Phase 3B Parcels 1 & 2 ,Houghton Regis North Site 1, Land on the northern edge of Houghton Regis Data via plota.co.uk
Proposal
Reserved Matters: following Outline application (Outline planning permission with the details of access, appearance, landscaping, layout and scale reserved for later determination. Development to comprise: up to 5,150 dwellings (Use Class C3); up to 202,500 sqm gross of additional development in Use Classes: A1, A2, A3 (retail), A4 (public house), A5 (take away); B1, B2, B8 (offices, industrial and storage and distribution); C1 (hotel), C2 (care home), D1 and D2 (community and leisure); car showroom; data centre; petrol filling station; car parking; primary substation; energy centre; and for the laying out of the buildings; routes and open spaces within the development; and all associated works and operations including but not limited to: demolition; earthworks; engineering operations. All development, works and operations to be in accordance with the Development Parameters Schedule and Plans) Approval of Access, Appearance, Landscaping, Layout and Scale for 161 dwellings and associated works Data via plota.co.uk
Application progress
Approved on 26 May 2026 · Last checked 14 Oct 2026
Every application in Central Bedfordshire - and every UK council - as a live feed, an API, or a bulk CSV export.
Important details
- Council
- Central Bedfordshire
- Application type
- Reserved Matters
- Received
- 1 Aug 2025
- Validated
- 6 Aug 2025
- Parish
- Chalton, Houghton Regis
- Case officer
- Show
- Target decision
- 5 Nov 2025
- Decision
- Reserved Matters- Granted Conditions or Reasons: View Conditions or Reasons Informative Notes: 1 )GDP Policy Informative Central Beds Local Plan In accordance with Article 35 (1) of the Town and Country Planning (Development Management Procedure) (England) Order 2015, the reason for any condition above relates to the Policies as referred to in the Central Bedfordshire Local Plan and the National Planning Policy Framework (NPPF).GDP Policy Informative Central Beds Local Plan In accordance with Article 35 (1) of the Town and Country Planning (Development Management Procedure) (England) Order 2015, the reason for any condition above relates to the Policies as referred to in the Central Bedfordshire Local Plan and the National Planning Policy Framework (NPPF). 2 )This permission relates only to that required under the Town & Country Planning Acts and does not include any consent or approval under any other enactment or under the Building Regulations. Any other consent or approval which is necessary must be obtained from the appropriate authority.This permission relates only to that required under the Town & Country Planning Acts and does not include any consent or approval under any other enactment or under the Building Regulations. Any other consent or approval which is necessary must be obtained from the appropriate authority. 3 )The applicant is advised that if it is the intention to request Central Bedfordshire Council as Local Highway Authority to adopt the proposed highways within the site as maintainable at the public expense then details of the specification, layout and alignment, width and levels of the said highways together with all the necessary highway and drainage arrangements, including run off calculations shall be submitted to the Highways Agreements Officer, Highways Contract Team, Community Services, Central Bedfordshire Council, Priory House, Monks Walk, Chicksands, Shefford SG17 5TQ. The applicant is advised that the requirements of the New Roads and Street Works Act 1991 will apply to any works undertaken within the limits of the existing public highway. Further details can be obtained by contacting The Street Works Co-ordinator, Central Bedfordshire Highways, by contacting the Highways Helpdesk 0300 300 8301. The applicant is advised that parking for contractor's vehicles and the storage of materials and deliveries associated with this development should take place within the site and not extend into within the public highway without authorisation from the highway authority. If necessary, the applicant is advised to contact The Street Works Co-ordinator, Central Bedfordshire Highways, by contacting the Highways Helpdesk 0300 300 8301. Under the provisions of the Highways Act 1980 the developer may be liable for any damage caused to the public highway as a result of demolition/construction of the development hereby approved. The applicant is advised that no private surface water drainage system designed as part of a new development will be allowed to enter any existing highway surface water drainage system.The applicant is advised that if it is the intention to request Central Bedfordshire Council as Local Highway Authority to adopt the proposed highways within the site as maintainable at the public expense then details of the specification, layout and alignment, width and levels of the said highways together with all the necessary highway and drainage arrangements, including run off calculations shall be submitted to the Highways Agreements Officer, Highways Contract Team, Community Services, Central Bedfordshire Council, Priory House, Monks Walk, Chicksands, Shefford SG17 5TQ. The applicant is advised that the requirements of the New Roads and Street Works Act 1991 will apply to any works undertaken within the limits of the existing public highway. Further details can be obtained by contacting The Street Works Co-ordinator, Central Bedfordshire Highways, by contacting the Highways Helpdesk 0300 300 8301. The applicant is advised that parking for contractor's vehicles and the storage of materials and deliveries associated with this development should take place within the site and not extend into within the public highway without authorisation from the highway authority. If necessary, the applicant is advised to contact The Street Works Co-ordinator, Central Bedfordshire Highways, by contacting the Highways Helpdesk 0300 300 8301. Under the provisions of the Highways Act 1980 the developer may be liable for any damage caused to the public highway as a result of demolition/construction of the development hereby approved. The applicant is advised that no private surface water drainage system designed as part of a new development will be allowed to enter any existing highway surface water drainage system. 4 )Anglian Water has assets close to or crossing this site or there are assets subject to an adoption agreement. Therefore the site layout should take this into account and accommodate those assets within either prospectively adoptable highways or public open space. If this is not practicable then the sewers will need to be diverted at the developers cost under Section 185 of the Water Industry Act 1991. or, in the case of apparatus under an adoption agreement, liaise with the owners of the apparatus. It should be noted that the diversion works should normally be completed before development can commence.Anglian Water has assets close to or crossing this site or there are assets subject to an adoption agreement. Therefore the site layout should take this into account and accommodate those assets within either prospectively adoptable highways or public open space. If this is not practicable then the sewers will need to be diverted at the developers cost under Section 185 of the Water Industry Act 1991. or, in the case of apparatus under an adoption agreement, liaise with the owners of the apparatus. It should be noted that the diversion works should normally be completed before development can commence. 5 )Dunstable Water Recycling Centre is included in our nutrient removal programme and will be designed to technically achievable limits (TAL). For the majority of WRCs in this programme this will be for phosphorous removal where TAL is 0.25mg/l. When both TAL and DWF capacity constraints are forecast at a WRC, either due to housing/non-domestic growth or infiltration into the network then alternative options will need to be considered. Some WRCs will be either too remote or not near another WRC with capacity. The impact of environmental pressures, including sites at technical achievable limits, and the approach required to enable future sustainable growth is something we will continue to discuss with the Environment Agency and key stakeholders, including local planning authorities. Where TAL impacts on the DWF headroom and our ability to accommodate future growth we may start objecting, if we are not doing so already, to planning applications in the impacted catchments.Dunstable Water Recycling Centre is included in our nutrient removal programme and will be designed to technically achievable limits (TAL). For the majority of WRCs in this programme this will be for phosphorous removal where TAL is 0.25mg/l. When both TAL and DWF capacity constraints are forecast at a WRC, either due to housing/non-domestic growth or infiltration into the network then alternative options will need to be considered. Some WRCs will be either too remote or not near another WRC with capacity. The impact of environmental pressures, including sites at technical achievable limits, and the approach required to enable future sustainable growth is something we will continue to discuss with the Environment Agency and key stakeholders, including local planning authorities. Where TAL impacts on the DWF headroom and our ability to accommodate future growth we may start objecting, if we are not doing so already, to planning applications in the impacted catchments.
- Decision date
- 26 May 2026
How this decision compares
Decided in 293 days from validation, 96 days slower than Central Bedfordshire's median of 197 for reserved matters. Approved, as 100% of reserved matters here are.
Plota live figures for reserved matters decided by Central Bedfordshire in the last twelve months, from validation. Central Bedfordshire decision record →
Public comments
No public comments yet.
Last counted 14 Oct 2026
Consultation & key dates
- Consultation
- 6 Aug 2025
- Comments by
- 20 May 2026
- Site or press notice
- 27 Aug 2025
Central Bedfordshire is faster than most councils at deciding householder applications, ranking #62 out of 296. Householder applications are slightly more likely to be approved here (91%) than the national average (90%).
Track this application
Phase 3B Parcels 1 & 2 ,Houghton Regis North Site 1, Land on the northern edge of Houghton Regis
Tracking this application
Not there in a minute? Check junk - especially Hotmail and Outlook.
Go to your dashboard →Sign in to view contact details
Applicant and case-officer names are hidden from public view for privacy. Create a free Plota account - or sign back in - and we'll show them, plus you get a dashboard for alerts and tracked applications.
Check your email
Referenced application