The Paddock Chobham Road Ottershaw Surrey KT16 0QD Data via plota.co.uk

RU.26/0271 Decided

Proposal

Ground-mounted solar photovoltaic (PV) panels. Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
23 Apr 2026
✓
Decided
12 Jun 2026

Decided on 12 Jun 2026 · Last checked 18 Aug 2026

Site constraints 5

Green belt: London
Inappropriate development needs very special circumstances.
Green belt policy allows a short list of exceptions, such as limited extensions and replacement buildings. Anything else needs very special circumstances that clearly outweigh the harm. Some green belt land can count as grey belt, where it does not strongly serve the green belt's purposes. The council decides this in its green belt assessment or on each application, so we do not mark it here.
Read the government guidance ↗
Agricultural land, grade 3b
Not best and most versatile land (grades 1, 2 and 3a). Source: the Predictive Agricultural Land Classification Map (Defra and Natural England, 2025; the Welsh Government's Predictive ALC Map 2 in Wales), a model rather than a site survey. Natural England's Provisional ALC map (1:250,000, 1970s), which most planning maps still show, had this area as grade 4. The predicted grade is Defra's current estimate; only a site survey settles it.
Where development of farmland is needed, policy prefers poorer land over the best and most versatile (grades 1, 2 and 3a). Three sources: Natural England's post-1988 field surveys, which are definitive where they exist; the Defra predictive map for England (2025) and the Welsh Government predictive map, modelled from the soil map with 3a and 3b split; and the 1970s provisional map, which planners and other services still show, coarser and with grade 3 undivided. Where the provisional and predicted grades disagree, treat the predicted grade as the current estimate and expect an application to carry its own survey.
National infrastructure project about 583 m away: Southampton to London Pipeline Project
The site is about 583 m from the project boundary. Pipeline, decided. The project page says whether consent was granted.
Nationally significant infrastructure projects (power stations, electricity lines, pipelines, major roads and railways, harbours, airports and reservoirs) are consented by a Secretary of State under the Planning Act 2008, after an examination by the Planning Inspectorate, rather than by the council. The boundary is the one the Inspectorate consults on and can change as the scheme does. Projects are shown within 2 km of the site.
Planning Inspectorate project page ↗
Habitat network: Network Enhancement Zone 2
Where habitat is joined up enough to work as a network. Context, not a constraint on its own.
Also on the record
Priority habitat about 44 m away: Deciduous woodland.
Not affected
Outside flood zones 2 and 3 · No scheduled monument at the site

Checked on 6 October 2026. The pin for this application is the centre of its postcode rather than the building, so distances to nearby designations are measured from the postcode and can be out by the width of the postcode area. Historic England, the Environment Agency, Natural England, the Planning Inspectorate and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Sales history 1

Last sold for £1,680,000 in June 2018. Other property, freehold.

29 June 2018£1,680,000Recorded as a transfer outside a standard sale

Sale prices from HM Land Registry's price paid record, matched to this application by its address.

Work with planning data?

Every application in Runnymede - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Council
Runnymede
Postcode
KT16 0QD
Received
23 Apr 2026
Validated
23 Apr 2026
Case officer
Show
Decision date
12 Jun 2026
Runnymede
Planning Authority Score
5.2/10
Average
#140 of 296 councils
Relevant to this application:
Householder decisions

Runnymede ranks #108 out of 296 councils for householder decision speed. Householder applications are slightly less likely to be approved here (89%) than the national average (90%).

These figures are council-wide context, not a prediction for this application. View full council performance
Runnymede decision statistics
Based on MHCLG data, the year to March 2026
83%
Overall approval rate
Below avg (87%) #242 of 296
89%
Householder approved
Below avg (90%) #208 of 296
72%
Decided in 8 weeks
Above avg (63%) #108 of 296
36%
Extended time limit
Below avg (41%) #113 of 296
66%
Minor dwellings approved
74 decided (1-9 homes)
82%
Major dwellings approved
11 decided (10+ homes)
55%
Change of use approved
11 decided
661
Total decisions
110 refused in the year to March 2026