Application progress

✓
Received
11 Aug 2025
✓
Validated
19 Aug 2025
✓
Approved
27 May 2026

Approved on 27 May 2026 · Last checked 13 Oct 2026

Associated applications 3

Site constraints 9

1 listed building within 150 m of the postcode pin
Nearest: Luton Hoo Garden Centre, Grade II, the postcode pin is inside its outline
The site itself is not listed. Listed building consent is needed for work that affects the special interest of a listed building, inside or out, on top of planning permission. Setting can be a consideration for buildings nearby; there is no fixed radius.
Historic England ↗
Green belt: London
Inappropriate development needs very special circumstances.
Green belt policy allows a short list of exceptions, such as limited extensions and replacement buildings. Anything else needs very special circumstances that clearly outweigh the harm. Some green belt land can count as grey belt, where it does not strongly serve the green belt's purposes. The council decides this in its green belt assessment or on each application, so we do not mark it here.
Read the government guidance ↗
Registered park or garden: Luton Hoo
Nationally designated heritage. Its significance and setting carry great weight.
Registered parks and gardens, battlefields, world heritage sites and protected wrecks are designated heritage assets: harm needs clear and convincing justification.
Historic England ↗
Luton Hoo Conservation Area conservation area
Demolition needs planning permission and permitted development is restricted.
The council must give weight to preserving or enhancing the area's character and appearance. Not every council has published its boundaries as open data.
Agricultural land, grade 3a
Best and most versatile land (grades 1, 2 and 3a). Source: the Predictive Agricultural Land Classification Map (Defra and Natural England, 2025; the Welsh Government's Predictive ALC Map 2 in Wales), a model rather than a site survey. Natural England's Provisional ALC map (1:250,000, 1970s) agrees.
Where development of farmland is needed, policy prefers poorer land over the best and most versatile (grades 1, 2 and 3a). Three sources: Natural England's post-1988 field surveys, which are definitive where they exist; the Defra predictive map for England (2025) and the Welsh Government predictive map, modelled from the soil map with 3a and 3b split; and the 1970s provisional map, which planners and other services still show, coarser and with grade 3 undivided. Where the provisional and predicted grades disagree, treat the predicted grade as the current estimate and expect an application to carry its own survey.
Habitat network: Other Priority Habitats - NEZ
Where habitat is joined up enough to work as a network. Context, not a constraint on its own.
National infrastructure project about 975 m away: M1 Junction 10a Grade Separation - Luton
The site is about 975 m from the project boundary. Highway, decided. The project page says whether consent was granted. Also within 2 km: London Luton Airport Expansion (decided, about 1183 m).
Nationally significant infrastructure projects (power stations, electricity lines, pipelines, major roads and railways, harbours, airports and reservoirs) are consented by a Secretary of State under the Planning Act 2008, after an examination by the Planning Inspectorate, rather than by the council. The boundary is the one the Inspectorate consults on and can change as the scheme does. Projects are shown within 2 km of the site.
Planning Inspectorate project page ↗
Also on the record
Radon affected area, class 2; Priority habitat about 13 m away: Deciduous woodland.
Not affected
Outside flood zones 2 and 3 · No scheduled monument at the site

Checked on 13 October 2026. The pin for this application is the centre of its postcode rather than the building, so distances to nearby designations are measured from the postcode and can be out by the width of the postcode area. Historic England, the Environment Agency, Natural England, the Planning Inspectorate, the British Geological Survey and UK Health Security Agency (radon, contains BGS materials © UKRI) and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Work with planning data?

Every application in Central Bedfordshire - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Application type
Full Application
Postcode
LU1 3TQ
Received
11 Aug 2025
Validated
19 Aug 2025
Parish
Hyde
Case officer
Show
Target decision
18 Nov 2025
Decision
Full Application - Granted Conditions or Reasons: View Conditions or Reasons Informative Notes: 1 )GDP Policy Informative Central Beds Local Plan In accordance with Article 35 (1) of the Town and Country Planning (Development Management Procedure) (England) Order 2015, the reason for any condition above relates to the Policies as referred to in the Central Bedfordshire Local Plan and the National Planning Policy Framework (NPPF).GDP Policy Informative Central Beds Local Plan In accordance with Article 35 (1) of the Town and Country Planning (Development Management Procedure) (England) Order 2015, the reason for any condition above relates to the Policies as referred to in the Central Bedfordshire Local Plan and the National Planning Policy Framework (NPPF). 2 )This permission relates only to that required under the Town & Country Planning Acts and does not include any consent or approval under any other enactment or under the Building Regulations. Any other consent or approval which is necessary must be obtained from the appropriate authority.This permission relates only to that required under the Town & Country Planning Acts and does not include any consent or approval under any other enactment or under the Building Regulations. Any other consent or approval which is necessary must be obtained from the appropriate authority. 3 )The applicants attention is drawn to their responsibility under The Equality Act 2010 and with particular regard to access arrangements for the disabled. The Equality Act 2010 requires that service providers must think ahead and make reasonable adjustments to address barriers that impede disabled people. These requirements are as follows: Where a provision, criterion or practice puts disabled people at a substantial disadvantage to take reasonable steps to avoid that disadvantage; Where a physical feature puts disabled people at a substantial disadvantage to avoid that disadvantage or adopt a reasonable alternative method of providing the service or exercising the function; Where not providing an auxiliary aid puts disabled people at a substantial disadvantage to provide that auxiliary aid. In doing this, it is a good idea to consider the range of disabilities that your actual or potential service users might have. You should not wait until a disabled person experiences difficulties using a service, as this may make it too late to make the necessary adjustment. For further information on disability access contact: The Centre for Accessible Environments (www.cae.org.uk) Central Bedfordshire Access Group (www.centralbedsaccessgroup.co.uk)The applicants attention is drawn to their responsibility under The Equality Act 2010 and with particular regard to access arrangements for the disabled. The Equality Act 2010 requires that service providers must think ahead and make reasonable adjustments to address barriers that impede disabled people. These requirements are as follows: Where a provision, criterion or practice puts disabled people at a substantial disadvantage to take reasonable steps to avoid that disadvantage; Where a physical feature puts disabled people at a substantial disadvantage to avoid that disadvantage or adopt a reasonable alternative method of providing the service or exercising the function; Where not providing an auxiliary aid puts disabled people at a substantial disadvantage to provide that auxiliary aid. In doing this, it is a good idea to consider the range of disabilities that your actual or potential service users might have. You should not wait until a disabled person experiences difficulties using a service, as this may make it too late to make the necessary adjustment. For further information on disability access contact: The Centre for Accessible Environments (www.cae.org.uk) Central Bedfordshire Access Group (www.centralbedsaccessgroup.co.uk) 4 )The applicant is reminded that, under the Conservation of Habitats and Species Regulations 2017 (as amended) and the Wildlife and Countryside Act 1981 (as amended), it is an offence to (amongst other things): deliberately capture, disturb, injure or kill great crested newts; damage or destroy a breeding or resting place; deliberately obstruct access to a resting or sheltering place. Planning approval for a development does not provide a defence against prosecution under these acts. Should great crested newts be found at any stages of the development works, then all works should cease, and Natural England should be contacted for advice.The applicant is reminded that, under the Conservation of Habitats and Species Regulations 2017 (as amended) and the Wildlife and Countryside Act 1981 (as amended), it is an offence to (amongst other things): deliberately capture, disturb, injure or kill great crested newts; damage or destroy a breeding or resting place; deliberately obstruct access to a resting or sheltering place. Planning approval for a development does not provide a defence against prosecution under these acts. Should great crested newts be found at any stages of the development works, then all works should cease, and Natural England should be contacted for advice. 5 )The final design and maintenance arrangements for surface water system agreed at the detailed design stage shall accord with the following: 1 Surface water drainage must follow the SuDS National Standards; National standards for sustainable drainage systems (SuDS) - GOV.UK 2. We will require a full set of calculations for each phase and in total, providing evidence of all surface water retained on site for the 1 in 100 (+40%CC+10% Urban Creep). Any exceedance should be shown with pathways, depths and velocity. 3. We will require full drainage drawings showing all connections, control features, storage, inverts etc. and how it communicates with the development wide scheme. 4. We will require BRE365 infiltration test results 5. Under Central Bedfordshire Council and IDB bylaws, any watercourse within or adjoining the site boundary will maintain a 9m development free easement (on the development side), unless otherwise agreed with the relevant drainage authority. This applies to all watercourses, where water is present for all or some of the year, including those not clearly stated on mapping, topography or planning documents. 6. Permeable block paving should be laid to CIRIA C768 'Guidance on the construction of SuDS' guidelines. This guidance also stipulates following Interlay guidance. 7. The Council does not, and is not required to, adopt any SuDS feature. It is the responsibility of the applicant to ensure that the surface water drainage system, in its entirety, will be effectively maintained in the long-term. We therefore expect confirmation of the proposed arrangements for maintenance to be provided with the final detailed design, including the future maintenance and operational needs and the responsible bodies for undertaking maintenance (for all public and private drainage components). 8. The final detailed design including proposed standards of operation, construction, structural integrity and ongoing maintenance must be compliant with the 'Non-statutory technical standards for sustainable drainage systems' (March 2015, Ref: PB14308), 'Central Bedfordshire Sustainable Drainage Guidance' (Adopted April 2014, Updated May 2015), and recognised best practise including the Ciria SuDS Manual (2016, C753).The final design and maintenance arrangements for surface water system agreed at the detailed design stage shall accord with the following: 1 Surface water drainage must follow the SuDS National Standards; National standards for sustainable drainage systems (SuDS) - GOV.UK 2. We will require a full set of calculations for each phase and in total, providing evidence of all surface water retained on site for the 1 in 100 (+40%CC+10% Urban Creep). Any exceedance should be shown with pathways, depths and velocity. 3. We will require full drainage drawings showing all connections, control features, storage, inverts etc. and how it communicates with the development wide scheme. 4. We will require BRE365 infiltration test results 5. Under Central Bedfordshire Council and IDB bylaws, any watercourse within or adjoining the site boundary will maintain a 9m development free easement (on the development side), unless otherwise agreed with the relevant drainage authority. This applies to all watercourses, where water is present for all or some of the year, including those not clearly stated on mapping, topography or planning documents. 6. Permeable block paving should be laid to CIRIA C768 'Guidance on the construction of SuDS' guidelines. This guidance also stipulates following Interlay guidance. 7. The Council does not, and is not required to, adopt any SuDS feature. It is the responsibility of the applicant to ensure that the surface water drainage system, in its entirety, will be effectively maintained in the long-term. We therefore expect confirmation of the proposed arrangements for maintenance to be provided with the final detailed design, including the future maintenance and operational needs and the responsible bodies for undertaking maintenance (for all public and private drainage components). 8. The final detailed design including proposed standards of operation, construction, structural integrity and ongoing maintenance must be compliant with the 'Non-statutory technical standards for sustainable drainage systems' (March 2015, Ref: PB14308), 'Central Bedfordshire Sustainable Drainage Guidance' (Adopted April 2014, Updated May 2015), and recognised best practise including the Ciria SuDS Manual (2016, C753). 6 )Highway Notes The applicant is advised that the requirements of the New Roads and Street Works Act 1991 will apply to any works undertaken within the limits of the existing public highway. Further details can be obtained by contacting the Streetworks Manager, Central Bedfordshire Council, by contacting the Highways Helpdesk 0300 300 8301. The applicant is advised that the storage of materials associated with the construction of this development should take place within the site and not extend into or within the public highway without authorisation from the highway authority. If necessary the applicant should contact the Streetworks Manager, Central Bedfordshire Council, by contacting the Highways Helpdesk 0300 300 8301. The applicant is advised that no private surface water drainage system designed as part of a new development, will be allowed to enter any existing highway surface water drainage system. The applicant is advised that in order to comply with the conditions related to highways works associated with this permission it will be necessary for the developer of the site to enter into an agreement with Central Bedfordshire Council as Highway Authority under the Highways Act 1980 to ensure the satisfactory completion of the access and associated road improvements. You are advised to contact the Highways Agreements Officer, Community Services, Central Bedfordshire Council, Priory House, Monks Walk, Chicksands, Shefford SG17 5TQ. E-mail highwaysagreements@centralbedfordshire.gov.uk.Highway Notes The applicant is advised that the requirements of the New Roads and Street Works Act 1991 will apply to any works undertaken within the limits of the existing public highway. Further details can be obtained by contacting the Streetworks Manager, Central Bedfordshire Council, by contacting the Highways Helpdesk 0300 300 8301. The applicant is advised that the storage of materials associated with the construction of this development should take place within the site and not extend into or within the public highway without authorisation from the highway authority. If necessary the applicant should contact the Streetworks Manager, Central Bedfordshire Council, by contacting the Highways Helpdesk 0300 300 8301. The applicant is advised that no private surface water drainage system designed as part of a new development, will be allowed to enter any existing highway surface water drainage system. The applicant is advised that in order to comply with the conditions related to highways works associated with this permission it will be necessary for the developer of the site to enter into an agreement with Central Bedfordshire Council as Highway Authority under the Highways Act 1980 to ensure the satisfactory completion of the access and associated road improvements. You are advised to contact the Highways Agreements Officer, Community Services, Central Bedfordshire Council, Priory House, Monks Walk, Chicksands, Shefford SG17 5TQ. E-mail highwaysagreements@centralbedfordshire.gov.uk.
Decision date
27 May 2026

How this decision compares

Decided in 281 days from validation, 226 days slower than Central Bedfordshire's median of 55 for full applications. Approved, as 85% of full applications here are.

63%decided within 8 weeks
85%approved
100%go to committee

Plota live figures for full applications decided by Central Bedfordshire in the last twelve months, from validation. Central Bedfordshire decision record →

Public comments

No public comments yet.

Last counted 13 Oct 2026

Read the comments on the council site ↗

Consultation & key dates

Consultation
19 Aug 2025
Comments by
4 Dec 2025
Site or press notice
29 Oct 2025
Committee
17 Dec 2025
Central Bedfordshire
Planning Authority Score
6.3/10
Average
#88 of 296 councils
Relevant to this application:
Householder decisions

Central Bedfordshire is faster than most councils at deciding householder applications, ranking #62 out of 296. Householder applications are slightly more likely to be approved here (91%) than the national average (90%).

Faster than most councils
for householder decisions
These figures are council-wide context, not a prediction for this application. View full council performance
Central Bedfordshire decision statistics
Based on MHCLG data, the year to March 2026
84%
Overall approval rate
Below avg (87%) #218 of 296
91%
Householder approved
Above avg (90%) #169 of 296
76%
Decided in 8 weeks
Above avg (63%) #62 of 296
35%
Extended time limit
Below avg (41%) #99 of 296
61%
Minor dwellings approved
153 decided (1-9 homes)
86%
Major dwellings approved
29 decided (10+ homes)
73%
Change of use approved
45 decided
1,444
Total decisions
226 refused in the year to March 2026