aug 2026
Env. assessment
No
Doncaster
Planning Authority Score
7.7/10
Good
#36 of 296 councils
Relevant to this application:
Householder decisions

Doncaster is one of the fastest councils in England for householder decisions, ranking #27 out of 296. Householder applications are slightly more likely to be approved here (94%) than the national average (90%).

Among the fastest councils in England
for householder decisions
These figures are council-wide context, not a prediction for this application. View full council performance
Doncaster decision statistics
Based on MHCLG data, the year to March 2026
87%
Overall approval rate
Above avg (87%) #169 of 296
94%
Householder approved
Above avg (90%) #103 of 296
83%
Decided in 8 weeks
Above avg (63%) #27 of 296
33%
Extended time limit
Below avg (41%) #75 of 296
67%
Minor dwellings approved
135 decided (1-9 homes)
93%
Major dwellings approved
27 decided (10+ homes)
90%
Change of use approved
48 decided
928
Total decisions
122 refused in the year to March 2026

Energy performance: Energy performance certificates from the Energy Performance of Buildings Register, Ministry of Housing, Communities and Local Government. Contains public sector information licensed under the Open Government Licence v3.0. © Crown copyright 2026.