York Sports Village Lakeside Way Heslington York YO10 5FG Data via plota.co.uk

25/02434/FULM - Major Full Application Approved

Proposal

Construction of a geothermal facility to include the drilling of 3no. deep geothermal wells and new cycle track to existing disused velodrome area Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
8 Dec 2025
✓
Validated
11 Dec 2025
✓
Approved
10 Apr 2026

Approved on 10 Apr 2026 · Delegated Decision · Last checked 3 Oct 2026

Documents 61

Statements & assessments 43

PDF GEOARCHAEOLOGICAL ASSESSMENT: WRITTEN SCHEME OF INVESTIGATION (WSI) Report · 10 Mar 2026 View ↗ PDF TRANSPORT TECHNICAL NOTE Report · 5 Mar 2026 View ↗ PDF DRAINAGE PLAN Drainage Documentation · 17 Dec 2025 View ↗ PDF BNG METRIC Report · 10 Dec 2025 View ↗ PDF DEEP GEOTHERMAL ENERGY CONSTRUCTION LAYOUT Drawing · 8 Dec 2025 View ↗ PDF DESIGN & ACCESS STATEMENT Design & Access Statement · 8 Dec 2025 View ↗ PDF ENVIRONMENTAL STATEMENT VOLUME 1 Environmental Statement · 8 Dec 2025 View ↗ PDF NON-TECHNICAL SUMMARY Environmental Statement · 8 Dec 2025 View ↗ PDF ENERGY & SUSTAINABILITY STATEMENT Sustainability Appraisal · 8 Dec 2025 View ↗ PDF TRANSPORT STATEMENT Transport Assessment · 8 Dec 2025 View ↗ PDF ES VOLUME 2 CHAPTER 7 ZONE OF THEORETICAL VISIBILITY Environmental Statement · 8 Dec 2025 View ↗ PDF ES VOLUME 2 CHAPTER 7 VIEWPOINT 1 BASELINE PANORAMA Environmental Statement · 8 Dec 2025 View ↗ PDF PHASE 1 CONTAMINATION SURVEY & GEO-ENVIRONMENTAL ASSESSMENT Land Contamination Assessment · 8 Dec 2025 View ↗ PDF PLANNING STATEMENT Planning Statement · 8 Dec 2025 View ↗ PDF ES VOLUME 2 CHAPTER 7 VIEWPOINT 2 BASELINE PANORAMA Environmental Statement · 8 Dec 2025 View ↗ PDF ES VOLUME 2 CHAPTER 7 VIEWPOINT 3 BASELINE PANORAMA Environmental Statement · 8 Dec 2025 View ↗ PDF LIGHTING PLAN Lighting Assessment · 8 Dec 2025 View ↗ PDF ES VOLUME 2 CHAPTER 7 VIEWPOINT 4 BASELINE PANORAMA Environmental Statement · 8 Dec 2025 View ↗ PDF ES VOLUME 2 CHAPTER 7 VIEWPOINT 5 BASELINE PANORAMA Environmental Statement · 8 Dec 2025 View ↗ PDF ES VOLUME 2 CHAPTER 7 VIEWPOINT 6 BASELINE PANORAMA Environmental Statement · 8 Dec 2025 View ↗ PDF ES VOLUME 2 CHAPTER 7 VIEWPOINT 7 BASELINE PANORAMA Environmental Statement · 8 Dec 2025 View ↗ PDF ES VOLUME 2 CHAPTER 9 DESIGNATED HERITAGE ASSETS Environmental Statement · 8 Dec 2025 View ↗
PDF Commenter’s name hidden Show Statement of Community Involvement · 8 Dec 2025 View ↗
PDF ES VOLUME 2 CHAPTER 9 NON DESIGNATED HERITAGE ASSETS Environmental Statement · 8 Dec 2025 View ↗ PDF ES VOLUME 2 CHAPTER 9 ARCHAEOLOGICAL EVENTS Environmental Statement · 8 Dec 2025 View ↗ PDF ES VOLUME 2 CHAPTER 7 TOPOGRAPHY Environmental Statement · 8 Dec 2025 View ↗ PDF ES VOLUME 2 CHAPTER 7 DESIGNATED AREAS Environmental Statement · 8 Dec 2025 View ↗ PDF ES VOLUME 2 CHAPTER 7 SENSITIVE RECEPTORS Environmental Statement · 8 Dec 2025 View ↗ PDF ES VOLUME 2 CHAPTER 7 ACCESS NETWORK Environmental Statement · 8 Dec 2025 View ↗ PDF ES VOLUME 2 CHAPTER 7 LANDSCAPE CHARACTER Environmental Statement · 8 Dec 2025 View ↗ PDF LANDSCAPE AND VISUAL IMPACT ASSESSMENT METHODOLOGY -ES VOL 3 TECHNICAL APPENDIX Environmental Statement · 8 Dec 2025 View ↗ PDF PLANT LIST AND DETAILS - ES VOL 3 TECHNICAL APPENDIX 8.1 Environmental Statement · 8 Dec 2025 View ↗ PDF SITE ENABLING NOISE LEVELS -ES VOL 3 TECHNICAL APPENDIX 8.2 Environmental Statement · 8 Dec 2025 View ↗ PDF HISTORIC ENVIRONMENT DESK BASED ASSESSMENT - ES VOL 3 TECHNICAL APPENDIX 9.1 Environmental Statement · 8 Dec 2025 View ↗ PDF PRELIMINARY BIODIVERSITY NET GAIN REPORT ES VOL 3 TECHNICAL APPENDIX 10.2 Environmental Statement · 8 Dec 2025 View ↗ PDF PRELIMINARY ECOLOGICAL APPRAISAL - ES VOL 3 TECHNICAL APPENDIX 10.1 Environmental Statement · 8 Dec 2025 View ↗ PDF CLIMATE-RELATED LEGISLATION, POLICY AND GUIDANCE -ES VOL 3 TECHNICAL APPENDIX 11 Environmental Statement · 8 Dec 2025 View ↗ PDF BGS BOREHOLES - ES VOL 3 TECHNICAL APPENDIX 12.3 Environmental Statement · 8 Dec 2025 View ↗ PDF FLOOD RISK ASSESSMENT - ES VOL 3 TECHNICAL APPENDIX 12.1 Environmental Statement · 8 Dec 2025 View ↗ PDF WATER RESOURCES LEGISLATION, POLICY AND GUIDANCE -ES VOL 3 TECHNICAL APPENDIX 12 Environmental Statement · 8 Dec 2025 View ↗ PDF TESTING AND DRILLING NOISE LEVELS - ES VOL 3 TECHNICAL APPENDIX 8.3 Environmental Statement · 8 Dec 2025 View ↗ PDF ES VOL 3 TECHNICAL APPENDICES FRONT PAGE Environmental Statement · 8 Dec 2025 View ↗ PDF STATEMENT OF EXPERTISE - ES VOL 3 TECHNICAL APPENDIX 1 Environmental Statement · 8 Dec 2025 View ↗

All documents on the council site ↗

Associated applications 4

Site constraints 2

Agricultural land, grade 3a, surveyed
Best and most versatile land (grades 1, 2 and 3a). Source: Natural England's post-1988 ALC field survey (Leeds). Natural England's Provisional ALC map (1:250,000, 1970s) had this area as grade 2; the survey is the definitive reading.
Where development of farmland is needed, policy prefers poorer land over the best and most versatile (grades 1, 2 and 3a). Three sources: Natural England's post-1988 field surveys, which are definitive where they exist; the Defra predictive map for England (2025) and the Welsh Government predictive map, modelled from the soil map with 3a and 3b split; and the 1970s provisional map, which planners and other services still show, coarser and with grade 3 undivided. Where the provisional and predicted grades disagree, treat the predicted grade as the current estimate and expect an application to carry its own survey.
Survey report ↗
National infrastructure project 533 m away: Yorkshire GREEN
The site is 533 m from the project boundary. Electricity line, decided. The project page says whether consent was granted.
Nationally significant infrastructure projects (power stations, electricity lines, pipelines, major roads and railways, harbours, airports and reservoirs) are consented by a Secretary of State under the Planning Act 2008, after an examination by the Planning Inspectorate, rather than by the council. The boundary is the one the Inspectorate consults on and can change as the scheme does. Projects are shown within 2 km of the site.
Planning Inspectorate project page ↗
Not affected
Outside flood zones 2 and 3 · Not green belt · No listed building at the site

Checked on 6 October 2026. Historic England, the Environment Agency, Natural England, the Planning Inspectorate and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Work with planning data?

Every application in York - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Council
York
Application type
Major Full Application
Postcode
YO10 5FG
Received
8 Dec 2025
Validated
11 Dec 2025
Ward
Hull Road
Parish
Heslington Parish Council
Case officer
Show
Target decision
10 Apr 2026
Decision
Approve
Decision date
10 Apr 2026
Decision level
Delegated Decision
Applicant
Show
Agent
SLR Consulting

How this decision compares

Decided in 120 days from validation, 64 days slower than York's median of 56 for full applications. Approved, as 85% of full applications here are.

57%decided within 8 weeks
85%approved
866decided in the last year

Plota live figures for full applications decided by York in the last twelve months, from validation. York decision record →

Public comments

4comments received
3 neutral1 supporting

25% support · above the UK average of 16%

4 neighbours consulted · Last counted 3 Oct 2026

Read the comments on the council site ↗

Consultation & key dates

Alt. reference
PP-14520470
Planning Portal ref
PP-14520470
Comments by
21 Feb 2026
Statutory expiry
2 Apr 2026
Env. assessment
Yes
York
Planning Authority Score
3.7/10
Below average
#213 of 296 councils
Relevant to this application:
Major dwellings

York ranks #156 out of 296 councils for householder decision speed. Householder applications are slightly less likely to be approved here (87%) than the national average (90%).

These figures are council-wide context, not a prediction for this application. View full council performance
York decision statistics
Based on MHCLG data, the year to March 2026
82%
Overall approval rate
Below avg (87%) #255 of 296
87%
Householder approved
Below avg (90%) #237 of 296
64%
Decided in 8 weeks
Above avg (63%) #156 of 296
42%
Extended time limit
Above avg (41%) #168 of 296
69%
Minor dwellings approved
104 decided (1-9 homes)
71%
Major dwellings approved
17 decided (10+ homes)
63%
Change of use approved
68 decided
1,278
Total decisions
224 refused in the year to March 2026