55C Darwin Street London Southwark SE17 1HA Data via plota.co.uk

26/AP/2279 - Minor application Refused

Proposal

Alterations to the second floor rear elevation including the replacement of a pitched roof with a flat roof to facilitate the construction of a rear dormer extension and roof terrace. Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
31 Jul 2026
✓
Validated
17 Aug 2026
✗
Refused
16 Oct 2026
Appeal
Not lodged

Refused on 16 Oct 2026 · Delegated Panel - Complex · Last checked 17 Oct 2026

Documents 18

All documents on the council site ↗

Site constraints 10

Flood zone 3, rivers and sea
High chance: a 1 in 100 or greater annual chance from rivers, or 1 in 200 from the sea. Any development here needs a flood risk assessment. Defences are not counted.
The Environment Agency flood map for planning. Homes in zone 3 must also pass the sequential test. Surface water flooding is a separate map.
Flood map ↗
Yates Estate and Victory conservation area
Demolition needs planning permission and permitted development is restricted.
The council must give weight to preserving or enhancing the area's character and appearance. Not every council has published its boundaries as open data.
Council document ↗
Air quality management area: Southwark AQMA
The council has declared the area as failing an air quality objective.
Schemes that add traffic, parking or combustion plant are assessed against the area's action plan and may need an air quality assessment.
Council record ↗
National infrastructure project 681 m away: Thames Tideway Tunnel
The site is 681 m from the project boundary. Waste water treatment, decided. The project page says whether consent was granted. Also within 2 km: London Strategic Heat Main Project (at pre-application, 143 m).
Nationally significant infrastructure projects (power stations, electricity lines, pipelines, major roads and railways, harbours, airports and reservoirs) are consented by a Secretary of State under the Planning Act 2008, after an examination by the Planning Inspectorate, rather than by the council. The boundary is the one the Inspectorate consults on and can change as the scheme does. Projects are shown within 2 km of the site.
Planning Inspectorate project page ↗
Opportunity area
Where the London Plan expects significant growth.
Boundaries are indicative and the borough holds the detailed plan.
Also on the record
Wider setting of protected view 23A.1 Centre of Bridge over the Serpentine to the Palace of Westminster; Radon affected area, class 2; Inside the Southwark built-up area; Public transport access: PTAL 5 (very good), TfL 2023, for the 100 m square; Designated open space 17 m away.
Not affected
Not green belt · No listed building at the site · No scheduled monument at the site

Checked on 6 October 2026. Historic England, the Environment Agency, Natural England, the Planning Inspectorate, the British Geological Survey and UK Health Security Agency (radon, contains BGS materials © UKRI), Transport for London (public transport access levels, Powered by TfL Open Data, OGL v3.0, contains OS data © Crown copyright and database right 2025) and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Sales history 2

Last sold for £181,500 in July 2005. Flat or maisonette, leasehold.

13 July 2005£181,500
11 August 2000£120,000

Sale prices from HM Land Registry's price paid record, matched to this application by its address.

Work with planning data?

Every application in Southwark - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Council
Southwark
Application type
Minor application
Postcode
SE17 1HA
Received
31 Jul 2026
Validated
17 Aug 2026
Ward
North Walworth
Parish
Borough, Bankside And Walworth
Case officer
Show
Target decision
11 Oct 2026
Decision
Minor - REFUSED
Decision date
16 Oct 2026
Decision level
Delegated Panel - Complex
Applicant
Show
Agent
kristofer adelaide architecture

How this decision compares

Decided in 60 days from validation, 9 days slower than Southwark's median of 51 for extensions. Refused, as 7% of extensions here are.

75%decided within 8 weeks
93%approved
657decided in the last year

Plota live figures for extensions decided by Southwark in the last twelve months, from validation. Southwark decision record →

Public comments

4comments received
4 objecting

100% object · above the UK average of 74%

13 neighbours consulted · Last counted 17 Oct 2026

Read the comments on the council site ↗

Consultation & key dates

Statutory expiry
11 Oct 2026
Env. assessment
No
Southwark
Planning Authority Score
7/10
Good
#64 of 296 councils
Relevant to this application:
Householder decisions

Southwark is faster than most councils at deciding householder applications, ranking #54 out of 296. Householder applications are slightly more likely to be approved here (95%) than the national average (90%).

Faster than most councils
for householder decisions
These figures are council-wide context, not a prediction for this application. View full council performance
Southwark decision statistics
Based on MHCLG data, the year to March 2026
92%
Overall approval rate
Above avg (87%) #93 of 296
95%
Householder approved
Above avg (90%) #92 of 296
78%
Decided in 8 weeks
Above avg (63%) #54 of 296
37%
Extended time limit
Below avg (41%) #122 of 296
92%
Minor dwellings approved
259 decided (1-9 homes)
86%
Major dwellings approved
14 decided (10+ homes)
82%
Change of use approved
38 decided
1,622
Total decisions
132 refused in the year to March 2026

Sale prices: Contains HM Land Registry data © Crown copyright and database right 2026. This data is licensed under the Open Government Licence v3.0.

Freehold boundary: © Crown copyright and database rights 2026, HM Land Registry. Polygons © Crown copyright and database rights 2026 Ordnance Survey 100026316. Conditions of use